Tanzania Transport Integration Project

Abstract*

The development objectives of Transport Integration Project for Tanzania are to improve the safety, climate resilience and capacity of key road corridors and regional airports, and improve the capacity of relevant transport sector institutions to plan for and manage the sector. This project has four components. 1) The first component, Upgrading and Rehabilitation of Trunk and Regional Roads, will finance the upgrading and rehabilitation works of about...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objectives of the Project are to improve the safety, climate resilience and capacity of key road corridors and regional airports, and improve the capacity of relevant transport sector institutions to plan for and manage the sector.

Key Details

Project Details

  • P165660

  • Active

  • Nana Soetantri , Aymen Ali

  • United Republic of Tanzania

  • Tanzania

  • April 16, 2018

  • (as of board presentation)

    May 24, 2022

  • January 18, 2023

  • US$ 647.11 million

  • Tanzania National Roads Agency (TANROADS)

  • Eastern and Southern Africa

  • 2022

  • US$ 550.00 million

  • N/A

  • March 14, 2024

  • September 30, 2027

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 550.00
Borrower/Recipient 97.11

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 550.00
IBRD + IDA Commitment 550.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 647.11

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 24, 2022 IDA-71170 Loan Commitment 550,000,000.00
Mar 6, 2024 IDA-71170 Loan Disb 80,000,000.00
Apr 20, 2023 IDA-71170 Loan Disb 7,895,059.00
Mar 27, 2023 IDA-71170 Loan Disb 13,690,000.00
Jul 15, 2023 IDA-71170 Int Charges 48,005.43
Jul 15, 2023 IDA-71170 Int Charges 48,005.43
Jan 15, 2024 IDA-71170 Int Charges 87,025.63
Jan 15, 2024 IDA-71170 Int Charges 87,025.63
Jan 15, 2024 IDA-71170 Int Charges 417.90
Jan 15, 2024 IDA-71170 Int Charges 417.90
Jul 19, 2024 IDA-71170 Int Charges 634.61
Jul 19, 2024 IDA-71170 Int Charges 634.61
Jul 19, 2024 IDA-71170 Int Charges 300,780.97
Jul 19, 2024 IDA-71170 Int Charges 300,780.97
Apr 24, 2023 IDA-71170 Loan Disb 1,943,426.40

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2024-10-02
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-02
Procurement Moderately Satisfactory 2024-10-02
Project Management Satisfactory 2024-10-02
Monitoring and Evaluation Moderately Satisfactory 2024-10-02
Progress towards achievement of PDO Satisfactory 2024-10-02

