Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 23.00 |
P166187
Active
Ifeyinwa Bonheur , Boubacar Bocoum
Republic of Suriname
August 8, 2018
(as of board presentation)
July 9, 2019
December 19, 2019
US$ 23.00 million
Ministry of Economic Affairs, Entrepreneurship and Technological Innovation (MEA),Ministry of Natural Resources
2020
US$ 23.00 million
B
April 5, 2024
December 31, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 23.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 23.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 23.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 23.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 9, 2021 | IBRD-89850 | Int Charges | 26,757.39 |
Aug 15, 2022 | IBRD-89850 | Int Charges | 32,798.89 |
Feb 17, 2022 | IBRD-89850 | Int Charges | 25,144.50 |
Feb 17, 2022 | IBRD-89850 | Int Charges | 22,747.72 |
Aug 15, 2022 | IBRD-89850 | Int Charges | 24,734.54 |
Feb 15, 2023 | IBRD-89850 | Int Charges | 25,144.50 |
Feb 15, 2023 | IBRD-89850 | Int Charges | 74,631.18 |
Jul 9, 2019 | IBRD-89850 | Loan Commitment | 23,000,000.00 |
Jun 29, 2023 | IBRD-89850 | Loan Disb | 586,472.60 |
Aug 2, 2023 | IBRD-89850 | Loan Disb | 562,567.30 |
Aug 25, 2023 | IBRD-89850 | Int Charges | 24,495.66 |
Aug 25, 2023 | IBRD-89850 | Int Charges | 98,856.53 |
Aug 15, 2024 | IBRD-89850 | Int Charges | 222.94 |
Aug 15, 2024 | IBRD-89850 | Int Charges | 7,007.08 |
Aug 15, 2024 | IBRD-89850 | Int Charges | 17,449.20 |
Jan 12, 2024 | IBRD-89850 | Loan Disb | 959,953.50 |
Dec 8, 2023 | IBRD-89850 | Loan Disb | 2,442,757.50 |
Aug 15, 2024 | IBRD-89850 | Int Charges | 272,064.22 |
Jun 28, 2024 | IBRD-89850 | Loan Disb | 5,171,082.00 |
Feb 15, 2024 | IBRD-89850 | Int Charges | 238.88 |
Feb 15, 2024 | IBRD-89850 | Int Charges | 22,305.21 |
Feb 15, 2024 | IBRD-89850 | Int Charges | 6,010.03 |
Feb 15, 2024 | IBRD-89850 | Int Charges | 184,986.98 |
Dec 19, 2019 | IBRD-89850 | Loan Disb | 57,500.00 |
Dec 19, 2019 | IBRD-89850 | Fee Charges | 57,500.00 |
Mar 9, 2021 | IBRD-89850 | Int Charges | 11,208.00 |
Dec 28, 2020 | IBRD-89850 | Loan Disb | 1,452,000.00 |
Oct 2, 2020 | IBRD-89850 | Int Charges | 13,033.17 |
Oct 2, 2020 | IBRD-89850 | Int Charges | 310.34 |
Oct 2, 2020 | IBRD-89850 | Int Charges | 16,052.89 |
Oct 2, 2020 | IBRD-89850 | Int Charges | 12,468.51 |
Oct 2, 2020 | IBRD-89850 | Int Charges | 875.00 |
Sep 15, 2020 | IBRD-89850 | Loan Disb | 1,538,883.20 |
Aug 27, 2021 | IBRD-89850 | Int Charges | 1,591.37 |
Aug 27, 2021 | IBRD-89850 | Int Charges | 23,143.17 |
Aug 15, 2021 | IBRD-89850 | Int Charges | 487.20 |
Aug 15, 2021 | IBRD-89850 | Int Charges | 2,753.97 |
Aug 15, 2021 | IBRD-89850 | Int Charges | 23,143.17 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2024-11-15 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-11-15 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-11-15 |
Procurement | Moderately Satisfactory | 2024-11-15 |
Project Management | Moderately Satisfactory | 2024-11-15 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2024-11-15 |
Financial Management | Satisfactory | 2024-11-15 |
Project Management | Satisfactory | 2024-11-15 |
Overall Safeguards Rating | Satisfactory | 2024-11-15 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-11-15 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-11-15 |
Procurement | Moderately Satisfactory | 2024-11-15 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2024-11-15 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of mining concessions subject to formal inspections following good international practices | Value | 0.00 | 0.00 | 50.00 |
Date | May 15, 2019 | January 19, 2024 | September 30, 2025 | |
Comment |
Increase in revenue of SMEs benefitting from project support | Value | 0.00 | 0.00 | 15.00 |
Date | May 15, 2019 | January 22, 2024 | September 30, 2025 | |
Comment |
Number of regulatory or policy reforms adopted to strengthen governance and competitiveness in targeted industries | Value | 0.00 | 2.00 | 14.00 |
Date | May 15, 2019 | January 22, 2024 | September 30, 2025 | |
Comment |
Increase in revenue of SMEs benefitting from project support that are women-owned or that employ a majority of female workers | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Standard operating procedures and associated documentation of key mining functions within the Minerals Institute produced | Value | 0.00 | 0.00 | 7.00 |
Date | March 29, 2019 | January 19, 2024 | September 30, 2025 | |
Comment |
Number of SMEs benefitting from capacity upgrading support | Value | 0.00 | 200.00 | 160.00 |
Date | March 29, 2019 | January 22, 2024 | March 29, 2025 | |
Comment |
Number of government staff trained to manage, regulate, and monitor the mining sector (disaggregated by gender and function) | Value | 0.00 | 15.00 | 35.00 |
Date | March 29, 2019 | January 19, 2024 | September 30, 2025 | |
Comment |
Of which women-owned | Value | 0.00 | 0.00 | 8.00 |
Date | ||||
Comment |
Establishment of a system for transparent assessment and collection of revenues from the mining sector | Value | No | No | Yes |
Date | May 15, 2019 | January 19, 2024 | March 29, 2025 | |
Comment |
Number of SMEs receiving matching grants | Value | 0.00 | 26.00 | 150.00 |
Date | March 29, 2019 | January 22, 2024 | March 29, 2025 | |
Comment |
Number of mining concessions monitored and inspected by the Mines Inspectorate Department in collaboration with other relevant agencies | Value | 0.00 | 4.00 | 25.00 |
Date | March 29, 2019 | January 19, 2024 | September 30, 2025 | |
Comment |
Of which women-owned | Value | 0.00 | 0.00 | 4.00 |
Date | ||||
Comment |
Volume of private co-investment in competitive upgrading | Value | 0.00 | 1386447.00 | 1500000.00 |
Date | March 29, 2019 | January 22, 2024 | March 29, 2025 | |
Comment |
Number of recommended business environment regulations, codes, policies, or procedures adopted | Value | 0.00 | 2.00 | 4.00 |
Date | May 15, 2019 | January 22, 2024 | September 30, 2025 | |
Comment |
Beneficiaries satisfied with quality of services provided under Component 2 | Value | 0.00 | 92.00 | 85.00 |
Date | March 29, 2019 | January 22, 2024 | March 29, 2025 | |
Comment |