Lesotho Renewable Energy & Energy Access Project

Abstract*

The development objective of Renewable Energy and Energy Access Project is to increase access to electricity in rural and peri-urban areas of Lesotho. This project has three components. 1) The first component, Grid Extension to Peri-Urban Areas of Lesotho, aims to finance the design, procurement of materials, and construction works required to electrify selected industrial and commercial loads in peri-urban areas of Lesotho, as well as provide connections...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to increase access to electricity in rural and peri-urban areas of Lesotho.

Key Details

Project Details

  • P166936

  • Active

  • Leesle Hong , Miarintsoa Rakotondramanana

  • Kingdom of Lesotho

  • Lesotho

  • March 25, 2019

  • (as of board presentation)

    January 30, 2020

  • July 31, 2020

  • US$ 52.90 million

  • Ministry of Energy and Meteorology

  • Eastern and Southern Africa

  • 2020

  • US$ 52.90 million

  • B

  • April 11, 2024

  • January 31, 2027

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 40.00
Climate Investment Funds 12.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 40.00
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount 12.90
Total Project Cost** 52.90

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jan 30, 2020 TF-B1683 Loan Commitment 8,000,000.00
Jan 30, 2020 IDA-65320 Loan Commitment 40,000,000.00
May 15, 2024 IDA-65320 Int Charges 66,849.10
May 9, 2024 IDA-65320 Loan Disb 8,376,434.00
Apr 29, 2021 IDA-65320 Loan Disb 500,000.00
May 10, 2021 IDA-65320 Loan Disb 5,844,335.00
Nov 15, 2021 IDA-65320 Int Charges 755.84
Nov 15, 2021 IDA-65320 Int Charges 755.84
Nov 15, 2021 IDA-65320 Int Charges 1,259.72
Nov 15, 2021 IDA-65320 Int Charges 23,178.98
Nov 15, 2021 IDA-65320 Int Charges 23,178.98
Nov 15, 2021 IDA-65320 Int Charges 38,631.67
May 15, 2022 IDA-65320 Int Charges 20,998.26
May 15, 2022 IDA-65320 Int Charges 20,998.26
May 15, 2022 IDA-65320 Int Charges 36,592.48
May 15, 2022 IDA-65320 Int Charges 957.21
May 15, 2022 IDA-65320 Int Charges 957.21
Nov 16, 2022 IDA-65320 Int Charges 19,565.36
Nov 16, 2022 IDA-65320 Int Charges 19,565.36
Nov 18, 2022 IDA-65320 Int Charges 23,633.73
Nov 16, 2022 IDA-65320 Int Charges 11,634.78
Nov 15, 2022 IDA-65320 Int Charges 2,136.41
Nov 15, 2022 IDA-65320 Int Charges 2,136.41
May 15, 2023 IDA-65320 Int Charges 43,219.96
May 2, 2023 IDA-65320 Loan Disb 3,501,000.00
Dec 15, 2022 IDA-65320 Loan Disb 1,096,600.00
Dec 15, 2022 IDA-65320 Loan Disb 400,000.00
Nov 15, 2023 IDA-65320 Int Charges 40,426.19
Nov 15, 2023 IDA-65320 Int Charges 40,426.19
Nov 15, 2023 IDA-65320 Int Charges 66,738.93
Nov 15, 2023 IDA-65320 Int Charges 3,103.45
May 15, 2023 IDA-65320 Int Charges 865.53
May 15, 2023 IDA-65320 Int Charges 27,816.95
May 15, 2023 IDA-65320 Int Charges 27,816.95
May 15, 2024 IDA-65320 Int Charges 636.54
May 15, 2024 IDA-65320 Int Charges 41,384.72
May 15, 2024 IDA-65320 Int Charges 41,384.72

