The development objective of Livestock Commercialization Project for Mongolia is to improve livestock health, productivity, and commercialization of targeted value chains in project locations and to provide immediate and effective response in the event of an eligible crisis or emergency. This project has four components. 1) The first component, Animal Health Services, aims to improve the quality of and access to veterinary services nationally and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve livestock health, productivity, and commercialization of targeted value chains in project locations and to provide immediate and effective response in the event of an eligible crisis or emergency.

Key Details

Project Details

  • P165945

  • Active

  • Sitaramachandra Machiraju

  • Ministry of Finance

  • Mongolia

  • October 23, 2019

  • (as of board presentation)

    December 13, 2019

  • June 2, 2020

  • US$ 38.00 million

  • Ministry of Food Agriculture and Light Industry, Government of Mongolia

  • East Asia and Pacific

  • 2020

  • US$ 30.00 million

  • B

  • May 27, 2024

  • June 30, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 30.00
Local Beneficiaries 2.00
Borrowing Agency 6.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 30.00
IBRD + IDA Commitment 30.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 38.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 9, 2021 IDA-65080 Int Charges 10,011.56
Mar 9, 2021 IDA-65080 Int Charges 10,011.56
Mar 9, 2021 IDA-65080 Int Charges 2,839.43
Mar 9, 2021 IDA-65080 Int Charges 16,685.94
Mar 12, 2021 IDA-65080 Loan Disb 239,646.25
Mar 11, 2021 IDA-65080 Loan Disb 2,000,000.00
Mar 11, 2021 IDA-65080 Loan Disb 19,229.01
Mar 18, 2022 IDA-65080 Loan Disb 3,000,000.00
Aug 15, 2021 IDA-65080 Int Charges 229.12
Aug 15, 2021 IDA-65080 Int Charges 229.12
Aug 15, 2021 IDA-65080 Int Charges 36,689.66
Aug 15, 2021 IDA-65080 Int Charges 36,689.66
Aug 15, 2021 IDA-65080 Int Charges 61,531.29
Aug 15, 2022 IDA-65080 Int Charges 105,795.88
Feb 15, 2022 IDA-65080 Int Charges 612.70
Feb 15, 2022 IDA-65080 Int Charges 96,236.92
Feb 15, 2022 IDA-65080 Int Charges 612.70
Dec 13, 2019 IDA-65080 Loan Commitment 30,000,000.00
Aug 15, 2022 IDA-65080 Int Charges 63,477.52
Aug 15, 2022 IDA-65080 Int Charges 447.72
Feb 15, 2022 IDA-65080 Int Charges 57,414.44
Aug 15, 2022 IDA-65080 Int Charges 63,477.52
Jun 14, 2023 IDA-65080 Loan Disb 1,364,940.00
Aug 15, 2023 IDA-65080 Int Charges 69,338.97
Aug 15, 2023 IDA-65080 Int Charges 69,338.97
Aug 15, 2023 IDA-65080 Int Charges 115,564.93
Aug 15, 2023 IDA-65080 Int Charges 865.16
Feb 15, 2023 IDA-65080 Int Charges 64,822.15
Feb 15, 2023 IDA-65080 Int Charges 64,822.15
Feb 15, 2023 IDA-65080 Int Charges 109,617.16
Feb 15, 2023 IDA-65080 Int Charges 1,469.21
Feb 15, 2023 IDA-65080 Int Charges 1,469.21
Jun 26, 2024 IDA-65080 Loan Disb 1,102,015.60
Aug 15, 2024 IDA-65080 Int Charges 75,389.76
Aug 15, 2024 IDA-65080 Int Charges 75,389.76
Aug 15, 2024 IDA-65080 Int Charges 2,694.21
Aug 15, 2024 IDA-65080 Int Charges 2,694.21
Aug 15, 2024 IDA-65080 Int Charges 123,873.72
May 30, 2023 IDA-65080 Loan Disb 1,000,000.00
May 21, 2024 IDA-65080 Loan Disb 950,000.00
Feb 15, 2024 IDA-65080 Int Charges 123,955.46
Feb 15, 2024 IDA-65080 Int Charges 74,055.37
Feb 15, 2024 IDA-65080 Int Charges 74,055.37
Feb 15, 2024 IDA-65080 Int Charges 317.91
Feb 15, 2024 IDA-65080 Int Charges 317.91
Feb 15, 2022 IDA-65080 Int Charges 57,414.44
Mar 3, 2021 IDA-65080 Loan Disb 625,319.75
Jul 6, 2020 IDA-65080 Loan Disb 1,600,000.00
Jul 6, 2020 IDA-65080 Loan Disb 1,000,000.00
Jul 28, 2020 IDA-65080 Loan Disb 1,000,000.00
Jul 6, 2020 IDA-65080 Loan Disb -1,000,000.00
May 27, 2021 IDA-65080 Loan Disb 6,400,000.00
Jun 22, 2021 IDA-65080 Loan Disb 232,880.05
May 26, 2021 IDA-65080 Loan Disb 2,400,344.50
Apr 2, 2021 IDA-65080 Loan Disb 608,521.30
Apr 20, 2021 IDA-65080 Loan Disb 689,796.25
Mar 9, 2021 IDA-65080 Int Charges 1,703.68
Mar 9, 2021 IDA-65080 Int Charges 1,703.68

