Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
P167201
Active
Camilo Lombana Cordoba
Republic of Angola
May 2, 2018
(as of board presentation)
June 21, 2018
N/A
US$ 150.00 million
Ministry of Energy and Water
2018
US$ 150.00 million
B
June 20, 2024
December 31, 2027
TBD
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 150.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 0.00 | 951150.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 0.00 | 951150.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Number of independent audits of PWSU financial statements documenting financial performance | Value | 0.00 | 0.00 | 9.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Percentage of hydrometric stations supported by the project, providing information to INRH | Value | 0.00 | 0.00 | 80.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Regulatory framework for water and sanitation services in place | Value | No | No | Yes |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Female beneficiaries | Value | 50.00 | 0.00 | 50.00 |
Date | January 30, 2017 | January 30, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of water utilities that the project is supporting | Value | 0.00 | 6.00 | 9.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Average audited cost-recovery ratio for the 5 PWSUs supported by WSDIP I | Value | 0.00 | 0.00 | 80.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Assessment of the safety status of prioritized dam carried out by a panel of experts | Value | 0.00 | 0.00 | 6.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Integrated River Basin Management Plans supported by the Project | Value | 0.00 | 0.00 | 2.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 0.00 | 186500.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Increased capacity of water treatment (production) | Value | 0.00 | 0.00 | 48000.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Number of studies carried out to confirm the availability of water resources with adequate quality | Value | 0.00 | 0.00 | 2.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Length of water supply network laid under the project | Value | 0.00 | 0.00 | 1675.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Number of sanitation master plans updated | Value | 0.00 | 0.00 | 8.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Average audited cost-recovery ratio for 2 PWSUs to be supported by WSDIP II after year 3 | Value | 0.00 | 0.00 | 70.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Average audited cost-recovery ratio for 2 PWSUs to be supported by WSDIP II | Value | 0.00 | 0.00 | 80.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Systems to receive and respond to customer complaints at the PWSU level in place | Value | 0.00 | 0.00 | 9.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Percentage of registered grievances related to service delivery that are resolved | Value | 0.00 | 0.00 | 60.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Percentage of network expansion contracts that carry out information and consultation sessions | Value | 0.00 | 0.00 | 100.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Percentage of network expansion contracts that carry out information and consultation sessions specifically for women | Value | 0.00 | 0.00 | 100.00 |
Date | January 30, 2017 | December 10, 2018 | January 30, 2023 | |
Comment |
Number of people provided with safely managed sanitation service delivery under the project | Value | 0.00 | 0.00 | 35000.00 |
Date | March 23, 2018 | March 23, 2018 | March 29, 2024 | |
Comment |
Approval of guidelines for participatory urban sanitation master planning | Value | No | No | Yes |
Date | April 9, 2018 | April 9, 2018 | March 31, 2024 | |
Comment |
Development of a national strategy for scaling up the piloted approach to urban sanitation | Value | No | No | Yes |
Date | May 2, 2018 | May 2, 2018 | March 31, 2023 | |
Comment |