Financier | Commitments |
---|---|
IDA Credit | 300.00 |
P167401
Active
Franck Taillandier , Asuka Tsuboike
THE REPUBLIC OF COTE D’IVOIRE
October 30, 2018
(as of board presentation)
June 27, 2019
February 13, 2020
US$ 540.00 million
Ministry of Transport,Greater Abidjan Urban Mobility Authority (AMUGA)
2019
US$ 300.00 million
A
Not Applicable
October 15, 2028
Yes
BANK APPROVED
March 16, 2024
Financier | Commitments |
---|---|
IDA Credit | 300.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 300.00 |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 540.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 29, 2024 | IDA-64500 | Loan Disb | 3,518,453.00 |
May 30, 2024 | IDA-64500 | Loan Disb | -3,508,354.20 |
Dec 20, 2023 | IDA-64500 | Int Charges | 21,029.05 |
Dec 15, 2023 | IDA-64500 | Int Charges | 1,492.77 |
Dec 15, 2023 | IDA-64500 | Loan Disb | -5,735,369.50 |
Dec 20, 2023 | IDA-64500 | Int Charges | 322,291.20 |
Dec 20, 2023 | IDA-64500 | Int Charges | 146,524.89 |
Jun 15, 2023 | IDA-64500 | Int Charges | 323,308.16 |
May 8, 2023 | IDA-64500 | Loan Disb | 5,776,676.50 |
Sep 29, 2022 | IDA-64500 | Loan Disb | 3,149,478.50 |
Dec 15, 2022 | IDA-64500 | Loan Disb | -13,709,548.00 |
Dec 15, 2021 | IDA-64500 | Int Charges | 357,687.70 |
Feb 9, 2022 | IDA-64500 | Loan Disb | 11,042,809.00 |
Dec 21, 2022 | IDA-64500 | Int Charges | 321,956.16 |
Dec 21, 2022 | IDA-64500 | Int Charges | 80,844.33 |
Jun 15, 2022 | IDA-64500 | Int Charges | 322,135.53 |
Jun 15, 2022 | IDA-64500 | Int Charges | 24,813.22 |
Jun 15, 2021 | IDA-64500 | Int Charges | 382,386.53 |
Feb 13, 2020 | IDA-64500 | Fee Charges | 726,400.20 |
Dec 15, 2020 | IDA-64500 | Loan Disb | -17,496,804.00 |
Dec 15, 2020 | IDA-64500 | Int Charges | 384,864.30 |
Dec 15, 2020 | IDA-64500 | Int Charges | 95,168.02 |
Jun 16, 2020 | IDA-64500 | Int Charges | 433,627.78 |
Jun 16, 2020 | IDA-64500 | Int Charges | 26,686.48 |
Jun 15, 2023 | IDA-64500 | Int Charges | 99,066.32 |
Jun 15, 2023 | IDA-64500 | Int Charges | 262,316.30 |
Dec 15, 2023 | IDA-64500 | Loan Disb | 5,735,369.50 |
Dec 20, 2023 | IDA-64500 | Int Charges | 99,943.50 |
Dec 20, 2023 | IDA-64500 | Int Charges | 264,639.00 |
Dec 15, 2020 | IDA-64500 | Loan Disb | 17,496,804.00 |
Jun 19, 2024 | IDA-64500 | Int Charges | 98,230.26 |
Jun 19, 2024 | IDA-64500 | Int Charges | 260,102.55 |
Jun 19, 2024 | IDA-64500 | Int Charges | 111,860.34 |
Apr 14, 2020 | IDA-64500 | Loan Disb | 15,014,932.00 |
Feb 13, 2020 | IDA-64500 | Loan Disb | 726,400.20 |
Jun 27, 2019 | IDA-64500 | Loan Commitment | 300,000,000.00 |
Jun 15, 2021 | IDA-64500 | Int Charges | 110,720.93 |
Jun 15, 2022 | IDA-64500 | Int Charges | 95,781.47 |
Dec 15, 2021 | IDA-64500 | Int Charges | 102,977.08 |
Jun 28, 2024 | IDA-64500 | Loan Disb | 7,879,799.50 |
Dec 15, 2022 | IDA-64500 | Loan Disb | 13,709,548.00 |
Jun 19, 2024 | IDA-64500 | Int Charges | 309,873.38 |
Jun 19, 2024 | IDA-64500 | Int Charges | 97,215.29 |
Jul 3, 2024 | IDA-64500 | Loan Disb | 3,026,750.20 |
Jan 26, 2024 | IDA-64500 | Loan Disb | 4,828,310.50 |
May 21, 2024 | IDA-64500 | Loan Disb | 6,546,318.00 |
Dec 21, 2022 | IDA-64500 | Int Charges | 96,909.93 |
Jun 28, 2024 | IDA-64500 | Loan Disb | 18,386,198.00 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2024-12-05 |
Progress towards achievement of PDO | Satisfactory | 2024-12-05 |
Financial Management | Satisfactory | 2024-12-05 |
Monitoring and Evaluation | Satisfactory | 2024-12-05 |
Procurement | Satisfactory | 2024-12-05 |
Project Management | Satisfactory | 2024-12-05 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of the population of GAA able to access the Plateau within 60 minutes during rush hour by public transport | Value | 26.00 | 26.00 | 64.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Satisfaction rating by public transport users of the BRT and its feeder lines | Value | 0.00 | 0.00 | 75.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Percentage of the poor residents of Greater Abidjan with access to the city center (Place de la Republique) within 60 minutes commuting period using public transport | Value | 27.00 | 27.00 | 0.00 |
