Financier | Commitments |
---|---|
IDA Grant | 25.00 |
P165855
Active
Senakpon Dakpogan
Ministre de l’Economie, du Plan et de la Coopération
February 18, 2019
(as of board presentation)
May 17, 2019
September 30, 2019
US$ 25.00 million
Ministry of Agriculture and Rural Development
2019
US$ 25.00 million
B
February 22, 2024
December 30, 2025
TBD
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 25.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 25.00 |
IBRD + IDA Commitment | 25.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 25.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 17, 2022 | IDA-D4610 | Loan Disb | 691,624.00 |
Feb 17, 2022 | IDA-D4610 | Loan Disb | 576,731.25 |
Dec 29, 2021 | IDA-D4610 | Loan Disb | 113,553.94 |
Dec 22, 2021 | IDA-D4610 | Loan Disb | 248,108.14 |
Apr 11, 2022 | IDA-D4610 | Loan Disb | 39,312.17 |
Dec 30, 2021 | IDA-D4610 | Loan Disb | 4,123,769.00 |
Feb 6, 2023 | IDA-D4610 | Loan Disb | 129,555.01 |
Feb 6, 2023 | IDA-D4610 | Loan Disb | 208,978.62 |
Nov 16, 2022 | IDA-D4610 | Loan Disb | 92,886.50 |
Nov 16, 2022 | IDA-D4610 | Loan Disb | 102,279.21 |
Nov 16, 2022 | IDA-D4610 | Loan Disb | 128,110.29 |
Nov 16, 2022 | IDA-D4610 | Loan Disb | 206,405.48 |
Feb 15, 2023 | IDA-D4610 | Loan Disb | 109,878.14 |
Aug 1, 2023 | IDA-D4610 | Loan Disb | 512,524.30 |
May 17, 2019 | IDA-D4610 | Loan Commitment | 25,000,000.00 |
Mar 21, 2023 | IDA-D4610 | Loan Disb | 203,363.17 |
Sep 28, 2023 | IDA-D4610 | Loan Disb | -407,664.80 |
Aug 29, 2024 | IDA-D4610 | Loan Disb | 29,890.10 |
Aug 30, 2024 | IDA-D4610 | Loan Disb | 46,099.27 |
Sep 28, 2023 | IDA-D4610 | Loan Disb | 406,807.00 |
Aug 29, 2024 | IDA-D4610 | Loan Disb | 28,902.81 |
Aug 29, 2024 | IDA-D4610 | Loan Disb | 37,029.36 |
Aug 29, 2024 | IDA-D4610 | Loan Disb | 26,657.34 |
Sep 28, 2023 | IDA-D4610 | Loan Disb | -406,807.00 |
Sep 28, 2023 | IDA-D4610 | Loan Disb | 406,807.00 |
Oct 6, 2023 | IDA-D4610 | Loan Disb | 1,236,122.00 |
Nov 9, 2023 | IDA-D4610 | Loan Disb | 920,829.00 |
Jun 20, 2024 | IDA-D4610 | Loan Disb | 63,692.45 |
Jun 11, 2024 | IDA-D4610 | Loan Disb | 16,661.11 |
Jun 11, 2024 | IDA-D4610 | Loan Disb | 325,500.94 |
Sep 30, 2019 | IDA-D4610 | Loan Disb | 2,000,000.00 |
Jun 24, 2020 | IDA-D4610 | Loan Disb | 291,518.30 |
Apr 30, 2020 | IDA-D4610 | Loan Disb | 102,221.20 |
Mar 31, 2020 | IDA-D4610 | Loan Disb | 1,576,254.90 |
Oct 16, 2020 | IDA-D4610 | Loan Disb | 2,140,109.00 |
Oct 28, 2020 | IDA-D4610 | Loan Disb | 53,144.06 |
Jul 23, 2020 | IDA-D4610 | Loan Disb | 96,014.74 |
Sep 1, 2020 | IDA-D4610 | Loan Disb | 201,372.20 |
Dec 7, 2020 | IDA-D4610 | Loan Disb | 256,967.90 |
Mar 3, 2021 | IDA-D4610 | Loan Disb | 187,882.34 |
Sep 16, 2020 | IDA-D4610 | Loan Disb | 64,191.76 |
Feb 4, 2021 | IDA-D4610 | Loan Disb | 99,010.03 |
Mar 16, 2021 | IDA-D4610 | Loan Disb | 57,907.11 |
Feb 4, 2021 | IDA-D4610 | Loan Disb | 84,172.89 |
Jul 29, 2021 | IDA-D4610 | Loan Disb | 441,612.16 |
May 28, 2021 | IDA-D4610 | Loan Disb | 177,040.48 |
Jul 29, 2021 | IDA-D4610 | Loan Disb | 247,509.06 |
Apr 20, 2021 | IDA-D4610 | Loan Disb | 581,653.30 |
Nov 15, 2021 | IDA-D4610 | Loan Disb | 211,425.94 |
Nov 17, 2021 | IDA-D4610 | Loan Disb | 208,834.67 |
Oct 6, 2021 | IDA-D4610 | Loan Disb | 93,412.06 |
Jul 11, 2022 | IDA-D4610 | Loan Disb | 107,715.78 |
Jul 11, 2022 | IDA-D4610 | Loan Disb | 590,612.50 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Satisfactory | 2025-03-05 |
Monitoring and Evaluation | Moderately Satisfactory | 2025-03-05 |
Procurement | Moderately Satisfactory | 2025-03-05 |
Project Management | Moderately Satisfactory | 2025-03-05 |
