Financier | Commitments |
---|---|
IDA Grant | 75.00 |
P166100
Active
Sara Troiano
Republic of Mozambique
July 20, 2018
(as of board presentation)
February 14, 2020
May 21, 2020
US$ 75.00 million
Secretária do Estado da Juventude e Emprego (SEJE)
2020
US$ 75.00 million
C
Not Applicable
June 30, 2025
No
BANK APPROVED
February 15, 2024
Financier | Commitments |
---|---|
IDA Grant | 75.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 75.00 |
IBRD + IDA Commitment | 75.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 75.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 1, 2021 | IDA-D5550 | Loan Disb | 231,286.69 |
Jul 1, 2021 | IDA-D5550 | Loan Disb | 194,008.70 |
Jan 20, 2023 | IDA-D5550 | Loan Disb | 465,000.40 |
Dec 8, 2022 | IDA-D5550 | Loan Disb | 572,439.44 |
Nov 29, 2022 | IDA-D5550 | Loan Disb | 498,755.10 |
Nov 21, 2022 | IDA-D5550 | Loan Disb | 984,280.90 |
Oct 19, 2022 | IDA-D5550 | Loan Disb | 755,831.30 |
Oct 11, 2022 | IDA-D5550 | Loan Disb | 841,398.75 |
Nov 28, 2022 | IDA-D5550 | Loan Disb | 492,669.53 |
Dec 27, 2022 | IDA-D5550 | Loan Disb | 613,604.25 |
Jul 8, 2024 | IDA-D5550 | Loan Disb | 125,700.00 |
Feb 14, 2020 | IDA-D5550 | Loan Commitment | 75,000,000.00 |
Aug 10, 2022 | IDA-D5550 | Loan Disb | 1,485,240.40 |
Jan 13, 2022 | IDA-D5550 | Loan Disb | 1,444,765.60 |
Jan 10, 2022 | IDA-D5550 | Loan Disb | 139,604.27 |
Jul 26, 2023 | IDA-D5550 | Loan Disb | 682,039.25 |
Jun 8, 2023 | IDA-D5550 | Loan Disb | 796,828.25 |
Jul 18, 2023 | IDA-D5550 | Loan Disb | 1,712,451.00 |
Aug 30, 2023 | IDA-D5550 | Loan Disb | 1,417,355.40 |
Mar 31, 2023 | IDA-D5550 | Loan Disb | 672,785.20 |
Jul 31, 2023 | IDA-D5550 | Loan Disb | 648,928.00 |
May 16, 2023 | IDA-D5550 | Loan Disb | 1,431,936.90 |
Apr 4, 2023 | IDA-D5550 | Loan Disb | 1,730,995.20 |
Feb 24, 2023 | IDA-D5550 | Loan Disb | 521,413.28 |
Mar 9, 2023 | IDA-D5550 | Loan Disb | 812,815.44 |
Apr 21, 2023 | IDA-D5550 | Loan Disb | 673,401.20 |
Mar 7, 2023 | IDA-D5550 | Loan Disb | 668,908.25 |
Jan 25, 2023 | IDA-D5550 | Loan Disb | 488,758.06 |
Jun 14, 2024 | IDA-D5550 | Loan Disb | 1,237,427.00 |
Apr 19, 2024 | IDA-D5550 | Loan Disb | 1,081,496.00 |
Dec 15, 2023 | IDA-D5550 | Loan Disb | 1,481,130.50 |
Sep 28, 2023 | IDA-D5550 | Loan Disb | 1,067,790.60 |
Jan 10, 2024 | IDA-D5550 | Loan Disb | 1,117,869.20 |
Nov 20, 2023 | IDA-D5550 | Loan Disb | 1,606,112.90 |
Dec 13, 2023 | IDA-D5550 | Loan Disb | 318,531.38 |
Dec 14, 2023 | IDA-D5550 | Loan Disb | 321,340.47 |
Oct 17, 2023 | IDA-D5550 | Loan Disb | 1,071,054.00 |
Jul 6, 2023 | IDA-D5550 | Loan Disb | 337,615.70 |
Aug 26, 2024 | IDA-D5550 | Loan Disb | 315,074.80 |
Aug 7, 2024 | IDA-D5550 | Loan Disb | 1,813,006.60 |
Aug 26, 2024 | IDA-D5550 | Loan Disb | 614,671.30 |
Aug 26, 2024 | IDA-D5550 | Loan Disb | 330,976.84 |
Jul 1, 2024 | IDA-D5550 | Loan Disb | 1,057,157.50 |
Jul 31, 2024 | IDA-D5550 | Loan Disb | 614,671.30 |
Feb 20, 2024 | IDA-D5550 | Loan Disb | 1,056,028.80 |
May 17, 2024 | IDA-D5550 | Loan Disb | 620,777.00 |
May 17, 2024 | IDA-D5550 | Loan Disb | 308,658.62 |
Mar 26, 2024 | IDA-D5550 | Loan Disb | 490,191.30 |
Apr 24, 2024 | IDA-D5550 | Loan Disb | 1,205,152.00 |
Feb 21, 2024 | IDA-D5550 | Loan Disb | 769,202.56 |
Jan 24, 2024 | IDA-D5550 | Loan Disb | 724,081.44 |
Jul 21, 2020 | IDA-D5550 | Loan Disb | 2,645,746.80 |
Nov 6, 2020 | IDA-D5550 | Loan Disb | 353,691.80 |
Feb 12, 2021 | IDA-D5550 | Loan Disb | 318,226.62 |
Feb 12, 2021 | IDA-D5550 | Loan Disb | 140,003.53 |
Dec 16, 2020 | IDA-D5550 | Loan Disb | 44,324.88 |
May 21, 2020 | IDA-D5550 | Loan Disb | 400,000.00 |
Aug 8, 2022 | IDA-D5550 | Loan Disb | 376,988.80 |
Aug 22, 2022 | IDA-D5550 | Loan Disb | 798,711.70 |
Apr 21, 2022 | IDA-D5550 | Loan Disb | 515,345.38 |
Apr 27, 2022 | IDA-D5550 | Loan Disb | 1,754,805.00 |
Jun 10, 2022 | IDA-D5550 | Loan Disb | 202,638.80 |
Jun 1, 2022 | IDA-D5550 | Loan Disb | 1,067,117.40 |
Aug 3, 2021 | IDA-D5550 | Loan Disb | 42,235.90 |
May 5, 2022 | IDA-D5550 | Loan Disb | 896,582.00 |
Apr 12, 2022 | IDA-D5550 | Loan Disb | 296,392.97 |
Apr 12, 2022 | IDA-D5550 | Loan Disb | 443,581.12 |
Oct 15, 2021 | IDA-D5550 | Loan Disb | 285,213.84 |
Jun 1, 2021 | IDA-D5550 | Loan Disb | 556,745.90 |
Mar 26, 2021 | IDA-D5550 | Loan Disb | 103,887.69 |
Nov 12, 2021 | IDA-D5550 | Loan Disb | 444,046.38 |
