Financier | Commitments |
---|---|
South Asia Regional Integration Partnership | 1.00 |
IDA Grant | 131.00 |
P166820
Active
Abdul Khalili , Muhammad Zulfiqar Ahmed, Sudeshna Mitra
Ministry of Finance
Central Asia
December 16, 2019
(as of board presentation)
July 30, 2020
November 12, 2021
US$ 132.00 million
Ministry of Transport,Customs Service
2021
US$ 132.00 million
N/A
May 12, 2024
October 31, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
South Asia Regional Integration Partnership | 1.00 |
IDA Grant | 131.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 131.00 |
IBRD + IDA Commitment | 131.00 |
Lending Instrument | |
---|---|
Grant Amount | 1.00 |
Total Project Cost** | 132.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 11, 2023 | IDA-D6990 | Loan Disb | 1,068,849.50 |
Oct 23, 2023 | IDA-D6990 | Loan Disb | 220,255.78 |
Nov 6, 2023 | IDA-D6990 | Loan Disb | 815,861.30 |
Nov 15, 2023 | IDA-D6990 | Loan Disb | 2,267,193.20 |
Jan 4, 2024 | IDA-D6990 | Loan Disb | 976,638.50 |
Jan 8, 2024 | IDA-D6990 | Loan Disb | 229,239.42 |
Nov 20, 2023 | IDA-D6990 | Loan Disb | 532,468.94 |
Nov 16, 2023 | IDA-D6990 | Loan Disb | 1,409,376.90 |
Nov 16, 2023 | IDA-D6990 | Loan Disb | 1,564,187.10 |
Nov 16, 2023 | IDA-D6990 | Loan Disb | 1,745,402.40 |
Jan 4, 2024 | IDA-D6990 | Loan Disb | 1,353,922.80 |
Nov 20, 2023 | IDA-D6990 | Loan Disb | 409,922.03 |
Oct 18, 2023 | IDA-D6990 | Loan Disb | 939,540.60 |
Jun 29, 2023 | IDA-D6990 | Loan Disb | 533,665.10 |
Jun 26, 2023 | IDA-D6990 | Loan Disb | 3,128,374.20 |
Jun 26, 2023 | IDA-D6990 | Loan Disb | 2,267,193.20 |
Aug 7, 2024 | IDA-D6990 | Loan Disb | 1,017,244.40 |
Aug 7, 2024 | IDA-D6990 | Loan Disb | 928,248.06 |
Jun 3, 2024 | IDA-D6990 | Loan Disb | 217,326.50 |
Jun 3, 2024 | IDA-D6990 | Loan Disb | 416,031.60 |
Jun 28, 2024 | IDA-D6990 | Loan Disb | 1,030,306.40 |
Jun 28, 2024 | IDA-D6990 | Loan Disb | 984,619.25 |
Mar 7, 2024 | IDA-D6990 | Loan Disb | 998,879.44 |
Apr 24, 2024 | IDA-D6990 | Loan Disb | 229,690.61 |
May 29, 2024 | IDA-D6990 | Loan Disb | 1,185,198.00 |
Mar 7, 2024 | IDA-D6990 | Loan Disb | 1,820,794.90 |
May 22, 2024 | IDA-D6990 | Loan Disb | 1,126,599.10 |
Jul 3, 2024 | IDA-D6990 | Loan Disb | 237,240.95 |
Jun 4, 2024 | IDA-D6990 | Loan Disb | 1,744,318.20 |
Jun 4, 2024 | IDA-D6990 | Loan Disb | 452,970.78 |
Mar 15, 2024 | IDA-D6990 | Loan Disb | 234,637.95 |
Apr 22, 2024 | IDA-D6990 | Loan Disb | 975,312.70 |
Dec 28, 2022 | IDA-D6990 | Loan Disb | 4,534,386.50 |
Jul 30, 2020 | IDA-D6990 | Loan Commitment | 131,000,000.00 |
Aug 9, 2024 | IDA-D6990 | Loan Disb | 225,167.52 |
Dec 5, 2022 | IDA-D6990 | Loan Disb | 423,284.10 |
Dec 22, 2021 | IDA-D6990 | Loan Disb | 2,000,000.00 |
Jun 28, 2022 | IDA-D6990 | Loan Disb | 3,850,193.00 |
Mar 9, 2022 | IDA-D6990 | Loan Disb | 1,000,000.00 |
Jun 27, 2023 | IDA-D6990 | Loan Disb | 1,564,187.10 |
Aug 10, 2023 | IDA-D6990 | Loan Disb | 237,600.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-05-23 |
Procurement | Satisfactory | 2024-05-23 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-05-23 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-05-23 |
Financial Management | Satisfactory | 2024-05-23 |
