Connectivity for Rural Livelihood Improvement Project

Abstract*

The objective of the Connectivity for Rural Livelihood Improvement Project for Madagascar is to enhance transport connectivity in selected rural areas to improve access to social and economic opportunities of communities. The project is composed of five components. Component 1 primarily focuses on the climate-resilient rehabilitation of the secondary road network in priority regions, the 'missing middle' which is critical for continuity and connecting...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to enhance transport connectivity in selected rural areas to improve access to social and economic opportunities of communities.

Key Details

Project Details

  • P166526

  • Active

  • Vincent Vesin , Alphonse Soh, Raman Krishnan

  • REPUBLIC OF MADAGASCAR

  • Madagascar

  • November 27, 2018

  • (as of board presentation)

    November 15, 2019

  • March 13, 2020

  • US$ 140.00 million

  • A

  • April 5, 2024

  • June 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 140.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 140.00
IBRD + IDA Commitment 140.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 140.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 4, 2022 IDA-65050 Int Charges 112,081.41
Mar 4, 2022 IDA-65050 Int Charges 112,081.41
Mar 4, 2022 IDA-65050 Int Charges 1,041.16
Mar 4, 2022 IDA-65050 Int Charges 1,041.16
Apr 8, 2022 IDA-65050 Loan Disb 1,232,211.50
Dec 21, 2022 IDA-65050 Loan Disb 2,541,272.80
Mar 13, 2020 IDA-65050 Loan Disb 517,338.75
Sep 1, 2020 IDA-65050 Int Charges 15,705.13
Sep 1, 2020 IDA-65050 Int Charges 15,705.13
Sep 28, 2020 IDA-65050 Loan Disb 62,531.53
Oct 23, 2020 IDA-65050 Loan Disb 4,604,860.00
Jun 24, 2020 IDA-65050 Loan Disb 10,000,000.00
Mar 3, 2021 IDA-65050 Loan Disb 634,302.06
Nov 20, 2020 IDA-65050 Loan Disb 2,085,902.80
Mar 1, 2021 IDA-65050 Int Charges 534.87
Mar 1, 2021 IDA-65050 Int Charges 534.87
Mar 1, 2021 IDA-65050 Int Charges 65,554.84
Mar 1, 2021 IDA-65050 Int Charges 65,554.84
Nov 15, 2019 IDA-65050 Loan Commitment 140,000,000.00
Jun 29, 2023 IDA-65050 Loan Disb 2,215,655.50
Jun 5, 2023 IDA-65050 Loan Disb 647,036.10
Dec 20, 2023 IDA-65050 Loan Disb 5,994,838.50
Jan 9, 2024 IDA-65050 Loan Disb 2,113,996.00
Jan 16, 2024 IDA-65050 Loan Disb 2,018,537.60
Jan 10, 2024 IDA-65050 Loan Disb 2,518,633.80
Nov 30, 2023 IDA-65050 Loan Disb 260,778.88
Sep 29, 2023 IDA-65050 Loan Disb 956,979.60
Dec 22, 2023 IDA-65050 Loan Disb 4,528,606.00
Mar 4, 2024 IDA-65050 Int Charges 267,483.03
Jul 19, 2024 IDA-65050 Loan Disb 906,864.20
Apr 8, 2024 IDA-65050 Loan Disb 3,334,426.20
Apr 8, 2024 IDA-65050 Loan Disb 487,616.88
May 20, 2024 IDA-65050 Loan Disb 1,732,221.40
Mar 1, 2024 IDA-65050 Int Charges 1,175.41
Mar 1, 2024 IDA-65050 Int Charges 1,175.41
Mar 4, 2024 IDA-65050 Int Charges 267,483.03
Feb 5, 2024 IDA-65050 Loan Disb 2,264,186.00
Jun 12, 2024 IDA-65050 Loan Disb 4,080,483.80
Dec 27, 2021 IDA-65050 Loan Disb 2,332,858.50
Jan 28, 2022 IDA-65050 Loan Disb 2,043,931.20
Aug 5, 2022 IDA-65050 Loan Disb 2,185,305.00
Jun 6, 2022 IDA-65050 Loan Disb 3,434,925.80
Sep 6, 2022 IDA-65050 Loan Disb 1,048,333.80
Sep 6, 2022 IDA-65050 Int Charges 217.37
Sep 6, 2022 IDA-65050 Int Charges 217.37
Sep 6, 2022 IDA-65050 Int Charges 146,463.81
Sep 6, 2022 IDA-65050 Int Charges 146,463.81
Feb 13, 2023 IDA-65050 Loan Disb 462,234.28
Apr 7, 2023 IDA-65050 Loan Disb 2,369,687.20
Oct 5, 2022 IDA-65050 Loan Disb 2,761,346.50
Sep 8, 2023 IDA-65050 Loan Disb 1,284,907.50
May 11, 2023 IDA-65050 Loan Disb 769,483.90
Mar 6, 2023 IDA-65050 Int Charges 188,869.92
Mar 6, 2023 IDA-65050 Int Charges 188,869.92
Mar 1, 2023 IDA-65050 Int Charges 2,723.38
Mar 1, 2023 IDA-65050 Int Charges 2,723.38
Sep 6, 2023 IDA-65050 Int Charges 220,268.14
Sep 6, 2023 IDA-65050 Int Charges 220,268.14
Aug 4, 2023 IDA-65050 Loan Disb 51,521.54
Jun 16, 2023 IDA-65050 Loan Disb 2,177,349.50
Jun 23, 2023 IDA-65050 Loan Disb 2,106,997.50
Jun 23, 2023 IDA-65050 Loan Disb 829,116.70
Sep 6, 2023 IDA-65050 Int Charges 64.71
Sep 6, 2023 IDA-65050 Int Charges 64.71
May 11, 2021 IDA-65050 Loan Disb 58,913.07
May 11, 2021 IDA-65050 Loan Disb 589,455.20
Nov 30, 2020 IDA-65050 Loan Disb 3,508,740.50
Nov 30, 2020 IDA-65050 Loan Disb 359,845.56
Feb 2, 2021 IDA-65050 Loan Disb 265,578.97
Jul 20, 2021 IDA-65050 Loan Disb 870,356.75
Jun 1, 2021 IDA-65050 Loan Disb 1,356,763.90
Aug 17, 2021 IDA-65050 Loan Disb 1,259,121.90
Nov 12, 2021 IDA-65050 Loan Disb 1,903,433.10
Oct 4, 2021 IDA-65050 Loan Disb 2,362,973.80
Sep 2, 2021 IDA-65050 Int Charges 87,712.49
Sep 2, 2021 IDA-65050 Int Charges 87,712.49
Sep 1, 2021 IDA-65050 Int Charges 2.80
Sep 1, 2021 IDA-65050 Int Charges 2.80
Apr 21, 2022 IDA-65050 Loan Disb 1,568,740.20
Mar 11, 2022 IDA-65050 Loan Disb 1,073,097.40
Jun 10, 2022 IDA-65050 Loan Disb 2,416,700.00
May 19, 2022 IDA-65050 Loan Disb 2,096,495.90

