Skip to Main Navigation

Vietnam University Development of VNU-Hanoi, VNU-HCM, and UD

Abstract*

The objective of the University Development of VNU-Hanoi, VNU-HCM, and UD Project for Vietnam is to improve the quality of teaching and research at three targeted national universities. The Project has three components. Component 1: Vietnam National University Development – VNU-Hanoi has three subcomponents. Under subcomponent 1.1. Improved Quality of Teaching and Learning, VNU-HN will construct modern learning and teaching infrastructure and supply...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the quality of teaching and research at three targeted national universities.

Key Details

Project Details

  • P166656

  • Active

  • Dung Vo , Michael Drabble

  • Socialist Republic of Vietnam

  • Viet Nam

  • February 24, 2019

  • (as of board presentation)

    June 30, 2020

  • April 19, 2022

  • US$ 356.94 million

  • The University of Danang (UD),Vietnam National University-HCM,Vietnam National University-Hanoi

  • East Asia and Pacific

  • 2020

  • US$ 294.87 million

  • B

  • March 28, 2024

  • December 31, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 294.87
Borrower/Recipient 62.07

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 294.87
IBRD + IDA Commitment 294.87
Lending Instrument
Grant Amount N/A
Total Project Cost** 356.94

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 15, 2023 IDA-67230 Int Charges 123,926.09
Dec 15, 2023 IDA-67240 Int Charges 122,835.63
Dec 15, 2022 IDA-67250 Int Charges 78,534.25
Dec 15, 2022 IDA-67250 Int Charges 122,835.63
Jun 11, 2024 IDA-67250 Loan Disb 55,000.00
Jun 27, 2024 IDA-67230 Fee Charges 30.00
Jun 15, 2024 IDA-67240 Int Charges 122,531.18
Jun 15, 2024 IDA-67250 Int Charges 122,529.68
Jun 15, 2024 IDA-67230 Int Charges 123,618.95
Jul 12, 2024 IDA-67230 Loan Disb 50,000.00
Jun 15, 2023 IDA-67240 Int Charges 122,164.39
Jun 22, 2023 IDA-67240 Fee Charges 245,000.00
Jun 15, 2023 IDA-67230 Int Charges 123,248.91
Jan 31, 2024 IDA-67230 Fee Charges 247,145.00
Dec 15, 2022 IDA-67230 Int Charges 123,926.09
Dec 15, 2022 IDA-67240 Int Charges 78,534.25
Jun 30, 2020 IDA-67230 Loan Commitment 98,870,000.00
Jun 30, 2020 IDA-67240 Loan Commitment 98,000,000.00
Jun 30, 2020 IDA-67250 Loan Commitment 98,000,000.00
Dec 15, 2022 IDA-67230 Int Charges 79,231.44
Jun 22, 2023 IDA-67240 Fee Charges -245,000.00
Jul 28, 2023 IDA-67240 Fee Charges 245,000.00
Jun 22, 2023 IDA-67250 Fee Charges 245,000.00
Jun 15, 2023 IDA-67250 Int Charges 122,164.39
Dec 15, 2023 IDA-67250 Int Charges 122,835.63
Dec 15, 2022 IDA-67240 Int Charges 122,835.63

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Moderately Satisfactory 2024-09-13
Project Management Moderately Unsatisfactory 2024-09-13
Financial Management Moderately Satisfactory 2024-09-13
Monitoring and Evaluation Moderately Satisfactory 2024-09-13
Progress towards achievement of PDO Moderately Unsatisfactory 2024-09-13
Procurement Moderately Satisfactory 2024-09-13
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-09-13

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of internationally accredited programsValue129.00239.00197.00
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment
  • Number of articles published in Web of Science and Scopus journals, in relation to full-time academic staffValue12747.0026053.0030930.00
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • IR 4 - Proportion of articles published in Web of Science and Scopus journals, with female author(s)Value32.0038.2037.00
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment
  • IR 8 - Improved management information system (MIS) and beneficiary feedback systemValueNo unified management information and unified feedPartially metA unified management information and beneficiary f
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment
  • IR 5 - Number of functional partnerships (international and domestic)Value73.00135.00225.00
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment
  • IR 9 - Improved governanceValueNo effective policies in place to facilitate moderPARTIALLY MET - Staff KPIs developed and deployed Policies are in place for modern governance
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment
  • IR 1- Modern research infrastructure built and in operationValue0.000.00100.00
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment
  • IR 6 - Modern research infrastructure built and in operationValue0.000.0040.00
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment
  • IR 2- On-time graduation student rates for programs using technology and innovations by education levels (bachelor and master)Value63.0068.1075.00
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment
  • IR 7 - Number of research groups getting external grants above threshold, especially interdisciplinary teamsValue9.0017.0031.00
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment
  • IR 3 - Student satisfaction with the learning experienceValue0.004.1083.40
    DateJanuary 31, 2020December 31, 2023December 31, 2025
    Comment