Progress towards achievement of PDO | Satisfactory | 2025-03-05 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-03-05 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries, of which female and youth beneficiaries | Value | 0.00 | 100791.00 | 20000.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Increase in sales turnover among MSMEs supported by the Project | Value | 0.00 | 121.00 | 35.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2025 | |
Comment |
Women | Value | 0.00 | 43067.00 | 8000.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Youth (18-30 years) | Value | 0.00 | 3329.00 | 6000.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Yields per hectare of selected indicative crops, changes in yield (tracked by gender) | Value | 0.00 | 100.00 | 50.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Male farmers | Value | 100.00 | 100.00 | 50.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Female farmers | Value | 0.00 | 100.00 | 50.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Reduction in mortality rate of small stock and chickens | Value | 0.00 | 65.00 | 50.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Farmers reached with agricultural assets or services | Value | 0.00 | 100791.00 | 20000.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Roads rehablitated | Value | 0.00 | 45.00 | 45.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Quantity of improved seeds cerified (Base seed R1, kg) | Value | 0.00 | 73295.00 | 50000.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Crisis Information Alert System and a crisis response framework approved and put in place | Value | No | No | Yes |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Rural roads maintained | Value | 0.00 | 87.00 | 300.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Climate Smart Technology packages disseminated in the project zone | Value | 0.00 | 3.00 | 5.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Farmers reached with agricultural assets or services - Female | Value | 0.00 | 0.00 | 2100.00 |
Date | ||||
Comment |
Number of producer groups/cooperatives supported | Value | 0.00 | 132.00 | 600.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Rural logistics and commercialization infrastructure rehabilitated (markets, storage, sales points, etc.) | Value | 0.00 | 5.00 | 3.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Beneficiary satisfaction rate with quality of services provided by the project | Value | 0.00 | 80.50 | 80.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Reduction in mortality rate of small stock and chickens | Value | 0.00 | 65.00 | 50.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Number of women producer groups | Value | 0.00 | 101.00 | 300.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2024 | |
Comment |
Community managed productive infrastructure realized | Value | 0.00 | 102.00 | 160.00 |
Date | June 30, 2019 | February 19, 2024 | June 30, 2025 | |
Comment |
Number of micro, small, and medium enterprises co-financed | Value | 0.00 | 19.00 | 50.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2025 | |
Comment |
Women | Value | 0.00 | 3.00 | 20.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2025 | |
Comment |
Youth (18-30 years) | Value | 0.00 | 2.00 | 16.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2025 | |
Comment |
Productive business linkages established and sustained over one year | Value | 0.00 | 27.00 | 10.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2025 | |
Comment |
Number of jobs created through Matching Grants | Value | 0.00 | 197.00 | 600.00 |
Date | June 30, 2019 | February 19, 2024 | May 30, 2025 | |
Comment |