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2024-12-16
Overall Safeguards Rating Satisfactory 2024-12-16
Progress towards achievement of PDO Moderately Satisfactory 2024-12-16
Financial Management Moderately Satisfactory 2024-12-16
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-16
Procurement Satisfactory 2024-12-16
Monitoring and Evaluation Satisfactory 2024-12-16

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Mutton carcassValue0.000.0020.00
    DateJuly 31, 2020March 31, 2023June 30, 2025
    Comment
  • Cow milkValue0.000.0020.00
    DateJuly 31, 2020March 31, 2023June 30, 2025
    Comment
  • Increased yield of livestock products (meat and diary)Value0.000.0010.00
    DateJuly 31, 2020March 31, 2023June 30, 2025
    Comment
  • Reduced prevalence of priority diseases in project intervention areasValue0.000.0010.00
    DateJuly 31, 2020May 31, 2022June 30, 2025
    Comment
  • Increase in live animal weight of small ruminants (sheep)Value0.000.000.00
    Date
    Comment
  • Increase in live animal weight of small ruminants (goat)Value0.000.000.00
    Date
    Comment
  • Increase in milk outputValue0.000.000.00
    Date
    Comment
  • Increased inflation-adjusted value of livestock productsValue0.000.0020.00
    DateJuly 31, 2020March 31, 2023June 30, 2025
    Comment
  • Beef carcassesValue0.000.0020.00
    DateJuly 31, 2020March 31, 2023June 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of veterinarian and veterinary paraprofessionals trainedValue0.002575.00500.00
    DateJuly 31, 2020March 31, 2024June 30, 2025
    Comment
  • Farmers reached with agricultural assets or servicesValue0.0057016.0020000.00
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • Number of herders participating in trainingValue0.009032.0010000.00
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • Adoption of improved post disaster impact assessment practices and procedures, as reflected in the improved quality and comprehensiveness of assessmentsValueNoYesYes
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • of which are female beneficialriesValue0.000.000.00
    Date
    Comment
  • Farmers reached with agricultural assets or services - FemaleValue0.000.000.00
    Date
    Comment
  • Number of veterinarian and veterinary professionals trained - FemaleValue0.001250.00200.00
    DateJuly 31, 2020March 31, 2024June 30, 2025
    Comment
  • Total number of beneficiaries benefiting from emergency response and recovery activitiesValue0.00180801.00180000.00
    DateJuly 31, 2020June 30, 2023June 30, 2025
    Comment
  • Increased coverage of quality animal health services in the project intervention areasValue0.004578.0010000.00
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • At at least 50 percent women are hired for all ‘Project’ funded professional positionsValue0.0050.0050.00
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • Adoption and implementation of resilience measures to avert/mitigate future disastersValueNoYesYes
    DateApril 30, 2021March 29, 2024June 30, 2025
    Comment
  • Number of veterinary laboratories accredited to national or international standardsValue0.002.002.00
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • Grievances registered related to delivery of project benefits addressedValue0.00100.00100.00
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • Productive Partnerships established and functioningValue0.0016.008.00
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • Number of beneficiaries of the immediate dzud response (fodder distribution)Value0.0046470.0045570.00
    DateJuly 30, 2020March 29, 2024June 30, 2025
    Comment
  • Time between sampling of animals and final test results, in case of surveillance for priority animal diseasesValue4 months or more15 days2 months max
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • of which are women led or women owned enterprisesValue0.000.000.00
    Date
    Comment
  • Citizen’s feedback received via ICT applications on services provided by ProjectValuen/aSatisfactorySatisfactory
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • Number of herder households benefitting from the second-layer support (cash assistance)Value0.00179849.00180000.00
    DateApril 30, 2021March 29, 2024June 30, 2025
    Comment
  • Number of local government officials and herders participating in simulation exercises (disaster preparadness)Value0.00952.00750.00
    DateApril 30, 2021March 29, 2024June 30, 2025
    Comment
  • Innovative solutions on animal health, nutrition, and breeding contractedValue0.0025.0015.00
    DateApril 30, 2021March 29, 2024June 30, 2025
    Comment
  • Number of veterinary professionals populated in the Human-resource management systemValue200.003067.001500.00
    DateJuly 30, 2020March 29, 2024June 30, 2025
    Comment
  • Primary producers (herders) mobilized and benefited through productive partnershipsValue0.001514.002000.00
    DateJune 30, 2023March 29, 2024June 30, 2025
    Comment
  • Share of animal products marketed through commercial channelsValue0.000.0020.00
    DateJuly 31, 2020March 29, 2024June 30, 2025
    Comment
  • Frequency of analysis of veterinary certificates issued for transport of livestock out of Soum by species, place of origin, place of destinationValue0weeklyMonthly
    DateApril 30, 2021March 29, 2024June 30, 2025
    Comment