Nov 12, 2021 | IDA-D5550 | Loan Disb | 178,705.95 |
Sep 9, 2021 | IDA-D5550 | Loan Disb | 125,998.45 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Satisfactory | 2024-12-18 |
Procurement | Satisfactory | 2024-12-18 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-18 |
Progress towards achievement of PDO | Satisfactory | 2024-12-18 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-18 |
Project Management | Satisfactory | 2024-12-18 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries completing life-skills training | Value | 0.00 | 22696.00 | 40800.00 |
Date | March 14, 2019 | August 31, 2023 | April 30, 2025 | |
Comment |
Reduction in average drop-out rates among girls in grades receiving individual in-kind support | Value | 0.00 | 0.00 | 20.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Direct jobs created by winners of the Business Plan Competition (BPC) in sub-component 2.1 | Value | 0.00 | 108.00 | 2500.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Gender Parity Index (GPI) in grades receiving individual in-kind support | Value | 0.83 | 0.84 | 0.91 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Direct jobs created by winners of the BPC in sub-component 2.1 among women | Value | 0.00 | 21.00 | 1250.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Jobs created by beneficiaries of sub component 2.2 | Value | 0.00 | 0.00 | 3200.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Schools reached through GBV activities in sub-component 1.1 | Value | 0.00 | 359.00 | 150.00 |
Date | November 25, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Beneficiaries trained by the BPC in sub-component 2.1 | Value | 0.00 | 350.00 | 3000.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Government staff trained | Value | 0.00 | 422.00 | 400.00 |
Date | March 14, 2019 | June 22, 2023 | December 31, 2024 | |
Comment |
Community leaders sensitized | Value | 0.00 | 5830.00 | 4000.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Process evaluation of youth programs completed | Value | 0.00 | 1.00 | 1.00 |
Date | March 14, 2019 | June 22, 2023 | December 31, 2024 | |
Comment |
Beneficiaries trained by the BPC in sub-component 2.1, females | Value | 0.00 | 175.00 | 1500.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Uniforms delivered to schools | Value | 0.00 | 424569.00 | 560000.00 |
Date | March 14, 2019 | August 31, 2023 | December 31, 2024 | |
Comment |
Number of beneficiaries (firms) receiving financial support from BPC in sub-component 2.1, overall | Value | 0.00 | 50.00 | 500.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Impact evaluations | Value | 0.00 | 0.00 | 2.00 |
Date | March 14, 2019 | June 22, 2023 | December 31, 2024 | |
Comment |
Beneficiaries receiving bikes | Value | 0.00 | 4662.00 | 20800.00 |
Date | March 14, 2019 | June 22, 2023 | December 31, 2024 | |
Comment |
Grievances registered related to delivery of project benefits that are actually addressed | Value | 0.00 | 100.00 | 95.00 |
Date | March 14, 2019 | June 22, 2023 | December 31, 2024 | |
Comment |
Number of beneficiaries (firms) receiving financial support from BPC in sub-component 2.1, female | Value | 0.00 | 25.00 | 250.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Schools receiving sports kits | Value | 0.00 | 0.00 | 266.00 |
Date | March 14, 2019 | June 22, 2023 | December 31, 2024 | |
Comment |
Number of youth receiving training and services for productive employment under sub-component 2.2 | Value | 0.00 | 20750.00 | 16000.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Reports on inputs and effects of consultations on project/program/policies | Value | 0.00 | 3.00 | 2.00 |
Date | March 14, 2019 | June 22, 2023 | December 31, 2024 | |
Comment |
Sports events carried out at the district level | Value | 0.00 | 0.00 | 140.00 |
Date | March 14, 2019 | June 22, 2023 | December 31, 2024 | |
Comment |
Number of youth receiving financial support under comp. 2.2 | Value | 0.00 | 0.00 | 3200.00 |
Date | May 1, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Beneficiaries of job-focused interventions | Value | 0.00 | 5350.00 | 20000.00 |
Date | March 14, 2019 | June 22, 2023 | April 30, 2025 | |
Comment |
Beneficiaries of job-focused interventions - Female | Value | 0.00 | 0.00 | 1500.00 |
Date | ||||
Comment |