Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 233.60 |
Borrowing Agency | 6.00 |
P165716
Active
Zael Sanz Uriarte , Iris Marmanillo
Municipality of Guayaquil
April 13, 2018
(as of board presentation)
June 29, 2018
N/A
US$ 239.60 million
EMAPAG-EP
2018
US$ 233.60 million
A
October 10, 2023
April 30, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 233.60 |
Borrowing Agency | 6.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 233.60 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 233.60 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 239.60 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Volume(mass) of BOD pollution load removed by treatment plant under the project | Value | 0.00 | 0.00 | 14000.00 |
Date | September 15, 2015 | September 15, 2017 | April 28, 2023 | |
Comment |
Water & sanitation utility operating ratio | Value | 0.90 | 0.90 | 0.90 |
Date | September 15, 2015 | November 14, 2018 | April 28, 2023 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 24000.00 | 1900000.00 |
Date | September 15, 2015 | November 14, 2018 | April 28, 2023 | |
Comment |
People in urban areas provided with access to improved sanitation services under the project | Value | 0.00 | 15288.00 | 169800.00 |
Date | September 15, 2015 | November 14, 2018 | April 28, 2023 | |
Comment |
Female beneficiaries | Value | 0.00 | 50.00 | 50.00 |
Date | September 15, 2015 | September 15, 2017 | April 28, 2023 | |
Comment |
Share of poor people in urban areas provided with access to improved sanitation services under the project | Value | 0.00 | 0.00 | 20.00 |
Date | September 15, 2015 | September 15, 2017 | April 28, 2023 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduction of the average wastewater flow pumped in the “La Chala” pump station | Value | 0.00 | 25.00 | |
Date | September 15, 2015 | December 31, 2019 | ||
Comment |
Reduction of the annually reported repair tickets in the La Chala sector sewer main system | Value | 0.00 | 0.00 | 50.00 |
Date | September 15, 2015 | November 14, 2018 | December 31, 2019 | |
Comment |
Meters of sewers mains rehabilitated under the project | Value | 0.00 | 16800.00 | 40000.00 |
Date | September 15, 2015 | November 14, 2018 | December 31, 2019 | |
Comment |
New household sewer connections constructed under the project | Value | 0.00 | 7075.00 | 35400.00 |
Date | September 15, 2015 | November 14, 2018 | April 28, 2023 | |
Comment |
Start of Construction of Las Esclusas WWTP | Value | No | Yes | Yes |
Date | September 15, 2015 | November 14, 2018 | December 31, 2016 | |
Comment |
Commissioning of Las Esclusas WWTP | Value | No | No | Yes |
Date | September 15, 2015 | November 14, 2018 | March 31, 2020 | |
Comment |
Share of the monthly average effluent from Las Esclusas WWTP outlet discharged into the Guayas River is compliant with regulatory quality standard for BDO, TSS and total coliforms | Value | 0.00 | 0.00 | 100.00 |
Date | September 15, 2015 | November 14, 2018 | December 31, 2019 | |
Comment |
Water quality Monitoring System for the Daule and Guayas River finalized and system operational | Value | No | No | Yes |
Date | September 15, 2015 | November 14, 2018 | November 30, 2021 | |
Comment |
Water Quality Monitoring System for the Estero Salado Estuary | Value | No | No | Yes |
Date | September 15, 2015 | September 15, 2017 | November 30, 2021 | |
Comment |
Master plan for the Management and Final Disposal or Reutilization of Bio-solids from WWTP finalized | Value | No | Yes | |
Date | September 15, 2015 | December 31, 2019 | ||
Comment |
Citizen Engagement: Number of beneficiary households that sign a certification that they are satisfied with the works conducted in their houses. | Value | 0.00 | 4900.00 | 34075.00 |
Date | September 15, 2015 | September 15, 2017 | December 31, 2019 | |
Comment |
People trained to improve hygiene behavior/sanitation practices under the proj | Value | 0.00 | 22500.00 | |
Date | September 15, 2015 | December 31, 2019 | ||
Comment |
Share of surveyed beneficiaries (gender disaggregated) that feel project investments reflect their needs | Value | 0.00 | 0.00 | 85.00 |
Date | September 15, 2015 | September 15, 2017 | April 3, 2023 | |
Comment |
People trained to improve hygiene behavior/sanitation practices - female | Value | 0.00 | 18000.00 | |
Date | September 15, 2015 | April 28, 2023 | ||
Comment |
Start of Construction of Los Merinos WWTP | Value | No | No | Yes |
Date | February 14, 2018 | November 14, 2018 | June 7, 2019 | |
Comment |
Commissioning of Los Merinos WWTP | Value | No | No | Yes |
Date | February 14, 2018 | November 14, 2018 | December 30, 2022 | |
Comment |
Share of the monthly average effluent from Los Merinos WWTP outlet discharged into the Daule River is compliant with regulatory quality standard for BDO, TSS and total coliforms | Value | 0.00 | 0.00 | 100.00 |
Date | February 14, 2018 | November 14, 2018 | April 28, 2023 | |
Comment |
Percentage of Component 1 social mobilization team members that are women | Value | 0.00 | 0.00 | 80.00 |
Date | February 21, 2018 | November 14, 2018 | March 31, 2023 | |
Comment |
The Los Merinos WWTP Forest Compensation Plan has being developed and approved by National Environmental Authorities | Value | No | No | Yes |
Date | April 30, 2018 | November 14, 2018 | February 28, 2019 | |
Comment |