Financier | Commitments |
---|---|
IDA Grant | 35.00 |
P166695
Closed
Michael Jelenic , Munkyung Park
THE GAMBIA
December 26, 2018
(as of board presentation)
June 4, 2020
July 28, 2020
US$ 35.00 million
Ministry of Finance and Economic Affairs
2020
US$ 35.00 million
N/A
Moderate
June 30, 2024
No
BANK APPROVED
May 2, 2024
Financier | Commitments |
---|---|
IDA Grant | 35.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 35.00 |
IBRD + IDA Commitment | 35.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 35.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 3, 2023 | IDA-D6190 | Loan Disb | 635,979.30 |
Jan 11, 2024 | IDA-D6190 | Loan Disb | 240,061.45 |
Dec 13, 2023 | IDA-D6190 | Loan Disb | 277,814.72 |
Nov 10, 2023 | IDA-D6190 | Loan Disb | 408,940.00 |
May 19, 2023 | IDA-D6190 | Loan Disb | 410,005.38 |
May 31, 2023 | IDA-D6190 | Loan Cancel | 13,445,256.00 |
Aug 22, 2023 | IDA-D6190 | Loan Disb | 137,300.40 |
Oct 11, 2023 | IDA-D6190 | Loan Disb | 283,263.94 |
Jul 26, 2023 | IDA-D6190 | Loan Disb | 238,423.02 |
Jun 21, 2021 | IDA-D6190 | Loan Disb | 427,464.47 |
Sep 11, 2023 | IDA-D6190 | Loan Disb | 500,000.00 |
Sep 11, 2023 | IDA-D6190 | Loan Disb | 386,363.94 |
Jun 9, 2023 | IDA-D6190 | Loan Disb | 427,829.22 |
Jun 4, 2020 | IDA-D6190 | Loan Commitment | 35,000,000.00 |
Jun 11, 2024 | IDA-D6190 | Loan Disb | 964,397.40 |
Apr 17, 2024 | IDA-D6190 | Loan Cancel | 2,027,969.20 |
Apr 10, 2024 | IDA-D6190 | Loan Disb | 145,365.34 |
Jul 15, 2024 | IDA-D6190 | Loan Disb | 1,271,835.50 |
Mar 29, 2024 | IDA-D6190 | Loan Disb | 236,762.05 |
Oct 19, 2022 | IDA-D6190 | Loan Disb | 349,676.53 |
Aug 14, 2020 | IDA-D6190 | Loan Disb | 1,500,000.00 |
Jul 1, 2024 | IDA-D6190 | Loan Disb | 500,000.00 |
Nov 6, 2023 | IDA-D6190 | Loan Disb | 4,000,000.00 |
Nov 6, 2020 | IDA-D6190 | Loan Disb | 1,657,496.50 |
Jun 21, 2022 | IDA-D6190 | Loan Disb | 332,290.20 |
Jul 1, 2022 | IDA-D6190 | Loan Disb | 250,000.00 |
May 16, 2022 | IDA-D6190 | Loan Disb | 1,639,873.10 |
May 23, 2024 | IDA-D6190 | Loan Disb | 407,054.12 |
Sep 2, 2022 | IDA-D6190 | Loan Disb | 776,078.60 |
Feb 15, 2023 | IDA-D6190 | Loan Disb | 223,919.77 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2024-06-27 |
Financial Management | Satisfactory | 2024-06-27 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-06-27 |
Monitoring and Evaluation | Satisfactory | 2024-06-27 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-06-27 |
Project Management | Moderately Satisfactory | 2024-06-27 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of on-time tax filing rates | Value | 0.00 | 0.00 | 0.00 |
Date | December 31, 2022 | April 1, 2024 | June 30, 2024 | |
Comment |
Performance audit reports of SOE prepared by the National Audit Office and discussed with the Public Enterprises Committee of the National Assembly and published on the website of the MoFEA | Value | 1.00 | 3.00 | 5.00 |
Date | December 31, 2022 | April 1, 2024 | June 30, 2024 | |
Comment |
CIT and PIT taxes by large taxpayers | Value | 89.00 | 85.30 | 0.00 |
Date | ||||
Comment |
Percentage of government procurement tenders by value that are single sourced | Value | 27.00 | 6.98 | 22.00 |
Date | December 31, 2022 | April 1, 2024 | June 30, 2024 | |
Comment |
VAT by all VAT registrants | Value | 28.00 | 48.80 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Tax Directorate established and tax expenditure policy developed by the Ministry of Finance and Economic Affairs. | Value | No | Yes | Yes |
Date | December 31, 2022 | April 1, 2024 | June 30, 2024 | |
Comment |
Comprehensive SOE Bill including adequate institutional framework | Value | Current legal and institutional framework is chara | SOE Act Adopted by the National Assembly | SOE Act adopted by the National Assembly |
Date | July 31, 2019 | October 9, 2023 | June 30, 2024 | |
Comment |
Number of GRA staff trained on Tax Compliance, Risk Management, and Project Management for effective implementation and oversight projects | Value | 0.00 | 72.00 | 58.00 |
Date | December 31, 2022 | April 1, 2024 | June 30, 2024 | |
Comment |
Performance contracts signed with the main corporatized State-Owned Enterprises | Value | 0.00 | 8.00 | 2.00 |
Date | July 31, 2019 | April 1, 2024 | June 30, 2024 | |
Comment |
Dissemination of e-GP readiness assessment report to public and private stakeholders | Value | No | Yes | Yes |
Date | December 31, 2022 | April 1, 2024 | June 30, 2024 | |
Comment |
Aggregate annual SOEs report prepared and published by the Directorate of State-Owned Enterprises (MOFEA) on a timely basis | Value | None | Yes | Yes |
Date | December 31, 2022 | April 1, 2024 | June 30, 2024 | |
Comment |
Certified procurement professionals in the procuring organizations | Value | 0.00 | 80.00 | 50.00 |
Date | December 31, 2022 | April 1, 2024 | June 30, 2024 | |
Comment |
Establishment of a centralized and independent regulatory agency (SOE Commission), approved by law to monitor financial and operational performance of the SOEs in its portfolio | Value | No | Yes | Yes |
Date | December 31, 2022 | April 1, 2024 | June 30, 2024 | |
Comment |
Internal Audit charter and audit manual for SOEs developed and approved by Management | Value | 0.00 | 10.00 | 8.00 |
Date | December 31, 2022 | April 1, 2024 | June 30, 2024 | |
Comment |
Certified women procurement professionals in the procuring organizations | Value | 0.00 | 46.00 | 0.00 |
Date | ||||
Comment |