Strengthening Disaster Risk Management Project

Abstract*

The development objective of the Strengthening Disaster Risk Management Project for Romania is to enhance the resilience of critical disaster and emergency response facilities and to strengthen the institutional capacities in investment planning for disaster risk reduction and climate change adaptation. The project comprises of three components. The first component, improving seismic resilience of disaster and emergency response infrastructure objective...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to enhance the resilience of critical disaster and emergency response infrastructure and to strengthen the Borrower’s institutional capacities in disaster risk reduction and climate change adaptation.

Key Details

Project Details

  • P166302

  • Active

  • Alexandra Calin , Marcel Ionescu-Heroiu

  • Romania (through its Ministry of Public Finance)

  • Romania

  • January 15, 2018

  • (as of board presentation)

    July 24, 2018

  • December 20, 2018

  • US$ 60.48 million

  • Ministry of Internal Affairs - Department of Emergency Situations and General Inspectorate for Emerg

  • Europe and Central Asia

  • 2019

  • US$ 60.48 million

  • B

  • May 31, 2024

  • June 30, 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 60.48

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 60.48
IDA Commitment N/A
IBRD + IDA Commitment 60.48
Lending Instrument
Grant Amount N/A
Total Project Cost** 60.48

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 21, 2024 IBRD-88920 Loan Disb 1,839,472.60
May 1, 2024 IBRD-88920 Int Charges 464,819.84
May 1, 2024 IBRD-88920 Int Charges 497.04
May 1, 2024 IBRD-88920 Int Charges 7,908.65
May 1, 2024 IBRD-88920 Int Charges 41,103.47
Feb 27, 2024 IBRD-88920 Loan Disb 663,571.25
Nov 15, 2023 IBRD-88920 Loan Disb 1,869,094.00
Apr 8, 2024 IBRD-88920 Loan Disb 1,437,696.60
Jul 11, 2024 IBRD-88920 Loan Disb 2,374,507.20
Jun 17, 2024 IBRD-88920 Loan Disb 1,009,228.70
May 21, 2024 IBRD-88920 Loan Disb 781,837.75
Aug 7, 2024 IBRD-88920 Loan Disb 2,362,905.50
Apr 15, 2024 IBRD-95290 Int Charges 178,436.19
Dec 21, 2023 IBRD-95290 Fee Charges 252,540.00
Jul 24, 2018 IBRD-88920 Loan Commitment 60,480,000.00
May 23, 2023 IBRD-95290 Loan Commitment 99,900,000.00
Sep 1, 2022 IBRD-88920 Loan Disb 739,023.50
Aug 11, 2023 IBRD-88920 Loan Disb 870,105.56
Sep 13, 2023 IBRD-88920 Loan Disb 1,490,539.50
May 1, 2023 IBRD-88920 Int Charges 106,375.50
May 1, 2023 IBRD-88920 Int Charges 108.64
May 1, 2023 IBRD-88920 Int Charges 57,536.91
May 1, 2023 IBRD-88920 Int Charges 422.42
Mar 10, 2023 IBRD-88920 Loan Disb 1,394,622.90
Feb 15, 2023 IBRD-88920 Loan Disb 967,667.56
Apr 28, 2023 IBRD-88920 Loan Disb 1,166,811.20
Nov 1, 2022 IBRD-88920 Int Charges 4,285.40
May 26, 2023 IBRD-88920 Loan Disb 693,490.56
Jul 13, 2023 IBRD-88920 Loan Disb 1,179,506.80
Nov 1, 2023 IBRD-88920 Int Charges 279,764.28
Nov 1, 2023 IBRD-88920 Int Charges 517.76
Nov 1, 2023 IBRD-88920 Int Charges 4,899.85
Nov 1, 2023 IBRD-88920 Int Charges 49,432.77
Jan 9, 2024 IBRD-88920 Loan Disb 1,924,882.90
Nov 1, 2023 IBRD-88920 Loan Disb 863,931.70
May 10, 2022 IBRD-88920 Loan Disb 455,960.53
Feb 23, 2022 IBRD-88920 Loan Disb 558,652.50
Aug 16, 2022 IBRD-88920 Loan Disb 450,529.20
Jul 21, 2022 IBRD-88920 Loan Disb 532,197.25
Jun 27, 2022 IBRD-88920 Loan Disb 441,611.22
May 1, 2022 IBRD-88920 Int Charges 63,960.82
May 1, 2022 IBRD-88920 Int Charges 123.93
Nov 1, 2022 IBRD-88920 Int Charges 58,826.82
Nov 14, 2022 IBRD-88920 Loan Disb 1,404,626.80
Dec 23, 2022 IBRD-88920 Loan Disb 1,631,924.10
Oct 14, 2022 IBRD-88920 Loan Disb 596,167.80
Nov 1, 2020 IBRD-88920 Int Charges 73,161.34
Nov 1, 2020 IBRD-88920 Int Charges 299.14
Nov 30, 2021 IBRD-88920 Loan Disb 480,256.97
Jul 20, 2021 IBRD-88920 Loan Disb 520,597.72
Nov 1, 2021 IBRD-88920 Int Charges 72,279.71
Nov 1, 2021 IBRD-88920 Int Charges 77.46
May 1, 2021 IBRD-88920 Int Charges 74,531.06
May 1, 2021 IBRD-88920 Int Charges 34.02
May 1, 2020 IBRD-88920 Int Charges 68,325.11
Jun 24, 2020 IBRD-88920 Loan Disb 211,190.88
May 1, 2019 IBRD-88920 Int Charges 81,968.53
Nov 1, 2019 IBRD-88920 Int Charges 70,247.67
Feb 14, 2019 IBRD-88920 Fee Charges 140,856.25

