Financier | Commitments |
---|---|
IDA Credit | 15.00 |
Education for All - Fast Track Initiative | 8.55 |
P166744
Active
Dung Vo
Democratic Republic of Timor-Leste
March 14, 2019
(as of board presentation)
April 22, 2020
August 11, 2020
US$ 23.55 million
Ministry of Education
2020
US$ 23.55 million
B
February 12, 2024
June 30, 2025
No
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 15.00 |
Education for All - Fast Track Initiative | 8.55 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 15.00 |
IBRD + IDA Commitment | 15.00 |
Lending Instrument | |
---|---|
Grant Amount | 8.55 |
Total Project Cost** | 23.55 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 22, 2020 | IDA-65510 | Loan Commitment | 15,000,000.00 |
Mar 15, 2024 | IDA-65510 | Int Charges | 1,526.05 |
Oct 11, 2022 | IDA-65510 | Loan Disb | 200,000.00 |
Mar 22, 2023 | IDA-65510 | Loan Disb | 84,360.00 |
Mar 15, 2023 | IDA-65510 | Int Charges | 677.81 |
Mar 15, 2023 | IDA-65510 | Int Charges | 677.81 |
Mar 15, 2024 | IDA-65510 | Int Charges | 1,526.05 |
Sep 15, 2023 | IDA-65510 | Int Charges | 137.90 |
Sep 15, 2023 | IDA-65510 | Int Charges | 1,544.42 |
Sep 15, 2023 | IDA-65510 | Int Charges | 1,544.42 |
Jan 19, 2023 | IDA-65510 | Loan Disb | 128,440.87 |
Mar 15, 2024 | IDA-65510 | Int Charges | 45.66 |
Mar 15, 2024 | IDA-65510 | Int Charges | 45.66 |
Sep 15, 2023 | IDA-65510 | Int Charges | 137.90 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Unsatisfactory | 2024-12-17 |
Project Management | Moderately Satisfactory | 2024-12-17 |
Financial Management | Moderately Satisfactory | 2024-12-17 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-17 |
Overall Implementation Progress (IP) | Unsatisfactory | 2024-12-17 |
Procurement | Moderately Satisfactory | 2024-12-17 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of students accessing classrooms meeting newly developed 21st Century School Standards (cumulative) | Value | 0.00 | 0.00 | 15360.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Share of basic education teachers in rural areas who utilize effective mathematics and language teaching approaches in the classroom | Value | 45.00 | 56.00 | 55.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Verified EMIS data utilized for the preparation of annual budgets and making infrastructure investment decisions | Value | No | No | Yes |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Number of students accessing classrooms meeting newly developed 21st Century School Standards--Female (cumulative) | Value | 0.00 | 0.00 | 7680.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Share of students in Cycles 1 and 2 who use individual textbooks in the classroom | Value | Unknown | 0.00 | TBD |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Total number of project beneficiaries | Value | 0.00 | 499.00 | 149100.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Total number of project beneficiaries - Female (cumulative) | Value | 0.00 | 135.00 | 74085.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Students benefiting from direct interventions to enhance learning | Value | 0.00 | 0.00 | 144000.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Students benefiting from direct interventions to enhance learning - Female | Value | 0.00 | 0.00 | 24000.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Development/upgrade and use of standards for infrastructure | Value | Standards under development | Not achieved. Standards have been adopted. | All new public school infrastructure development c |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Share of basic education schools that receive full package of teaching-learning materials | Value | 50.00 | 0.00 | 90.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Teachers recruited or trained | Value | 0.00 | 0.00 | 4500.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Integrated platform for EMIS and other applications (Gestão Escolar) developed (with provisions for accessing gender specific data) | Value | Gestion Escolar platform not operational | Not achieved. EMIS policy expected end of February | Gestion Escolar platform operational |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Review of education sector progress, including progress on project activities, through stakeholder consultation and community engagement | Value | Formal community consultation not done | Not achieved. No stakeholder consultation has been | Conducted in Baucau, Viqueque |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Development/upgrade and use of new infrastructure development prioritization system | Value | Prioritization system under development | Partially achieved. Use of prioritization system f | All schools targeted for infrastructure developmen |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Share of Cycle 1 and 2 students in public schools with access to book corners/libraries in their classrooms | Value | 0.00 | 80.00 | 100.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Share of basic education schools completing electronic data entry in EMIS through the Gestão Escolar platform by March of the current academic year | Value | 0.00 | 0.00 | 80.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Teachers recruited or trained - Female (RMS requirement) | Value | 0.00 | 0.00 | 615.00 |
Date | ||||
Comment |
Feedback from beneficiaries has been used to make needed adjustments to the project | Value | No | No | Yes |
Date | ||||
Comment |
Implementation of school infrastructure census | Value | Old census data not sufficient | Partially achieved. Data collection completed. | School infrastructure survey report prepared and p |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Implementation of a sample-based nationally representative assessment of foundational literacy and numeracy skills of students in grades 2 and 3 (results disaggregated by gender) | Value | Nationally representative assessment not done | Not applicable. No Year 3 target defined. | Second assessment report published |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Independent verification of EMIS data completed | Value | Independent verification of EMIS data not done | Not applicable. No Year 3 target defined. | EMIS data updated incorporating finding from the v |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Number of teachers trained | Value | 0.00 | 0.00 | 4500.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Number of classrooms meeting minimum standards in basic education schools (cumulative) | Value | 0.00 | 0.00 | 200.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Share of teachers monitored using a classroom observation tool | Value | 25.00 | 19.00 | 75.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Number of school leaders who completed the new leadership training (cumulative) | Value | 0.00 | 0.00 | 600.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Share of females among those completing the new leadership training program during the current fiscal year | Value | 25.00 | 28.00 | 40.00 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |
Female-male difference in primary net enrollment rate (percentage points) | Value | 5.97 | 10.69 | 3.50 |
Date | April 22, 2020 | October 15, 2023 | June 30, 2025 | |
Comment |