Dhaka City Neighborhood Upgrading Project

Abstract*

The development objective of the Dhaka City Neighborhood Upgrading Project for Bangladesh is to enhance public spaces and improve urban services in selected neighborhoods in Dhaka. The project comprises of two components. The first component, public space enhancements consists of following sub-components: (i) neighborhood-level public space upgrading; and (ii) city-wide pilot traffic management improvements. The second component, place management...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To enhance public spaces and improve urban services in selected neighborhoods in Dhaka.

Key Details

Project Details

  • P165477

  • Active

  • Ishita Abonee , Rumana Huque

  • People’s Republic of Bangladesh

  • Bangladesh

  • January 31, 2018

  • (as of board presentation)

    March 29, 2019

  • July 1, 2019

  • US$ 106.00 million

  • Dhaka South City Corporation

  • South Asia

  • 2019

  • US$ 100.50 million

  • B

  • January 3, 2024

  • June 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 100.50
Borrower/Recipient 5.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.50
IBRD + IDA Commitment 100.50
Lending Instrument
Grant Amount N/A
Total Project Cost** 106.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 15, 2021 IDA-63610 Int Charges 41,198.07
Jul 15, 2021 IDA-63610 Int Charges 68,387.13
Dec 29, 2021 IDA-63610 Loan Disb 562,168.30
Jan 15, 2022 IDA-63610 Int Charges 273.09
Jan 15, 2022 IDA-63610 Int Charges 45,991.38
Jan 15, 2022 IDA-63610 Int Charges 45,991.38
Jan 15, 2022 IDA-63610 Int Charges 75,891.36
Jul 15, 2022 IDA-63610 Int Charges 707.63
Jul 15, 2022 IDA-63610 Int Charges 45,862.22
Jul 15, 2022 IDA-63610 Int Charges 45,862.22
Jul 15, 2022 IDA-63610 Int Charges 76,437.03
Jun 27, 2022 IDA-63610 Loan Disb 473,248.50
Feb 28, 2023 IDA-63610 Loan Disb 441,972.16
Dec 1, 2022 IDA-63610 Loan Disb 174,962.38
Sep 1, 2022 IDA-63610 Loan Disb 817,383.94
Jun 5, 2023 IDA-63610 Loan Disb 852,637.44
Jul 15, 2023 IDA-63610 Int Charges 92,372.49
Jul 27, 2023 IDA-63610 Loan Disb 1,131,819.10
Jul 15, 2023 IDA-63610 Int Charges 3,896.41
Jul 15, 2023 IDA-63610 Int Charges 57,396.64
Jul 15, 2023 IDA-63610 Int Charges 57,396.64
Jan 15, 2023 IDA-63610 Int Charges 153.81
Jan 15, 2023 IDA-63610 Int Charges 153.81
Jan 15, 2023 IDA-63610 Int Charges 53,665.53
Jan 15, 2023 IDA-63610 Int Charges 53,665.53
Jan 15, 2023 IDA-63610 Int Charges 85,820.03
Jun 5, 2024 IDA-63610 Loan Disb 854,454.06
Jun 5, 2024 IDA-63610 Loan Disb 979,903.50
Feb 27, 2024 IDA-63610 Loan Disb 838,535.30
Dec 21, 2023 IDA-63610 Loan Disb 714,307.44
Mar 28, 2024 IDA-63610 Loan Cancel 25,000,000.00
Jul 15, 2024 IDA-63610 Int Charges 70,342.58
Jul 15, 2024 IDA-63610 Int Charges 70,342.58
Jul 15, 2024 IDA-63610 Int Charges 106,677.69
Jun 27, 2024 IDA-63610 Loan Disb 1,186,403.40
Jan 15, 2024 IDA-63610 Int Charges 63,794.20
Jan 15, 2024 IDA-63610 Int Charges 63,794.20
Jan 15, 2024 IDA-63610 Int Charges 104,121.42
Jan 15, 2024 IDA-63610 Int Charges 3,243.76
Jul 15, 2024 IDA-63610 Int Charges 2,187.67
Jul 15, 2024 IDA-63610 Loan Repay 1,594,304.80
Mar 29, 2019 IDA-63610 Loan Commitment 100,500,000.00
Oct 29, 2020 IDA-63610 Loan Disb 193,568.23
Jun 25, 2020 IDA-63610 Loan Disb 115,439.81
Jun 4, 2020 IDA-63610 Loan Disb 124,274.54
Nov 19, 2019 IDA-63610 Loan Disb 9,433,962.00
Jun 21, 2021 IDA-63610 Loan Disb 700,206.75
Dec 28, 2020 IDA-63610 Loan Disb 113,574.31
Jan 15, 2021 IDA-63610 Int Charges 3,315.76
Jan 15, 2021 IDA-63610 Int Charges 38,317.26
Jan 15, 2021 IDA-63610 Int Charges 38,317.26
Jan 15, 2021 IDA-63610 Int Charges 62,249.08
Mar 24, 2021 IDA-63610 Loan Disb 554,388.70
Feb 11, 2021 IDA-63610 Loan Disb 221,306.88
Jul 15, 2020 IDA-63610 Int Charges 18,530.80
Jul 15, 2020 IDA-63610 Int Charges 35,893.86
Jul 15, 2020 IDA-63610 Int Charges 35,893.86
Jul 15, 2020 IDA-63610 Int Charges 56,622.43
Jul 15, 2020 IDA-63610 Int Charges 11,118.48
Jul 15, 2020 IDA-63610 Int Charges 11,118.48
Jun 9, 2022 IDA-63610 Loan Disb 703,899.90
May 5, 2022 IDA-63610 Loan Disb 145,968.44
Aug 31, 2021 IDA-63610 Loan Disb 464,458.75
Jun 9, 2021 IDA-63610 Loan Disb 220,705.72
Jul 15, 2021 IDA-63610 Int Charges 1,595.32
Jul 15, 2021 IDA-63610 Int Charges 41,198.07

