Enhanced Road Access Project Additional Financing

Development Objective

To restore key road sector assets damaged by extreme weather events and enhance the climate resilience of critical roads and bridges in Samoa.

Key Details

Project Details

  • P165943

  • Closed

  • Sean Michaels

  • Ministry of Finance

  • Samoa

  • February 5, 2018

  • (as of board presentation)

    May 31, 2018

  • N/A

  • US$ 3.36 million

  • Land Transport Authority

  • East Asia and Pacific

  • 2018

  • US$ 3.36 million

  • B

  • July 15, 2021

  • October 31, 2022

  • Yes

  • BANK APPROVED

  • P145545

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Australia-Pacific Islands Partnership Trust Fund 3.36

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 3.36
Total Project Cost** 3.36

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads rehabilitated, Non-ruralValue0.002.3010.00
    DateOctober 17, 2013November 7, 2017April 30, 2019
    Comment
  • 2. Bridges rehabilitated to improved standards.Value0.001.006.00
    DateOctober 17, 2013November 7, 2017April 30, 2019
    Comment
  • 3. Reduction in disruptions in traffic flows at targeted locations.Value4.002.000.00
    DateOctober 17, 2013August 7, 2017April 30, 2019
    Comment
  • 4. Instances when project designs are informed by access audits.Value0.004.007.00
    DateOctober 17, 2013August 7, 2017April 30, 2019
    Comment
  • Improved connectivity through rehabilitation or construction of roads to improved standardsValue2.302.303.90
    DateNovember 7, 2017November 7, 2017April 30, 2019
    Comment
  • Improved connectivity through rehabilitation or replacement of water crossings to improved standardsValue1.001.003.00
    DateNovember 7, 2017November 7, 2017April 30, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Agreement on key roads for reconstruction.Value0.002.005.00
    DateOctober 17, 2013November 7, 2017April 30, 2019
    Comment
  • Identification of specific bridges to be improved.Value0.002.006.00
    DateOctober 17, 2013November 7, 2017April 30, 2019
    Comment
  • Roads constructedValue2.302.302.30
    DateNovember 7, 2017November 7, 2017April 30, 2019
    Comment
  • Roads rehablitatedValue0.000.001.60
    DateNovember 7, 2017November 7, 2017April 30, 2019
    Comment
  • Water crossings replaced or rehabilitatedValue1.001.003.00
    DateNovember 7, 2017November 7, 2017April 30, 2019
    Comment
  • Targeted locations where traffic flows will have reduced disruptionsValue3.003.004.00
    DateNovember 7, 2017November 7, 2017April 30, 2019
    Comment
  • Instances when project designs are informed by access auditsValue4.004.005.00
    DateNovember 7, 2017November 7, 2017April 30, 2019
    Comment
  • Grievances registered related to delivery of project benefits that are addressedValue100.00100.00100.00
    DateNovember 7, 2017November 7, 2017April 30, 2019
    Comment
  • Number of gender responsive design featuresValue5.005.005.00
    DateNovember 7, 2017November 7, 2017April 30, 2019
    Comment