Financier | Commitments |
---|---|
Clean Technology Fund | 93.00 |
IDA Credit | 75.00 |
GLOBAL INFRASTRUCTURE FACILITY | 0.70 |
P166785
Active
Regina Nesiama Miller , Raluca Golumbeanu, Leopold Sedogo
Burkina Faso
February 25, 2019
(as of board presentation)
June 21, 2021
June 22, 2022
US$ 607.70 million
SONABEL,Ministry of Energy,ABER
2021
US$ 168.70 million
N/A
February 8, 2024
December 31, 2028
TBD
BANK APPROVED
Financier | Commitments |
---|---|
Clean Technology Fund | 93.00 |
IDA Credit | 75.00 |
GLOBAL INFRASTRUCTURE FACILITY | 0.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 75.00 |
IBRD + IDA Commitment | 75.00 |
Lending Instrument | |
---|---|
Grant Amount | 93.70 |
Total Project Cost** | 607.70 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 21, 2021 | TF-B5744 | Loan Commitment | 91,000,000.00 |
Mar 4, 2024 | IDA-69190 | Int Charges | 6,206.79 |
Jul 5, 2024 | IDA-69190 | Loan Disb | 10,896.14 |
Feb 29, 2024 | IDA-69190 | Loan Disb | 2,711.18 |
Sep 4, 2023 | IDA-69190 | Int Charges | 6,177.07 |
Sep 4, 2023 | IDA-69190 | Int Charges | 6,177.07 |
Sep 4, 2023 | IDA-69190 | Int Charges | 995.19 |
Sep 4, 2023 | IDA-69190 | Int Charges | 995.19 |
Nov 22, 2023 | IDA-69190 | Loan Disb | 144.28 |
Feb 2, 2023 | IDA-69190 | Loan Disb | 1,676,786.80 |
May 15, 2024 | IDA-69190 | Loan Disb | 32,330.25 |
May 7, 2024 | IDA-69190 | Loan Disb | 667.86 |
Jun 21, 2021 | IDA-69190 | Loan Commitment | 75,000,000.00 |
Mar 4, 2024 | IDA-69190 | Int Charges | 6,206.79 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-09-15 |
Procurement | Moderately Satisfactory | 2024-09-15 |
Financial Management | Moderately Satisfactory | 2024-09-15 |
Project Management | Satisfactory | 2024-09-15 |
Monitoring and Evaluation | Satisfactory | 2024-09-15 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-09-15 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Generation capacity of energy constructed or rehabilitated | Value | 0.00 | 0.00 | 325.00 |
Date | June 1, 2020 | June 13, 2023 | June 2, 2025 | |
Comment |
VRE integration capacity enabled by the project | Value | 0.00 | 0.00 | 150.00 |
Date | June 1, 2020 | June 13, 2023 | June 2, 2025 | |
Comment |
Private investments mobilized | Value | 0.00 | 0.00 | 439000000.00 |
Date | June 1, 2020 | June 13, 2023 | June 2, 2025 | |
Comment |
Avoided GHG emission (tCO2e per year) | Value | 0.00 | 0.00 | 318000.00 |
Date | May 29, 2020 | June 13, 2023 | November 20, 2025 | |
Comment |
Renewable energy generation capacity (other than hydropower) constructed under the project | Value | 0.00 | 0.00 | 325.00 |
Date | June 1, 2020 | June 13, 2023 | June 2, 2025 | |
Comment |
People provided with new or improved electricity service | Value | 0.00 | 0.00 | 700000.00 |
Date | June 1, 2020 | June 13, 2023 | June 2, 2025 | |
Comment |
People provided with new or improved electricity service - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People provided with access to electricity under the project by household connections (grid or off-grid). | Value | 0.00 | 0.00 | 700000.00 |
Date | June 1, 2020 | June 13, 2023 | June 2, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Financial closing achieved for the phase 1 of the Regional Solar Parks | Value | No | No | Yes |
Date | June 1, 2020 | June 13, 2023 | December 6, 2021 | |
Comment |
Recruitment of transaction advisory firm with requisite legal, financial and technical expertise for anchor customers VRE IPP project | Value | No | No | Yes |
Date | June 1, 2020 | June 13, 2023 | October 5, 2020 | |
Comment |
Financial closing achieved for the first green mini-grid development and operation by concessionaire | Value | No | No | Yes |
Date | June 13, 2023 | June 13, 2023 | June 7, 2021 | |
Comment |
Installed capacity of battery storage | Value | 0.00 | 0.00 | 0.32 |
Date | May 5, 2021 | June 13, 2023 | December 31, 2026 | |
Comment |
Share of female-headed households provided with new or improved electricity services | Value | 0.00 | 0.00 | 7.00 |
Date | July 30, 2021 | June 13, 2023 | October 30, 2025 | |
Comment |
Percentage of women working in mini-grid operations | Value | 0.00 | 0.00 | 20.00 |
Date | July 30, 2021 | June 13, 2023 | October 30, 2025 | |
Comment |
Grievances received and addressed through the project’s Grievance Redress Mechanism within the specified timeframe | Value | 0.00 | 0.00 | 90.00 |
Date | June 14, 2021 | June 13, 2023 | June 30, 2025 | |
Comment |