Financier | Commitments |
---|---|
FRANCE: French Agency for Development | 167.00 |
International Bank for Reconstruction and Development | 250.00 |
P166805
Active
Leonardo Tshama , Samuel Oguah
Instituto Regulador dos Serviços de Electricidade e de Águas,Republic of Angola
December 20, 2018
(as of board presentation)
February 18, 2021
February 25, 2022
US$ 417.00 million
Ministerio da Energia e Aguas
2021
US$ 417.00 million
N/A
April 9, 2024
March 30, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
FRANCE: French Agency for Development | 167.00 |
International Bank for Reconstruction and Development | 250.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 250.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 250.00 |
Lending Instrument | |
---|---|
Grant Amount | 167.00 |
Total Project Cost** | 417.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 18, 2021 | IBRD-92040 | Loan Commitment | 250,000,000.00 |
Apr 3, 2024 | IBRD-92040 | Loan Disb | 16,000.00 |
Apr 3, 2024 | IBRD-92040 | Loan Disb | 16,946.23 |
Apr 3, 2024 | IBRD-92040 | Loan Disb | 29,860.00 |
Aug 22, 2024 | IBRD-92040 | Loan Disb | 17,119.64 |
Oct 6, 2023 | IBRD-92040 | Loan Disb | 9,091.01 |
Aug 7, 2024 | IBRD-92040 | Loan Disb | 17,163.88 |
Jul 30, 2024 | IBRD-92040 | Loan Disb | 21,934.09 |
May 3, 2024 | IBRD-92040 | Loan Disb | 16,006.00 |
May 3, 2024 | IBRD-92040 | Loan Disb | 6,144.09 |
Aug 7, 2024 | IBRD-92040 | Loan Disb | 1,229,606.00 |
Jul 30, 2024 | IBRD-92040 | Loan Disb | 12,023.20 |
Jul 30, 2024 | IBRD-92040 | Loan Disb | 9,587.63 |
May 28, 2024 | IBRD-92040 | Loan Disb | 16,121.39 |
May 28, 2024 | IBRD-92040 | Loan Disb | 17,000.00 |
May 28, 2024 | IBRD-92040 | Loan Disb | 9,587.63 |
May 28, 2024 | IBRD-92040 | Loan Disb | 6,143.87 |
May 28, 2024 | IBRD-92040 | Loan Disb | 12,070.90 |
Jun 24, 2024 | IBRD-92040 | Loan Disb | 9,587.63 |
Jun 24, 2024 | IBRD-92040 | Loan Disb | 16,011.79 |
Jun 24, 2024 | IBRD-92040 | Loan Disb | 20,532.24 |
May 28, 2024 | IBRD-92040 | Loan Disb | 22,181.38 |
Jun 24, 2024 | IBRD-92040 | Loan Disb | 12,103.12 |
Jun 24, 2024 | IBRD-92040 | Loan Disb | 17,803.61 |
May 3, 2024 | IBRD-92040 | Loan Disb | 20,439.11 |
May 3, 2024 | IBRD-92040 | Loan Disb | 9,587.63 |
May 3, 2024 | IBRD-92040 | Loan Disb | 12,068.40 |
May 21, 2024 | IBRD-92040 | Loan Disb | 17,122.74 |
May 21, 2024 | IBRD-92040 | Loan Disb | 22,165.44 |
Jun 10, 2024 | IBRD-92040 | Loan Cancel | 20,000,000.00 |
Feb 15, 2024 | IBRD-92040 | Int Charges | 161.35 |
Feb 15, 2024 | IBRD-92040 | Int Charges | 4,124.71 |
Feb 15, 2024 | IBRD-92040 | Int Charges | 153,714.83 |
Feb 15, 2024 | IBRD-92040 | Int Charges | 155,857.34 |
Feb 15, 2024 | IBRD-92040 | Int Charges | 153,714.83 |
Feb 2, 2024 | IBRD-92040 | Loan Disb | 17,909.66 |
Jul 30, 2024 | IBRD-92040 | Loan Disb | 17,119.77 |
Aug 7, 2024 | IBRD-92040 | Loan Disb | 6,138.67 |
Aug 7, 2024 | IBRD-92040 | Loan Disb | 6,136.13 |
Sep 26, 2023 | IBRD-92040 | Loan Disb | 20,706.04 |
Sep 26, 2023 | IBRD-92040 | Loan Disb | 17,089.44 |
Aug 4, 2023 | IBRD-92040 | Loan Disb | 29,603.01 |
Aug 15, 2023 | IBRD-92040 | Int Charges | 106,080.49 |
Aug 15, 2023 | IBRD-92040 | Int Charges | 27.43 |
Aug 3, 2023 | IBRD-92040 | Loan Disb | 29,603.01 |
