Kingdom of Eswatini: Water Supply and Sanitation Access Project

Abstract*

The objective of the Water Supply and Sanitation Access Project for Eswatini is to increase access to improved water supply and sanitation services in targeted areas of Eswatini. The project has four components. (1) Resilient water access and management component will provide financing to increase potable water supply coverage in the Shiselweni region; improve long-term management of water resources, investment planning, and sustainability of water...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase access to improved water supply and sanitation services in targeted areas of Eswatini.

Key Details

Project Details

  • P166697

  • Active

  • Nathan Engle , Palesa Mokorosi

  • Ministry of Finance

  • Eswatini

  • February 6, 2019

  • (as of board presentation)

    October 10, 2019

  • June 17, 2020

  • US$ 45.00 million

  • Eswatini Water Services Corporation

  • Eastern and Southern Africa

  • 2020

  • US$ 45.00 million

  • N/A

  • Substantial

  • September 30, 2025

  • Yes

  • BANK APPROVED

  • January 3, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 45.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 45.00
IDA Commitment N/A
IBRD + IDA Commitment 45.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 45.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 10, 2019 IBRD-90120 Loan Commitment 45,000,000.00
Feb 16, 2024 IBRD-90120 Int Charges 43,058.49
Feb 16, 2024 IBRD-90120 Int Charges 391,279.72
Aug 15, 2024 IBRD-90120 Int Charges 556,225.00
Aug 15, 2024 IBRD-90120 Int Charges 36,617.20
Aug 15, 2024 IBRD-90120 Int Charges 1,986.87
Mar 18, 2024 IBRD-90120 Loan Disb 4,489,200.00
Jun 14, 2024 IBRD-90120 Loan Disb 3,035,922.00
Aug 24, 2023 IBRD-90120 Int Charges 350,597.53
Aug 24, 2023 IBRD-90120 Int Charges 42,384.77
Feb 15, 2023 IBRD-90120 Int Charges 161,702.97
Feb 15, 2023 IBRD-90120 Int Charges 48,388.32
Dec 7, 2022 IBRD-90120 Loan Disb 6,789,059.50
Feb 15, 2022 IBRD-90120 Int Charges 30,013.96
Feb 15, 2022 IBRD-90120 Int Charges 51,643.36
Aug 15, 2022 IBRD-90120 Int Charges 43,275.77
Aug 15, 2022 IBRD-90120 Int Charges 50,801.35
Feb 15, 2021 IBRD-90120 Int Charges 387.19
Feb 15, 2021 IBRD-90120 Int Charges 13,490.78
Aug 15, 2021 IBRD-90120 Int Charges 30,043.75
Aug 15, 2021 IBRD-90120 Int Charges 50,881.68
Feb 15, 2021 IBRD-90120 Int Charges 943.02
Feb 15, 2021 IBRD-90120 Int Charges 56,453.80
Feb 18, 2021 IBRD-90120 Loan Disb 3,909,620.00
Jun 17, 2020 IBRD-90120 Loan Disb 112,500.00
Jun 17, 2020 IBRD-90120 Fee Charges 112,500.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2024-12-12
Financial Management Satisfactory 2024-12-12
Progress towards achievement of PDO Moderately Satisfactory 2024-12-12
Project Management Moderately Satisfactory 2024-12-12
Monitoring and Evaluation Moderately Satisfactory 2024-12-12
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-12

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with access to improved water sourcesValue0.000.0018478.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • People provided with access to improved water sources - Female (RMS requirement)Value0.000.000.00
    Date
    Comment
  • People provided with access to improved sanitation servicesValue0.000.008000.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • People provided with access to improved sanitation services - Female (RMS requirement)Value0.000.000.00
    Date
    Comment
  • People reached through hygiene behavior awareness campaignsValue0.000.0038233.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Schools provided with improved water accessValue0.000.0032.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • Household containment facilities constructedValue0.000.002000.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • Health centers provided with improved water accessValue0.000.004.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • Sanitation facilities constructed in schoolsValue0.000.0032.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • Length of water pipeline constructedValue0.000.00305.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • Sanitation facilities constructed in health centersValue0.000.004.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • Grievances satisfactorily addressed with new grievance redress mechanismValue0.0063.00100.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • Develop and implement a drought monitoring and early warning systemValueNoNoYes
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • Reduction in open defecationValue12.0012.000.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • Women in the target area that spend 30 minutes or more to go to source of drinking water, get water and returnValue20.3020.3010.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment
  • Girls who benefited from having school sanitation with adequate WASH, MHM facilities and MHM education.Value0.000.002800.00
    DateSeptember 30, 2019November 9, 2023September 30, 2025
    Comment