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Unsatisfactory 2025-01-28
Procurement Unsatisfactory 2025-01-28
Monitoring and Evaluation Satisfactory 2025-01-28
Financial Management Moderately Satisfactory 2025-01-28
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-01-28
Progress towards achievement of PDO Moderately Unsatisfactory 2025-01-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Industrial/Economic Zones connected to main gridValue0.000.006.00
    DateJune 28, 2018December 12, 2023June 26, 2026
    Comment
  • People provided with new or improved electricity service (CRI)Value0.000.0022825.00
    DateJune 28, 2018December 12, 2023June 26, 2026
    Comment
  • People provided with new or improved electricity service - Female (CRI)Value0.000.0011751.00
    DateJune 28, 2018December 12, 2023June 26, 2026
    Comment
  • People provided with access to electricity under the project by household connections (grid or off-grid). (CRI)Value0.000.0022825.00
    DateJune 28, 2018December 12, 2023June 26, 2026
    Comment
  • Renewable energy generation capacity of mini-grids constructed under the projectValue0.000.004.09
    DateNovember 1, 2019December 12, 2023January 15, 2027
    Comment
  • Community facilities provided with access to electricity service by mini-gridsValue0.000.00245.00
    DateNovember 1, 2019December 12, 2023January 15, 2027
    Comment
  • Small and Medium enterprises provided with access to electricity service by mini-gridsValue0.000.00490.00
    DateNovember 1, 2019December 12, 2023January 15, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Independent verification of new connections completedValueNoNoYes
    DateJune 28, 2018December 12, 2023January 15, 2027
    Comment
  • Households provided with access to electricity services by grid extensionValue0.000.001400.00
    DateJune 28, 2018December 12, 2023January 15, 2027
    Comment
  • Mini-grids constructed or rehabilitated under projectValue0.000.0039.00
    DateMarch 5, 2019December 12, 2023January 15, 2027
    Comment
  • Consumer awareness program developed, with a focus on female members of households and businessesValueNoNoYes
    DateJune 28, 2018December 12, 2023January 15, 2027
    Comment
  • Medium Voltage Distribution lines constructed or rehabilitated under the projectValue0.000.00240.00
    DateJune 28, 2018December 12, 2023January 15, 2027
    Comment
  • Households provided with access to electricity services by mini-gridsValue0.000.004165.00
    DateJune 28, 2018December 12, 2023January 15, 2027
    Comment
  • Assessment of barriers to female entrepreneurship completed and action plan for in mini-grid sector deliveredValueNoNoYes
    DateAugust 30, 2019December 12, 2023January 15, 2027
    Comment
  • Low voltage distribution lines constructed or rehabilitated under the projectValue0.000.0090.00
    DateJune 28, 2019December 12, 2023January 15, 2027
    Comment
  • Health facilities provided with access to electricity serviceValue0.000.0030.00
    DateNovember 1, 2019December 12, 2023January 15, 2027
    Comment
  • Percentage of female engineers employed at LECValue5.005.0010.00
    DateAugust 30, 2019December 12, 2023January 15, 2027
    Comment
  • Distribution substations constructed or rehabilitated under the projectValue0.000.006.00
    DateJune 28, 2019December 12, 2023January 15, 2027
    Comment
  • Schools provided with access to electricity serviceValue0.000.00205.00
    DateNovember 1, 2019December 12, 2023January 15, 2027
    Comment
  • Grievances received and addressedValue0.00100.00100.00
    DateJune 28, 2019December 12, 2023June 26, 2026
    Comment
  • Volume of CO2 emissions reduced from electrification by grid extension per yearValue0.000.0012064.50
    DateJune 28, 2018December 12, 2023January 15, 2027
    Comment
  • Agricultural Resource Center provided with access to electricity serviceValue0.000.0010.00
    DateNovember 1, 2019December 12, 2023January 15, 2027
    Comment
  • Volume of CO2 emissions reduced from electrification by mini-grids per yearValue0.000.001571.00
    DateJune 28, 2018December 12, 2023January 15, 2027
    Comment
  • Volume of additional financing for clean energy investment leveraged (USD)Value0.000.0010000000.00
    DateMarch 5, 2019December 12, 2023January 15, 2027
    Comment