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2024-12-24
Monitoring and Evaluation Moderately Satisfactory 2024-12-24
Project Management Satisfactory 2024-12-24
Procurement Moderately Unsatisfactory 2024-12-24
Progress towards achievement of PDO Satisfactory 2024-12-24
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-24

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage increase in the number of people accessing enhanced public spacesValue0.0015.0020.00
    DateJune 30, 2019November 30, 2023June 30, 2024
    Comment
  • People provided with improved urban living conditionsValue0.00103685.001000000.00
    DateJune 30, 2019November 30, 2023June 30, 2024
    Comment
  • Percentage increase in the number of women accessing enhanced public spacesValue0.0016.0020.00
    DateJune 30, 2019November 30, 2023June 30, 2024
    Comment
  • Percentage increase in the number of women accessing enhanced public spacesValue0.0016.0020.00
    DateJune 30, 2019November 30, 2023June 30, 2024
    Comment
  • People provided with improved urban living conditions - Female (RMS requirement)Value0.000.00500000.00
    DateOctober 31, 2018October 31, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Total area of public spaces improvedValue0.000.0030.00
    DateJune 30, 2019March 30, 2023June 30, 2024
    Comment
  • Share of improved public spaces with approved plans for operation, management, programming and community outreachValue0.000.00100.00
    DateJuly 2, 2018November 30, 2023June 30, 2024
    Comment
  • Number of people consulted under participatory sessions for subproject design and implementationValue0.003707.001200.00
    DateJune 30, 2019November 30, 2023June 30, 2024
    Comment
  • Percentage of citizens in selected neighborhoods who consider that their views have been taken into account in the subproject designsValue0.0035.0060.00
    DateJune 30, 2019November 30, 2023June 30, 2024
    Comment
  • Percentage of women in selected neighborhoods who consider that their views have been taken into account in the subproject designsValue0.0020.0060.00
    DateJune 30, 2019November 30, 2023June 30, 2024
    Comment
  • Percentage of women who report feeling safe in public spaces in the selected neighborhood locationsValue0.000.0060.00
    DateJune 30, 2019November 30, 2023June 30, 2024
    Comment
  • Roads rehablitatedValue0.001.3330.00
    DateJune 30, 2019November 30, 2023June 30, 2024
    Comment
  • Number of intersection management strategies developedValue0.0010.005.00
    DateJune 30, 2019November 30, 2023June 30, 2024
    Comment