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Satisfactory 2024-12-09
Overall Implementation Progress (IP) Satisfactory 2024-12-09
Progress towards achievement of PDO Satisfactory 2024-12-09
Procurement Satisfactory 2024-12-09
Financial Management Satisfactory 2024-12-09
Monitoring and Evaluation Satisfactory 2024-12-09
Project Management Satisfactory 2024-12-09

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of disaster and emergency response facilities that are upgraded to be resilientValue0.001.0028.00
    DateJuly 2, 2018November 28, 2023June 30, 2027
    Comment
  • Enhanced Ro-Risk assessment supports enhanced risk reduction planning in other ministriesValueRo-Risk Assessment (2018 version)Procurement of services for this activity is expecRo-Risk data is being used by at least two ministr
    DateJuly 2, 2018May 31, 2024December 31, 2024
    Comment
  • Number of rescue personnel, emergency and disaster management staff, volunteers and administrative staff with access to disaster resilient buildingsValue0.00286.001000.00
    DateJuly 2, 2018May 31, 2024June 30, 2027
    Comment
  • MOIA, through DES and GIES, has strengthened institutional capacity for risk reduction investment planningValueGIES has started a process to collect data on vulnThe final version of the damage and loss assessmenGIES is systematically collecting data on emergenc
    DateJuly 2, 2018November 28, 2023December 31, 2024
    Comment
  • Number of project beneficiaries in areas covered by resilient emergency and disaster response facilitiesValue0.00405.003000.00
    DateJuly 2, 2018May 31, 2024June 30, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of emergency and response buildings retrofitted to improve structural resilienceValue0.003.008.00
    DateJuly 1, 2018May 31, 2024June 30, 2027
    Comment
  • Media content representing women in Public Awareness Campaign materials (content analysis)Value0.000.0050.00
    DateApril 27, 2023May 31, 2024June 30, 2027
    Comment
  • Number of communities reached out to via informative meetings and trainingsValue0.0024.0020.00
    DateJuly 1, 2018May 31, 2024June 30, 2027
    Comment
  • Number of direct project beneficiariesValue0.00290.001000.00
    DateJuly 1, 2018May 31, 2024June 30, 2027
    Comment
  • Female Project BeneficiariesValue0.004.00300.00
    DateJuly 1, 2018May 31, 2024June 30, 2027
    Comment
  • Number of technical designs completedValue0.0010.0028.00
    DateJuly 2, 2018May 31, 2024June 30, 2027
    Comment
  • Number of reports on the impacts of disasters and climate change in RomaniaValue0.000.003.00
    DateJuly 1, 2018May 31, 2024June 30, 2027
    Comment
  • Institutional capacity in engineering, procurement and contract management is in placeValueNoYesYes
    DateJuly 1, 2018May 31, 2024June 30, 2027
    Comment
  • Number of newly constructed emergency and response buildings with resilient structures and systemsValue0.003.0020.00
    DateJuly 1, 2018May 31, 2024June 30, 2027
    Comment
  • Public Awareness CampaignsValue0.0026.0028.00
    DateJuly 1, 2019May 31, 2024June 30, 2027
    Comment
  • Percentage of grievances responded to in the stipulated timeValue0.00100.00100.00
    DateJuly 1, 2018May 31, 2024June 30, 2027