Project Management | Satisfactory | 2024-05-23 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Average travel time between Kannibodam and Bekobod BCP | Value | 210.00 | 210.00 | 126.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Market accessibility index of Sughd region | Value | 0.00 | 0.00 | 0.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Road closures per year in Barsem caused by natural hazards | Value | 720.00 | 720.00 | 120.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Average time spent for customs clearance | Value | 834.00 | 625.00 | 584.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Road crashes or fatalities along the main routes in Khorog | Value | 12.00 | 12.00 | 6.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Average time spent for customs clearance for import | Value | 1112.00 | 922.00 | 778.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Average time spent for customs clearance for export | Value | 556.00 | 328.00 | 389.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehablitated | Value | 0.00 | 0.00 | 50.50 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Size of road network with baseline geometry, location, condition, traffic volume, and natural hazard exposure data are collected | Value | 0.00 | 2128.00 | 7000.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Establishment of customs procedures for paper-free clearance operations, including electronic payment of duties, taxes and fees | Value | No | No | Yes |
Date | June 4, 2020 | September 30, 2023 | December 31, 2022 | |
Comment |
Preparation of five-year and annual road maintenance plan and budget | Value | No | No | Yes |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Implementation of procedures for lodgement of pre-arrival information and risk-based border clearance | Value | There is no established customs procedures for pro | There is no established customs procedures for pro | Customs procedures are established for processing |
Date | May 20, 2020 | September 30, 2023 | December 31, 2024 | |
Comment |
Roads rehabilitated - rural | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Road sections where barriers have been retrofitted | Value | 0.00 | 0.00 | 40.00 |
Date | May 6, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Detailed implementation plan for customs automation | Value | Not prepared | Not prepared | Developed and adopted by the government (target by |
Date | June 4, 2020 | September 30, 2023 | December 31, 2024 | |
Comment |
Roads rehabilitated - non-rural | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Climate resilient structure constructed in project areas in GBAO | Value | 0.00 | 0.00 | 3.80 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Safety belt compliance | Value | 20.00 | 20.00 | 60.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Implementation of customs automation pilot | Value | No | No | Yes |
Date | May 7, 2020 | September 30, 2023 | December 31, 2025 | |
Comment |
Average daily traffic volume passing through Khorog Bridge | Value | 1233.00 | 1318.00 | 1480.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Adoption of a National Road Safety Strategy | Value | No | No | Yes |
Date | June 4, 2020 | September 30, 2023 | December 31, 2023 | |
Comment |
Female customs officers at managerial level as share of total managers | Value | 5.00 | 5.00 | 10.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Communities in target areas with effective citizen engagement channels | Value | 0.00 | 0.00 | 60.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Female customs inspectors as a share of total inspectors | Value | 10.50 | 10.50 | 20.00 |
Date | June 4, 2020 | September 30, 2023 | October 31, 2026 | |
Comment |
Road construction jobs created for the local community | Value | 0.00 | 271.00 | 350.00 |
Date | June 4, 2020 | September 30, 2023 | December 31, 2023 | |
Comment |