Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
P167246
Closed
Smita Misra
Republic of India
June 25, 2018
(as of board presentation)
January 16, 2019
April 24, 2019
US$ 0.00 million
Urban Development Department, Government of Himachal Pradesh
2019
US$ 40.00 million
N/A
July 11, 2024
October 31, 2020
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 40.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | N/A |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 16, 2019 | IBRD-89180 | Loan Commitment | 40,000,000.00 |
Jun 15, 2022 | IBRD-89180 | Int Charges | 188,066.66 |
Dec 15, 2022 | IBRD-89180 | Int Charges | 721,625.20 |
Jun 15, 2023 | IBRD-89180 | Int Charges | 51,176.49 |
Jun 15, 2023 | IBRD-89180 | Int Charges | 1,065,917.20 |
Jun 15, 2023 | IBRD-89180 | Loan Repay | 1,740,000.00 |
Dec 15, 2023 | IBRD-89180 | Int Charges | 21,272.04 |
Dec 15, 2023 | IBRD-89180 | Int Charges | 1,171,606.50 |
Dec 15, 2023 | IBRD-89180 | Loan Repay | 1,740,000.00 |
Jun 15, 2024 | IBRD-89180 | Int Charges | 1,187,013.60 |
Jun 15, 2024 | IBRD-89180 | Loan Repay | 1,740,000.00 |
Jun 15, 2024 | IBRD-89180 | Int Charges | 7,607.36 |
May 17, 2019 | IBRD-89180 | Loan Disb | 39,900,000.00 |
Apr 24, 2019 | IBRD-89180 | Loan Disb | 100,000.00 |
Apr 24, 2019 | IBRD-89180 | Fee Charges | 100,000.00 |
Dec 15, 2019 | IBRD-89180 | Int Charges | 8,477.40 |
Dec 15, 2019 | IBRD-89180 | Int Charges | 107,835.62 |
Dec 15, 2019 | IBRD-89180 | Int Charges | 593,733.30 |
Jun 15, 2020 | IBRD-89180 | Int Charges | 504,266.66 |
Dec 15, 2020 | IBRD-89180 | Int Charges | 205,366.69 |
Jun 15, 2021 | IBRD-89180 | Int Charges | 171,888.89 |
Dec 15, 2021 | IBRD-89180 | Int Charges | 158,600.00 |
Name | Review | Date |
---|---|---|
Program Management | Satisfactory | 2020-11-02 |
Overall Implementation Progress (IP) | Satisfactory | 2020-11-02 |
Progress towards achievement of PDO | Satisfactory | 2020-11-02 |
Monitoring and Evaluation | Satisfactory | 2020-11-02 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-28-2021 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 04-27-2022 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Modest | N/a |
M&e Quality | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of ULBs as customers of the SJPNL | Value | 1.00 | 1.00 | 3.00 |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Percentage of customers of the WSS Company serviced by private service provider(s) receiving continuous water supply and connected to sewage systems | Value | Nil | Private contractor successfully demonstrated 24/7 | At least 70% |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Annual reports on SJPNL performance, customer satisfaction, and citizen report cards published and disclosed | Value | No reports | Annual reports on SJPNL performance, customer sati | September 30, each year |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Percentage of decisions on investment, expenditure and staff recruitment referred to GoHP for approval | Value | 100.00 | 0.00 | 0.00 |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Energy consumption of water production from existing sources | Value | 7.69 kWh/m3 | 7.24 kWh/m3 | Less than 6.15 kWh/m3 |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Percentage of WSS complaints redressed within the specified redressal period | Value | Not available | 99% complaints redressed within the stipulated tim | 80% |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Annual audited financial statements of SJPNL publicly disclosed | Value | No consolidated financial statement | Annual audited financial statements of SJPNL for 2 | Financial statements disclosed within six months o |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Reduction in Non-Revenue water | Value | 50% | Not verified - indicator taken up under PforR | 30% |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Adherence to HR Policy for hiring MD cum CEO with a fixed tenure of at least two years | Value | 0.00 | 100.00 | 100.00 |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Percentage of SJPNL staff receiving performance incentives based on employee performance evaluation | Value | 0.00 | 0.00 | 50.00 |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Females as percentage of total staff in various services of SJPNL | Value | Nil | 40% - 16 out of 40 staff are female | At least 30% |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Percentage of corrective actions taken by SJPNL based on recommendations of corporate governance review | Value | Not applicable | 100% corrective actions are taken by SJPNL based o | 90% |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Improved performance of SJPNL as measured by the annual performance scorecard rating | Value | Not applicable | Performance Score Card Rating 4 out of 5 based on | Performance scorecard rating of at least 3 on a sc |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Timely determination of annual tariffs and subsidies | Value | No Policy | Policy approved & first applied in April 2019 but | Annual tariffs and subsidies determined and applie |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Volumetric billing of all customers | Value | Nil | All connections have volumetric billing but 24x7 w | 90% of 24x7 customers |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
Collection efficiency | Value | 70.00 | 100.00 | 90.00 |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
O&M cost recovery (bulk water & distribution) | Value | 21% | not verified - indicator taken up under PforR | 40% |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
O&M cost recovery (water distribution) | Value | 100% | not verified - indicator taken up under PforR | 150% |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |
O&M cost recovery (sewage) | Value | 30% | not verified - indicator taken up under PforR | 100% |
Date | September 30, 2018 | October 29, 2021 | December 31, 2024 | |
Comment |