Jul 27, 2023 | IBRD-92040 | Loan Disb | 12,600.73 |
Jul 27, 2023 | IBRD-92040 | Loan Disb | 17,149.97 |
Jul 27, 2023 | IBRD-92040 | Loan Disb | 18,795.65 |
Jul 27, 2023 | IBRD-92040 | Loan Disb | 16,564.35 |
Aug 30, 2023 | IBRD-92040 | Loan Disb | 6,291.00 |
Aug 30, 2023 | IBRD-92040 | Loan Disb | 17,095.53 |
Aug 15, 2023 | IBRD-92040 | Int Charges | 199,696.27 |
Aug 15, 2023 | IBRD-92040 | Int Charges | 516.63 |
Aug 15, 2024 | IBRD-92040 | Int Charges | 10.99 |
Aug 15, 2024 | IBRD-92040 | Int Charges | 217,669.39 |
Aug 15, 2024 | IBRD-92040 | Int Charges | 8,050.74 |
Nov 14, 2023 | IBRD-92040 | Loan Disb | -11,980.00 |
Aug 15, 2024 | IBRD-92040 | Int Charges | 1,068.09 |
Dec 12, 2023 | IBRD-92040 | Loan Disb | 22,152.39 |
Dec 12, 2023 | IBRD-92040 | Loan Disb | 6,147.38 |
Dec 12, 2023 | IBRD-92040 | Loan Disb | 12,079.64 |
Dec 12, 2023 | IBRD-92040 | Loan Disb | 17,087.22 |
Mar 10, 2023 | IBRD-92040 | Loan Disb | 12,198.99 |
Feb 2, 2023 | IBRD-92040 | Loan Disb | 12,921.87 |
Feb 6, 2023 | IBRD-92040 | Loan Disb | 12,000.01 |
Feb 14, 2023 | IBRD-92040 | Loan Disb | 923,427.50 |
Oct 31, 2023 | IBRD-92040 | Loan Disb | 20,771.07 |
Oct 31, 2023 | IBRD-92040 | Loan Disb | 6,145.29 |
Oct 31, 2023 | IBRD-92040 | Loan Disb | 17,077.28 |
Oct 31, 2023 | IBRD-92040 | Loan Disb | 12,000.00 |
May 19, 2023 | IBRD-92040 | Loan Disb | 17,226.42 |
May 19, 2023 | IBRD-92040 | Loan Disb | 17,000.00 |
May 19, 2023 | IBRD-92040 | Loan Disb | 17,837.22 |
May 19, 2023 | IBRD-92040 | Loan Disb | 12,000.01 |
Jun 26, 2023 | IBRD-92040 | Loan Disb | 368,779.34 |
Jun 30, 2023 | IBRD-92040 | Loan Disb | 17,118.86 |
Jun 30, 2023 | IBRD-92040 | Loan Disb | 15,000.00 |
Jun 30, 2023 | IBRD-92040 | Loan Disb | 18,142.09 |
May 19, 2023 | IBRD-92040 | Loan Disb | 3,515.78 |
May 19, 2023 | IBRD-92040 | Loan Disb | 11,791.48 |
May 22, 2023 | IBRD-92040 | Loan Disb | 17,000.00 |
Sep 26, 2023 | IBRD-92040 | Loan Disb | 6,290.76 |
May 30, 2023 | IBRD-92040 | Loan Disb | 22,729.67 |
May 30, 2023 | IBRD-92040 | Loan Disb | 18,466.32 |
May 30, 2023 | IBRD-92040 | Loan Disb | 17,180.90 |
May 30, 2023 | IBRD-92040 | Loan Disb | 12,000.01 |
May 30, 2023 | IBRD-92040 | Loan Disb | 12,000.01 |
Sep 26, 2023 | IBRD-92040 | Loan Disb | 17,075.39 |
Sep 26, 2023 | IBRD-92040 | Loan Disb | 12,089.94 |
Aug 15, 2022 | IBRD-92040 | Int Charges | 576,833.80 |
Aug 15, 2022 | IBRD-92040 | Int Charges | 17,563.03 |
Feb 25, 2022 | IBRD-92040 | Loan Disb | 625,000.00 |
Feb 25, 2022 | IBRD-92040 | Fee Charges | 625,000.00 |
Dec 12, 2023 | IBRD-92040 | Loan Disb | 17,052.92 |
Dec 12, 2023 | IBRD-92040 | Loan Disb | 12,000.00 |
Jan 16, 2024 | IBRD-92040 | Loan Disb | 19,175.26 |
May 24, 2023 | IBRD-92040 | Loan Disb | 12,000.00 |
May 24, 2023 | IBRD-92040 | Loan Disb | 12,000.01 |
May 19, 2023 | IBRD-92040 | Loan Disb | 12,066.94 |
May 19, 2023 | IBRD-92040 | Loan Disb | 17,000.00 |
May 19, 2023 | IBRD-92040 | Loan Disb | 17,000.00 |
May 19, 2023 | IBRD-92040 | Loan Disb | 12,078.92 |
Oct 31, 2023 | IBRD-92040 | Loan Disb | 8,000.00 |
Nov 29, 2023 | IBRD-92040 | Loan Disb | 18,594.20 |
Nov 29, 2023 | IBRD-92040 | Loan Disb | 17,075.21 |
Nov 29, 2023 | IBRD-92040 | Loan Disb | 6,144.98 |
