SUSTAINABLE ENERGY DEVELOPMENT AND ACCESS PROJECT

Abstract*

The objective of the Sustainable Energy Development and Access Project is to improve reliability of electricity supply, expand access to electricity, and scale up renewable energy generation. There are five components to the project, the first component being improving reliability of electricity supply in Pohnpei State. This component will address PUC’s challenges with insufficient available generation capacity, which is way below the installed capacity...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve reliability of electricity supply, expand access to electricity, and scale up renewable energy generation.

Key Details

Project Details

  • P165183

  • Active

  • Myoe Myint

  • FEDERATED STATES OF MICRONESIA

  • US$ 30.00 million

  • Department of Resources and Development (DR&D)

  • East Asia and Pacific

  • 2019

  • US$ 30.00 million

  • B

  • December 13, 2023

  • September 30, 2025

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 30.00
IBRD + IDA Commitment 30.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 30.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 6, 2018 IDA-D3970 Loan Commitment 30,000,000.00
Mar 26, 2024 IDA-D3970 Loan Disb 351,092.03
Feb 8, 2024 IDA-D3970 Loan Disb 342,671.84
Aug 23, 2024 IDA-D3970 Loan Disb 117,905.96
May 14, 2024 IDA-D3970 Loan Disb 1,068,335.90
Sep 3, 2024 IDA-D3970 Loan Disb 1,572,566.80
Jul 17, 2023 IDA-D3970 Loan Disb 184,742.56
Sep 13, 2023 IDA-D3970 Loan Disb 1,196,151.80
Mar 2, 2023 IDA-D3970 Loan Disb 209,417.42
Nov 4, 2022 IDA-D3970 Loan Disb 240,113.10
Nov 3, 2022 IDA-D3970 Loan Disb 95,357.97
Dec 15, 2021 IDA-D3970 Loan Disb -300,262.00
Feb 3, 2022 IDA-D3970 Loan Disb 300,262.00
Mar 23, 2022 IDA-D3970 Loan Disb 187,386.06
Jun 24, 2022 IDA-D3970 Loan Disb 336,143.38
Dec 2, 2021 IDA-D3970 Loan Disb 300,262.00
Sep 20, 2021 IDA-D3970 Loan Disb 132,202.81
Nov 2, 2021 IDA-D3970 Loan Disb 55,026.38
May 14, 2021 IDA-D3970 Loan Disb 107,476.73
Dec 9, 2019 IDA-D3970 Loan Disb 44,209.18
Dec 2, 2020 IDA-D3970 Loan Disb 57,497.87
Feb 4, 2021 IDA-D3970 Loan Disb 137,539.03
Aug 25, 2020 IDA-D3970 Loan Disb 133,822.19
Apr 28, 2020 IDA-D3970 Loan Disb 134,098.19
Apr 8, 2020 IDA-D3970 Loan Disb 147,552.56
Apr 9, 2020 IDA-D3970 Loan Disb 163,580.47
May 22, 2020 IDA-D3970 Loan Disb 76,758.86
Jul 11, 2019 IDA-D3970 Loan Disb 1,500,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-12-13
Procurement Moderately Satisfactory 2024-12-13
Financial Management Moderately Satisfactory 2024-12-13
Project Management Moderately Satisfactory 2024-12-13
Monitoring and Evaluation Moderately Satisfactory 2024-12-13
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-13

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People newly provided with access to electricity under the project by household connections Grid/Off-grid/mini-grid in ChuukValue0.000.001898.00
    DateNovember 30, 2018September 29, 2023September 30, 2025
    Comment
  • PUC System Average Interruption Duration Index (SAIDI)Value4000.003500.001500.00
    DateNovember 19, 2018September 29, 2023September 30, 2025
    Comment
  • Annual Generation Output of Renewable Energy (other than hydropower) in Chuuk, Yap and KosraeValue1930.001930.003500.00
    DateNovember 30, 2018September 29, 2023September 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Clean cooking assessment completedValueNoNoYes
    DateNovember 19, 2018September 29, 2023September 30, 2025
    Comment
  • Number of women in technical positions employed by power utilitiesValue0.004.004.00
    DateNovember 30, 2018September 29, 2023September 30, 2025
    Comment
  • Number of households receiving new connectionsValue0.000.00272.00
    DateNovember 30, 2018September 29, 2023September 30, 2025
    Comment
  • Number of GRM briefs published (Number)Value0.000.003.00
    DateNovember 19, 2018September 29, 2023September 30, 2025
    Comment
  • Battery Storage Capacity in KosraeValue0.000.001.00
    DateNovember 19, 2018September 29, 2023September 30, 2025
    Comment
  • Performance contract in effect for PUCValueNoNoYes
    DateNovember 30, 2018September 29, 2023September 30, 2025
    Comment
  • Generation capacity of energy constructed or rehabilitatedValue0.000.831.88
    DateNovember 30, 2018September 29, 2023September 30, 2025
    Comment
  • Generation capacity of energy constructed or rehabilitatedValue0.000.837.50
    DateNovember 30, 2018September 29, 2023September 30, 2025
    Comment
  • Thermal (conventional) power generation capacity constructed under the projectValue0.000.830.83
    DateNovember 30, 2018September 29, 2023September 30, 2025
    Comment
  • Thermal (conventional) power generation capacity constructed under the projectValue0.000.837.50
    DateNovember 30, 2018September 29, 2023September 30, 2025
    Comment
  • Renewable energy generation capacity (other than hydropower) constructed under the projectValue0.000.001.05
    DateNovember 30, 2018September 29, 2023September 30, 2025
    Comment