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average travel time along project corridors - Mtwara-Mingoyo-MasasiValue5.205.203.50
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Web-based Road Asset Management System fully operationalizedValueNoNoYes
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Average travel time along project corridors - Lusahunga-RusumoValue3.103.102.50
    DateJuly 1, 2022March 7, 2024June 30, 2027
    Comment
  • Road Accident Information System operationalizedValueNoNoYes
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Average travel time along project corridors - Songea-RutukilaValue2.502.501.80
    DateJuly 1, 2022March 7, 2024June 30, 2027
    Comment
  • Procedures and manuals for incorporation of climate resilience in design of road projects are operationalizedValueNoNoYes
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Average travel time along project corridors - Iringa-MsembeValue3.003.001.50
    DateJuly 1, 2022March 7, 2024June 30, 2027
    Comment
  • Female engineering students recruited in a technical internship program in TANROADSValue0.008.00250.00
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Annual fatalities due to road crashes on project roadsValueTo be confirmedNot AvailableTo be confirmed
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Annual closures of road sections due to weather related eventsValue4.004.000.00
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Emergency response time at project airportsValueTo be confirmedData Not AvailableTo be confirmed
    DateDecember 19, 2023December 8, 2022June 30, 2027
    Comment
  • Emergency response time - Lake Manyara AirportValueTo be determinedData not yet available
    Date
    Comment
  • Emergency response time - Tanga AirportValueTo be determinedData not yet available
    Date
    Comment
  • Emergency response time - Iringa AirportValueTo be determinedData not yet available
    Date
    Comment
  • People with enhanced access to transportation servicesValue27000.000.00717000.00
    DateApril 29, 2022March 7, 2024September 29, 2027
    Comment
  • People with enhanced access to transportation services - Roads/HighwaysValue0.000.00637000.00
    DateApril 29, 2022March 7, 2024September 29, 2027
    Comment
  • People with enhanced access to transportation services – AviationValue27000.000.0080000.00
    DateApril 29, 2022March 7, 2024September 29, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Vehicle operating costs on Iringa-Msembe corridor - TrucksValue1.451.450.00
    Date
    Comment
  • Length of road upgraded with climate resilience measuresValue0.000.00509.50
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • People with enhanced access to transportation servicesValue0.000.00637000.00
    DateApril 29, 2022March 7, 2024September 29, 2027
    Comment
  • People with enhanced access to transportation services - Roads/HighwaysValue0.000.00637000.00
    DateMay 24, 2022March 7, 2024September 29, 2027
    Comment
  • Roads constructedValue0.000.00509.50
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Airports with runway, apron, and taxiway constructed to paved standard with climate resilient measuresValue0.000.003.00
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Young graduates recruited and embedded in project activitiesValue0.0059.0045.00
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Vehicle operating costs on Mtwara-Mingoyo-Masasi corridorValue0.550.550.41
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Percentage of embedded graduates which are hired by TANROADSValue0.000.000.00
    Date
    Comment
  • Lake Manyara Airport ICAO aerodrome reference codeValueCode B Unpaved/GravelNot yet started
    Date
    Comment
  • Vehicle operating costs on Mtwara-Mingoyo-Masasi corridor - CarsValue0.230.230.00
    Date
    Comment
  • Percentage of embedded graduates hired by TANROADS which are womenValue0.000.000.00
    Date
    Comment
  • Tanga Airport ICAO aerodrome reference codeValueCode C*/deteriorated tarmacNot yet started
    Date
    Comment
  • Vehicle operating costs on Mtwara-Mingoyo-Masasi corridor - TrucksValue0.810.810.00
    Date
    Comment
  • Number of professional staff trained in collaboration with local universitiesValue0.000.00200.00
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Terminal buildings construction completed which meet an Optimized IATA Level of ServiceValue0.000.003.00
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Airports with improved navigation aidsValue0.000.002.00
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Vehicle operating costs on Lusahunga-Rusumo corridorValue0.600.600.45
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Number of TANROADS staff receiving post graduate degrees financed by the projectValue0.000.000.00
    Date
    Comment
  • Establishment of Contract Management System in TANROADSValueNoNoYes
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Airports with improved safety and security features, including security fences and fire tendersValue0.000.003.00
    DateJuly 1, 2022March 7, 2024June 30, 2027
    Comment
  • Vehicle operating costs on Lusahunga-Rusumo corridor - CarsValue0.240.240.00
    Date
    Comment
  • People with enhanced access to transportation servicesValue27000.000.0080000.00
    DateApril 29, 2022March 7, 2024September 29, 2027
    Comment
  • Number of consultations with project affected persons as per the SEP and included in quarterly reportsValue0Not yet startedAs per the SEP
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Vehicle operating costs on Lusahunga-Rusumo corridor - TrucksValue0.880.880.00
    Date
    Comment
  • Percentage of project grievance satisfactorily resolved within 4 weeks of initial complaint/submission being recordedValue0.000.0090.00
    DateJuly 1, 2022March 7, 2024June 30, 2027
    Comment
  • Vehicle operating costs on Songea-Rutukila corridorValue0.520.520.39
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Vehicle operating costs on Songea-Rutukila corridor - CarsValue0.180.180.00
    Date
    Comment
  • Vehicle operating costs on Songea-Rutukila corridor - TrucksValue0.970.970.00
    Date
    Comment
  • Vehicle operating costs on Iringa-Msembe corridorValue0.910.910.68
    DateJuly 1, 2022March 7, 2024July 1, 2027
    Comment
  • Vehicle operating costs on Iringa-Msembe corridor - CarsValue0.350.350.00
    Date
    Comment
  • People with enhanced access to transportation services – AviationValue27000.000.0080000.00
    DateApril 29, 2022March 7, 2024September 29, 2027
    Comment