Nov 29, 2023 | IBRD-92040 | Loan Disb | 12,152.58 |
Nov 29, 2023 | IBRD-92040 | Loan Disb | 19,860.12 |
Oct 31, 2023 | IBRD-92040 | Loan Disb | 18,613.66 |
Jan 26, 2024 | IBRD-92040 | Loan Disb | 6,144.79 |
Jan 26, 2024 | IBRD-92040 | Loan Disb | 9,587.63 |
Jan 31, 2024 | IBRD-92040 | Loan Disb | 12,000.00 |
Jan 31, 2024 | IBRD-92040 | Loan Disb | 20,408.77 |
Aug 22, 2024 | IBRD-92040 | Loan Disb | 20,537.66 |
Aug 22, 2024 | IBRD-92040 | Loan Disb | 9,587.63 |
Feb 29, 2024 | IBRD-92040 | Loan Disb | 12,293.00 |
Feb 29, 2024 | IBRD-92040 | Loan Disb | 20,591.40 |
Feb 29, 2024 | IBRD-92040 | Loan Disb | 13,968.43 |
Aug 22, 2024 | IBRD-92040 | Loan Disb | 12,196.81 |
Aug 22, 2024 | IBRD-92040 | Loan Disb | 17,036.62 |
Aug 22, 2024 | IBRD-92040 | Loan Disb | 2,511.82 |
Aug 22, 2024 | IBRD-92040 | Loan Disb | 6,146.13 |
Feb 29, 2024 | IBRD-92040 | Loan Disb | 9,587.63 |
Feb 29, 2024 | IBRD-92040 | Loan Disb | 17,085.72 |
Feb 29, 2024 | IBRD-92040 | Loan Disb | 6,144.88 |
Aug 15, 2024 | IBRD-92040 | Int Charges | 293,937.78 |
Jun 10, 2024 | IBRD-92040 | Loan Disb | 4,207,454.00 |
Apr 3, 2024 | IBRD-92040 | Loan Disb | 16,000.00 |
Apr 3, 2024 | IBRD-92040 | Loan Disb | 2,133.33 |
Apr 3, 2024 | IBRD-92040 | Loan Disb | 9,587.63 |
Apr 3, 2024 | IBRD-92040 | Loan Disb | 21,675.18 |
Apr 15, 2024 | IBRD-92040 | Loan Disb | 7,425.82 |
Apr 15, 2024 | IBRD-92040 | Loan Disb | 12,064.79 |
Apr 3, 2024 | IBRD-92040 | Loan Disb | 16,178.64 |
Mar 2, 2022 | IBRD-92040 | Loan Disb | 1,056,552.50 |
Sep 12, 2022 | IBRD-92040 | Loan Disb | 18,696.12 |
Sep 12, 2022 | IBRD-92040 | Loan Disb | 24,130.17 |
Sep 12, 2022 | IBRD-92040 | Loan Disb | 54,631.77 |
Sep 12, 2022 | IBRD-92040 | Loan Disb | 12,240.26 |
Sep 12, 2022 | IBRD-92040 | Loan Disb | 12,108.66 |
Sep 12, 2022 | IBRD-92040 | Loan Disb | 19,893.33 |
Sep 12, 2022 | IBRD-92040 | Loan Disb | 17,446.87 |
Sep 12, 2022 | IBRD-92040 | Loan Disb | 12,143.92 |
Nov 21, 2022 | IBRD-92040 | Loan Disb | 12,096.17 |
Nov 21, 2022 | IBRD-92040 | Loan Disb | 12,096.17 |
Nov 21, 2022 | IBRD-92040 | Loan Disb | 12,954.33 |
Nov 21, 2022 | IBRD-92040 | Loan Disb | 17,715.02 |
Nov 21, 2022 | IBRD-92040 | Loan Disb | 16,283.31 |
Nov 21, 2022 | IBRD-92040 | Loan Disb | 12,000.01 |
Nov 21, 2022 | IBRD-92040 | Loan Disb | 12,095.13 |
Sep 16, 2022 | IBRD-92040 | Loan Disb | 12,095.13 |
Sep 16, 2022 | IBRD-92040 | Loan Disb | 12,095.13 |
Sep 16, 2022 | IBRD-92040 | Loan Disb | 36,252.66 |
Dec 19, 2022 | IBRD-92040 | Loan Disb | 12,000.01 |
Dec 19, 2022 | IBRD-92040 | Loan Disb | 12,098.69 |
Dec 19, 2022 | IBRD-92040 | Loan Disb | 12,096.17 |
Dec 19, 2022 | IBRD-92040 | Loan Disb | 12,183.47 |
Nov 21, 2022 | IBRD-92040 | Loan Disb | 12,000.01 |
Jul 18, 2023 | IBRD-92040 | Loan Disb | 12,000.01 |
Jul 18, 2023 | IBRD-92040 | Loan Disb | 12,000.01 |
Aug 15, 2023 | IBRD-92040 | Int Charges | 106,080.49 |
Aug 24, 2023 | IBRD-92040 | Loan Disb | 17,075.16 |
Aug 24, 2023 | IBRD-92040 | Loan Disb | 12,075.41 |
Aug 24, 2023 | IBRD-92040 | Loan Disb | 20,604.99 |
Jul 28, 2023 | IBRD-92040 | Loan Disb | 6,000.00 |
Jul 28, 2023 | IBRD-92040 | Loan Disb | 6,000.00 |
Feb 15, 2023 | IBRD-92040 | Int Charges | 48,157.95 |
Feb 15, 2023 | IBRD-92040 | Int Charges | 264,454.78 |
