Skip to Main Navigation

Second Rwanda Energy Sector Development Policy Operation

Abstract*

The Energy Sector Development Policy Operation (DPO) is the second in a programmatic series of three DPOs. The Government’s reform program aims at balancing the triple objectives of achieving ambitious expansion targets for electricity generation and access while containing fiscal transfers to the sector and enhancing the affordability of electricity service for consumers. In line with the Government’s program, the PDO of the proposed operation is...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Program Development Objective (PDO) of the proposed operation is to enable fiscally sustainable expansion of electricity services in Rwanda. The proposed operation is built around two pillars: (i) containing the fiscal impact of the electricity sector; and (ii) improving the operational efficiency, affordability, and accountability of electricity service.

Key Details

Project Details

  • P166458

  • Closed

  • Yadviga Semikolenova , Joern Huenteler

  • MINECOFIN

  • Rwanda

  • May 22, 2018

  • (as of board presentation)

    November 15, 2018

  • December 7, 2018

  • US$ 125.00 million

  • N/A

  • June 8, 2022

  • June 30, 2020

  • BANK APPROVED

  • P162671

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 125.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 125.00
IBRD + IDA Commitment 125.00
Lending Instrument
Grant Amount N/A
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2018 IDA-63440 Loan Commitment 125,000,000.00
Oct 1, 2021 IDA-63440 Int Charges 467,040.00
Apr 1, 2024 IDA-63440 Int Charges 436,447.20
Apr 1, 2024 IDA-63440 Int Charges 8,309.28
Apr 1, 2024 IDA-63440 Int Charges 8,309.28
Oct 1, 2023 IDA-63440 Int Charges 2,120.17
Oct 1, 2023 IDA-63440 Int Charges 439,713.12
Oct 1, 2023 IDA-63440 Int Charges 439,713.12
Oct 1, 2023 IDA-63440 Int Charges 2,120.17
Oct 1, 2022 IDA-63440 Int Charges 424,132.80
Oct 1, 2022 IDA-63440 Int Charges 424,132.80
Oct 1, 2022 IDA-63440 Int Charges 5,906.86
Oct 1, 2022 IDA-63440 Int Charges 5,906.86
Apr 1, 2023 IDA-63440 Int Charges 15,076.32
Apr 1, 2023 IDA-63440 Int Charges 15,076.32
Apr 1, 2023 IDA-63440 Int Charges 436,920.97
Apr 1, 2023 IDA-63440 Int Charges 436,920.97
Apr 1, 2022 IDA-63440 Int Charges 458,065.44
Apr 1, 2022 IDA-63440 Int Charges 458,065.44
Apr 1, 2022 IDA-63440 Int Charges 5,742.24
Apr 1, 2022 IDA-63440 Int Charges 5,742.24
Dec 11, 2018 IDA-63440 Loan Disb 124,018,048.00
Apr 1, 2019 IDA-63440 Int Charges 285,033.47
Apr 1, 2019 IDA-63440 Int Charges 285,033.47
Oct 1, 2019 IDA-63440 Int Charges 455,523.78
Oct 1, 2019 IDA-63440 Int Charges 455,523.78
Oct 1, 2019 IDA-63440 Int Charges 2,114.94
Oct 1, 2019 IDA-63440 Int Charges 2,114.94
Apr 1, 2020 IDA-63440 Int Charges 2,556.96
Apr 1, 2020 IDA-63440 Int Charges 2,556.96
Apr 1, 2020 IDA-63440 Int Charges 456,388.80
Apr 1, 2020 IDA-63440 Int Charges 456,388.80
Oct 1, 2020 IDA-63440 Int Charges 3,709.46
Oct 1, 2020 IDA-63440 Int Charges 3,709.46
Oct 1, 2020 IDA-63440 Int Charges 470,225.25
Oct 1, 2020 IDA-63440 Int Charges 470,225.25
Apr 1, 2021 IDA-63440 Int Charges 856.81
Apr 1, 2021 IDA-63440 Int Charges 856.81
Apr 1, 2021 IDA-63440 Int Charges 475,127.50
Apr 1, 2021 IDA-63440 Int Charges 475,127.50
Oct 1, 2021 IDA-63440 Int Charges 7,284.48
Oct 1, 2021 IDA-63440 Int Charges 7,284.48
Oct 1, 2021 IDA-63440 Int Charges 467,040.00
Apr 1, 2024 IDA-63440 Int Charges 436,447.20

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2019-02-25
Monitoring and Evaluation Satisfactory 2019-02-25
Overall Implementation Progress (IP) Satisfactory 2019-02-25
Program Management Satisfactory 2019-02-25

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-07-2022
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-02-2022PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityN/a

Results Framework

No data available.