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2025-03-10
Financial Management Satisfactory 2025-03-10
Monitoring and Evaluation Satisfactory 2025-03-10
Progress towards achievement of PDO Moderately Satisfactory 2025-03-10
Procurement Satisfactory 2025-03-10
Project Management Moderately Satisfactory 2025-03-10

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Rural population with access to an all-season roadValue310000.00422000.00620000.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Number of rural women with access to an all-season roadValue158000.00158000.00205400.00
    Date
    Comment
  • Travel time from Fort-Dauphin to VangaindranoValue24.0017.308.00
    DateNovember 7, 2018January 31, 2024December 31, 2025
    Comment
  • Travel time from Marovoay to VohidialaValue8.002.003.00
    DateSeptember 9, 2019January 31, 2024December 31, 2025
    Comment
  • Number of schools in the project areas with improved road accessValue0.0065.00139.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Number of health centers in the project areas with improved road accessValue0.0014.0050.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Quantity of Litchi from the project areas (South-East) transported to marketsValue2000.002000.0015000.00
    DateSeptember 25, 2019January 31, 2024December 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads rehablitatedValue0.00113.00148.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Road Accident Data Management System (RADMS) establishedValueNoNoYes
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Digital platform for transport and agriculture services deployedValueNoNoYes
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Roads rehablitatedValue0.000.00500.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Number of new bridges constructed (spans greater than 20 meters)Value0.000.001.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Road Safety Strategy developedValueNoYesYes
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Number of beneficiaries of Digital Platform for Transport and Agricultural ServicesValue0.000.007500.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Roads rehabilitated - ruralValue0.000.000.00
    Date
    Comment
  • Number of GBV and HIV/AIDS awareness-raising campaigns carried out in the project areasValue0.00175.0020.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Percentage of grievances recorded and processed as per the project's GRMValue0.00100.00100.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Number of Women beneficiaries of Digital Platform for Transport and Agricultural ServicesValue0.000.000.00
    Date
    Comment
  • Kilometers of road network processed by the Road Asset Management SystemValue0.000.006000.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Number of rural people trained on Digital LiteracyValue0.000.004000.00
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Road asset management system is used to inform annual road maintenance planValueNoNoYes
    DateOctober 4, 2019January 31, 2024December 31, 2025
    Comment
  • Number of rural women trained on Digital LiteracyValue0.000.00200.00
    Date
    Comment
  • Share of construction workers that have signed the Code of ConductValue0.00100.00100.00
    DateSeptember 25, 2019January 31, 2024December 31, 2025
    Comment