Feb 15, 2023 | IBRD-92040 | Int Charges | 48,157.95 |
Mar 10, 2023 | IBRD-92040 | Loan Disb | 12,000.01 |
Mar 10, 2023 | IBRD-92040 | Loan Disb | 70,948.29 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Unsatisfactory | 2025-01-28 |
Procurement | Moderately Unsatisfactory | 2025-01-28 |
Project Management | Moderately Unsatisfactory | 2025-01-28 |
Monitoring and Evaluation | Satisfactory | 2025-01-28 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-01-28 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-01-28 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduction of total system losses | Value | 39.00 | 39.00 | 29.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
People provided with new or improved electricity service | Value | 0.00 | 0.00 | 1002150.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Reduction of duration of outages at the transmission system level, SAIDI | Value | 483.00 | 483.00 | 230.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
People provided with new or improved electricity service - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People provided with access to electricity under the project by household connections (grid or off-grid). | Value | 0.00 | 0.00 | 196500.00 |
Date | July 16, 2020 | December 6, 2023 | September 30, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Distribution lines constructed or rehabilitated under the project | Value | 0.00 | 0.00 | 4800.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Upgrade of PRODEL's ERP completed | Value | No | No | Yes |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Upgraded National Dispatch Center (SCADA) operational installed under the project | Value | No | No | Yes |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Medium and low voltage transformers constructed under the project | Value | 0.00 | 0.00 | 730.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Number of meters installed and operational to monitor PRODEL's generation and billing | Value | 0.00 | 0.00 | 150.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Increase in installed capacity in transmission substations | Value | 0.00 | 0.00 | 160.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Smart meters installed to customers under a revenue protection program | Value | 0.00 | 0.00 | 15000.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Percentage of registered grievances related to service delivery resolved | Value | 0.00 | 0.00 | 100.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Transmission substations upgraded under the project | Value | 0.00 | 0.00 | 2.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Female-headed households provided with new or improved electricity services | Value | 0.00 | 0.00 | 22.00 |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
Business processes reengineering and upgrades of existing information systems for management of corporate resources | Value | No | No | Yes |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |
PCU published reports on beneficiary feedback, including gender disaggregated data | Value | No | No | Yes |
Date | February 18, 2021 | December 6, 2023 | September 30, 2026 | |
Comment |