Sheberghan Gas to Power Project

Abstract*

The objective of the Gas-to-Power Project for the Islamic Republic of Afghanistan is to increase the amount of electricity generated in Afghanistan and to leverage private financing for the country's energy sector. The project has three components. A) The proposed Project comprises the development, financing, design, construction and operation of a 40MW green-field gas-to-power plant as an IPP on a Build-Own-Operate basis. It will be implemented by...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase the amount of electricity generated in Afghanistan and to leverage p rivate financing for the country's energy sector.

Key Details

Project Details

  • P166405

  • Closed

  • Monyl Toga Makang , Abdul Quraishi

  • Islamic Republic of Afghanistan

  • Afghanistan

  • October 29, 2018

  • (as of board presentation)

    October 10, 2019

  • N/A

  • US$ 51.65 million

  • Bayat Power Electricity Services Distributor Company

  • South Asia

  • 2020

  • US$ 0.00 million

  • N/A

  • Not Applicable

  • April 21, 2022

  • BANK APPROVED

  • December 19, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Guarantee 12.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount N/A
Total Project Cost** 51.65

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 10, 2019 IDA-G3020 Loan Commitment 12,800,000.00
Apr 21, 2022 IDA-G3020 Loan Cancel 12,800,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2022-04-26
Financial Management Moderately Satisfactory 2022-04-26
Monitoring and Evaluation Moderately Satisfactory 2022-04-26
Progress towards achievement of PDO Satisfactory 2022-04-26
Procurement Moderately Satisfactory 2022-04-26
Overall Implementation Progress (IP) Satisfactory 2022-04-26

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Generation capacity of the plant constructed under the projectValue0.0040.0040.00
    DateOctober 10, 2019August 15, 2021June 30, 2022
    Comment
  • Private Capital MobilizedValue0.0042300000.0042300000.00
    DateOctober 10, 2019August 15, 2021June 30, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Grievances registered under the GRM resolved within stipulated response timesValue0.000.0080.00
    DateOctober 10, 2019August 15, 2021June 30, 2022
    Comment