Financier | Commitments |
---|---|
Japan Social Development Fund | 2.85 |
P165411
Active
Nabil Samir , Gaelle Samaha
Kingdom of Morocco
October 17, 2017
(as of board presentation)
May 8, 2019
September 10, 2019
US$ 2.85 million
Regional Government of Souss-Massa,Ministry of Interior,Ministry of Equipment, Transport, Logistics and Water
2019
US$ 2.85 million
B
Not Applicable
March 31, 2026
Yes
BANK APPROVED
March 11, 2024
Financier | Commitments |
---|---|
Japan Social Development Fund | 2.85 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 2.85 |
Total Project Cost** | 2.85 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2024-07-19 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-07-19 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-07-19 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of direct beneficiaries | Value | 0.00 | 600.00 | 3000.00 |
Date | September 1, 2019 | July 10, 2023 | December 31, 2023 | |
Comment |
Average increase in income of direct beneficiaries | Value | 0.00 | 0.00 | 20.00 |
Date | September 1, 2019 | July 10, 2023 | December 31, 2023 | |
Comment |
Percentage of female direct beneficiaries | Value | 0.00 | 5.00 | 20.00 |
Date | September 1, 2019 | July 10, 2023 | December 31, 2023 | |
Comment |
Number of kilometers of rural roads maintained under the project | Value | 0.00 | 750.00 | 1000.00 |
Date | September 1, 2019 | July 10, 2023 | December 31, 2023 | |
Comment |
Percentage of subprojects that have been sustained after having benefited from financing under the project | Value | 0.00 | 0.00 | 50.00 |
Date | September 1, 2019 | July 10, 2023 | December 31, 2023 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of subprojects implemented under the project | Value | 0.00 | 32.00 | 100.00 |
Date | September 1, 2019 | July 10, 2023 | December 31, 2023 | |
Comment |
Number of workdays resulting from direct, indirect, and induced jobs generated by the project | Value | 0.00 | 50.00 | 200.00 |
Date | September 1, 2019 | July 10, 2023 | December 31, 2023 | |
Comment |
Contribution of local communities (compared to total project cost) | Value | 0.00 | 2.00 | 10.00 |
Date | September 1, 2019 | July 10, 2023 | December 31, 2023 | |
Comment |
Number of indirect beneficiaries | Value | 0.00 | 3000.00 | 50000.00 |
Date | September 1, 2019 | July 10, 2023 | December 31, 2023 | |
Comment |