Abstract*

The development objective of the Water and Sanitation Sectoral Project for Mauritania is to increase access to improved water and sanitation services in selected rural areas and small towns, and to strengthen the performance of sector institutions. The project comprises of four components. The first component is improvement of access to drinking water and sanitation in Gorgol, Guidimakha, and Assaba. It consists of following sub-components: (i) improving...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase access to improved water and sanitation services in selected rural areas and small towns, and to strengthen the performance of sector institutions.

Key Details

Project Details

  • P167328

  • Active

  • Mohamed Nanzoul

  • ISLAMIC REPUBLIC OF MAURITANIA

  • Mauritania

  • March 27, 2019

  • (as of board presentation)

    March 30, 2020

  • September 28, 2020

  • US$ 49.00 million

  • Ministère de l'Hydraulique et de l'Assainissement

  • Western and Central Africa

  • 2020

  • US$ 44.00 million

  • N/A

  • December 21, 2023

  • November 30, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
National Government 5.00
IDA Grant 44.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 44.00
IBRD + IDA Commitment 44.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 49.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 30, 2020 IDA-D5710 Loan Commitment 44,000,000.00
Mar 8, 2022 IDA-D5710 Loan Disb 116,404.87
Dec 18, 2020 IDA-D5710 Loan Disb 2,000,000.00
Nov 14, 2022 IDA-D5710 Loan Disb 572,010.06
Dec 8, 2021 IDA-D5710 Loan Disb 593,326.30
Jun 23, 2022 IDA-D5710 Loan Disb 622,267.70
Jul 31, 2023 IDA-D5710 Loan Disb 314,558.88
Jun 9, 2023 IDA-D5710 Loan Disb 261,821.56
Feb 7, 2023 IDA-D5710 Loan Disb 174,620.78
Apr 26, 2023 IDA-D5710 Loan Disb 309,300.00
Oct 4, 2023 IDA-D5710 Loan Disb 118,968.16
Dec 20, 2023 IDA-D5710 Loan Disb 373,239.88
Jan 12, 2024 IDA-D5710 Loan Disb 396,141.94
Oct 24, 2023 IDA-D5710 Loan Disb 712,668.25
Dec 5, 2023 IDA-D5710 Loan Disb 1,192,127.20
Nov 28, 2023 IDA-D5710 Loan Disb 1,017,197.25
Dec 5, 2023 IDA-D5710 Loan Disb 449,454.53
Dec 26, 2023 IDA-D5710 Loan Disb 427,087.25
Jun 8, 2023 IDA-D5710 Loan Disb 374,395.00
Jun 27, 2023 IDA-D5710 Loan Disb 675,784.56
Feb 21, 2024 IDA-D5710 Loan Disb 103,919.99
Aug 15, 2024 IDA-D5710 Loan Disb 352,364.90
Jun 10, 2024 IDA-D5710 Loan Disb 814,100.50
Apr 12, 2024 IDA-D5710 Loan Disb 846,030.10
Jun 28, 2024 IDA-D5710 Loan Disb 102,122.33
Jun 24, 2024 IDA-D5710 Loan Disb 506,534.60
Jun 25, 2024 IDA-D5710 Loan Disb 439,067.28
Jun 28, 2024 IDA-D5710 Loan Disb 1,135,416.50
Apr 30, 2024 IDA-D5710 Loan Disb 610,631.20
Apr 28, 2022 IDA-D5710 Loan Disb 403,741.72

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2024-12-27
Procurement Moderately Unsatisfactory 2024-12-27
Progress towards achievement of PDO Moderately Satisfactory 2024-12-27
Financial Management Moderately Satisfactory 2024-12-27
Monitoring and Evaluation Satisfactory 2024-12-27
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-27

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people provided with access to improved water sourcesValue0.000.00210000.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Groundwater reports produced and disseminatedValueNoYesYes
    DateDecember 31, 2019December 13, 2023December 31, 2024
    Comment
  • Proportion of water systems delegated to private operators in project areasValue0.000.0065.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Of which host communitiesValue0.000.0035000.00
    DateDecember 31, 2019June 14, 2023November 28, 2025
    Comment
  • Number of people provided with access to improved sanitation facilitiesValue0.000.0030000.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • MHA staff trained and equipped to undertake strategic planning and project management activitiesValue0.0030.0060.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Of which refugeesValue0.000.0015000.00
    DateDecember 31, 2019June 14, 2023November 28, 2025
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Of which host communitiesValue0.000.007000.00
    DateDecember 31, 2019June 14, 2023November 28, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Piezometers constructed under the projectValue0.000.0010.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Standposts constructed under the projectValue0.000.0050.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Water connections constructed under the projectValue0.000.008000.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Technical assistance recruited for MHA on project managementValueNoYesYes
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Number of boreholes drilled and equipped under the projectValue0.0010.0080.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Standposts constructed under the projectValue0.000.00110.00
    DateDecember 31, 2019December 13, 2023July 31, 2025
    Comment
  • Audit of the SNDE (indicator reformulated because it is the audit that will lead to the performance contract of the SNDE)ValueNoNoYes
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • People benefitting from improved water servicesValue0.000.00116000.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Boreholes drilled and equipped under the projectValue0.0025.0096.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Training plan adopted for MHA's departmentsValueNoNoYes
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Number of people benefitting from improved water servicesValue0.000.00120000.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • of which refugeesValue0.000.0068000.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Completion of studies on groundwater aquifersValue0.000.001.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Number of household latrines constructed under the projectValue0.000.001097.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Proportion of interns hired by MHA who are femaleValue0.000.0030.00
    DateDecember 31, 2019June 14, 2023November 28, 2025
    Comment
  • Satisfaction rate of users of WSS servicesValue0.000.0070.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Number of public establishments benefiting from latrines and handwashing facilities (Indicator reformulated by merging those relating to schools, health centers, mosques, etc.)Value0.0020.00116.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • of which water servicesValue0.000.0070.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • of which water servicesValue0.000.0070.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Satisfaction rate of users of WSS servicesValue0.000.0070.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • of which sanitation servicesValue0.000.0070.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • of which water servicesValue0.000.0070.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment
  • Number of public establishments benefiting from latrines and handwashing facilities (Indicator related to schools, health centers, mosques, etc.)Value0.0030.0097.00
    DateDecember 31, 2019December 13, 2023November 28, 2025
    Comment