Electricity Access Scale-up Project (EASP)

Abstract*

The proposed Electricity Access Scale-up Project (EASP) contributes to the NDP-III and Vision 2040’s goal of increasing clean energy access in Uganda to spur socio-economic transformation. The proposed project will directly support the scaling up of electricity connections and electricity demand in Uganda through on-grid, mini-grid, and off-grid solutions. The proposed project will be structured around five components: (1) Grid expansion and connectivity...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to increase access to energy for households, commercial enterprises, industrial parks, and public institutions.

Key Details

Project Details

  • P166685

  • Active

  • Joseph Kapika , Raihan Elahi, Yabei Zhang

  • Republic of Uganda

  • Uganda

  • June 19, 2019

  • (as of board presentation)

    March 31, 2022

  • July 20, 2023

  • US$ 638.00 million

  • Ministry of Energy and Mineral Development (MEMD),Uganda Energy Credit Capitalisation Company (UECCC)

  • Eastern and Southern Africa

  • 2022

  • US$ 608.00 million

  • N/A

  • January 24, 2024

  • June 30, 2027

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Energy Sector Management Assistance Program 10.00
IDA Credit 331.50
Clean Technology Fund 30.00
IDA Grant 236.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 568.00
IBRD + IDA Commitment 568.00
Lending Instrument
Grant Amount 40.00
Total Project Cost** 638.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 31, 2022 IDA-70750 Loan Commitment 331,500,000.00
Mar 31, 2022 IDA-D9970 Loan Commitment 236,500,000.00
Sep 26, 2023 IDA-D9970 Loan Disb 1,326,463.80
Sep 29, 2023 IDA-D9970 Loan Disb 2,296,288.00
Aug 7, 2024 IDA-D9970 Loan Disb 8,044,714.50
May 15, 2024 IDA-70750 Int Charges 4,351.02
Mar 11, 2024 IDA-D9970 Loan Disb 5,142,059.00
Feb 23, 2024 IDA-D9970 Loan Disb 2,327,490.00
Aug 12, 2024 IDA-70750 Loan Disb 39,797,424.00
Feb 23, 2024 IDA-70750 Loan Disb 2,554,349.20
May 15, 2024 IDA-70750 Int Charges 4,351.02
Aug 7, 2024 IDA-D9970 Loan Disb 2,530,871.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2025-01-30
Project Management Satisfactory 2025-01-30
Progress towards achievement of PDO Satisfactory 2025-01-30
Financial Management Satisfactory 2025-01-30
Monitoring and Evaluation Satisfactory 2025-01-30
Overall Implementation Progress (IP) Satisfactory 2025-01-30

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Connections provided under the project with grid, mini-grid, and off-gridValue0.000.001223500.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • People provided with access to electricity under the project with grid and mini-gridValue0.000.005050000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • People provided with access to electricity under the project with grid and mini-grid of which femaleValue0.000.002525000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • People provided with access to electricity under the project with off-gridValue0.000.00667400.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • People provided with access to electricity under the project with off-grid of which femaleValue0.000.00333700.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • People provided with access to electricity with grid, mini-grid, off-grid in refugee-hosting districtsValue0.000.00534000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • People provided with access to electricity with grid, mini-grid, off-grid under the project, of which refugeesValue0.000.00267000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • People with access to clean cooking solutions under the projectValue0.000.001660000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Commercial and productive uses beneficiaries of grid, mini-grid, off-grid accessValue0.000.0050500.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Public institutions provided with grid and off-grid access under the project.Value0.000.00700.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Public institutions provided with clean cooking solutionsValue0.000.00600.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Industrial parks electrified under the projectValue0.000.005.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Annual greenhouse gases emissions avoided (tCO2)Value0.000.00107000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Generation capacity of energy constructed or rehabilitatedValue0.000.0038.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Renewable energy generation capacity (other than hydropower) constructed under the projectValue0.000.0038.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Volume of financing to beneficiaries for access to energyValue0.000.0060000000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Number household connections provided with grid and mini-grid under the projectValue0.000.00940000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Number of grid and mini-grid connections provided the project in refugee-hosting districtsValue0.000.00100000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Establishment and adequate functioning of PCU at MEMDValueAdequately functioning PCU not in place, monitorinEstablished(A) 13 key staff specialists are retained througho
    DateJanuary 31, 2022July 20, 2023June 30, 2027
    Comment
  • Number of household connections provided with grid and mini-grid under the project of which female headedValue0.000.00235000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Number of grid and mini-grid connections provided under the project, of which refugeesValue0.000.0050000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Number of off-grid household connections provided under the projectValue0.000.00115000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Establishment and adequate functioning of PIU at MEMDValueAdequately functioning PIU not in place, reportingEstablished(A) 26 key staff specialists are retained througho
    DateJanuary 31, 2022July 20, 2023June 30, 2027
    Comment
  • MV/LV network constructed under the project in refugee-hosting districtsValue0.000.003550.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Commercial enterprises electrified under the project, grid and mini-gridValue0.000.0030000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Establishment and adequate functioning of PIU at UECCCValueAdequately functioning PIU not in place, reportingEstablished(A) 15 key staff specialists are retained througho
    DateJanuary 31, 2022July 20, 2023June 30, 2027
    Comment
  • Number of off-grid household connections provided under the project to female headed householdsValue0.000.0028750.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Commercial enterprises and institutions electrified under the project with grid and mini-grid connections in refugee-hosting districtsValue0.000.003500.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • MEMD optimizes investments for electricity access scale-upValueLack of optimized grid rolloutDecision not made yet
    DateJanuary 31, 2022December 19, 2023June 30, 2025
    Comment
  • Commercial enterprises electrified under the project, grid and mini-grid of which female ledValue0.000.0011400.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Commercial enterprises and institutions electrified under the project with grid and mini-grid connections, of which refugeesValue0.000.001750.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Number of clean cooking solutions providedValue0.000.00300000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Establishment by MEMD of an Enabling Environment for Energy Access scale-upValueLimited capacity for environmental, social, healthNot achieved yet(A) Environmental & social instruments and tools i
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Number of off-grid connections provided under the project in refugee-hosting districtsValue0.000.0027000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Public institutions provided with off-grid accessValue0.000.00500.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • UECCC conducts adequate monitoring of the energy market financingValueLack of adequate understanding of nation-wide enerNot achieved yetAdequate monitoring and challenge response in supp
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Number of off-grid connections provided under the project, of which refugeesValue0.000.0013500.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Commercial enterprises electrified under the project with off-grid solutions in refugee-hosting districtsValue0.000.003000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Productive uses technologies financedValue0.000.004000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Productive uses technologies financed of which female recipientsValue0.000.001200.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Commercial enterprises electrified under the project, of which refugeesValue0.000.001500.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Productive uses technologies distributed under the project in refugee-hosting districtsValue0.000.005000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Commercial enterprises benefited from modern energy solutionsValue0.000.005000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Productive uses technologies distributed to refugees customersValue0.000.002500.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Commercial enterprises benefited from modern energy solutions of which female-ledValue0.000.001750.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Number of clean cooking solutions provided under the project in refugee-hosting districtsValue0.000.0053000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Number of clean cooking solutions provided under the project in refugee-hosting districts, of which refugeesValue0.000.0026000.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Energy savings from the projectValue0.000.002628.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Public institutions provided with off-grid access in refugee-hosting districtsValue0.000.00200.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment
  • Number of public institutions provided with clean cooking solutions in refugee-hosting districtsValue0.000.0050.00
    DateJanuary 31, 2022December 19, 2023June 30, 2027
    Comment