Date | ||||
Comment |
Satisfaction rating among women who use the BRT and its feeder lines | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Percentage of the population of GAA able to access at least one additional hospital within 30 minutes during rush hour by public transport compared to baseline | Value | 0.00 | 0.00 | 25.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Satisfaction rating by poor public transport users of the BRT and its feeder lines | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Average passenger ridership in the BRT buses per weekday | Value | 0.00 | 0.00 | 330.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Percentage of the poor population of GAA able to access at least one additional hospital within 30 minutes during rush hour by public transport compared to baseline | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Percentage of population of GAA able to access at least one additional secondary school within 30 minutes during rush hour by public transport compared to baseline | Value | 0.00 | 0.00 | 44.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Average ridership by female passengers in the BRT buses per weekday | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of transport service providers trained through formal training programs | Value | 0.00 | 80.00 | 6000.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Percentage of the poor population of GAA able to access at least one additional secondary school within 30 minutes during rush hourby public transport compared to baseline | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of formal transport sector workers trained through the training programs financed by the project | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of female formal transport sector workers trained through the training programs financed by the project | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of informal transport service providers trained through the training programs financed by the project | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of female informal transport service providers trained through the training programs financed by the project | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of serious injuries and deaths involving a BRT bus | Value | 0.00 | 0.00 | 0.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Road safety assessment carried out on the BRT corridor with focus on pedestrians | Value | No | No | Yes |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
A road safety management plan is in place within the BRT operator | Value | No | No | Yes |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
A contract agreement with a private company to invest and operate in the BRT operations is signed | Value | No | No | Yes |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Restructuring Plan of the bus network is implemented | Value | No | No | Yes |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Number of facilities rehabilitated for the informal sector (stations, stops etc..) | Value | 0.00 | 0.00 | 10.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Number of student graduated from the ENPC/INPHB Master | Value | 0.00 | 4.00 | 30.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Percentage of the BRT infrastructure constructed | Value | 0.00 | 0.00 | 100.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Number of SOTRA facilities rehabilitated | Value | 0.00 | 0.00 | 4.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Pedestrian and cycle paths rehabilitated | Value | 0.00 | 0.00 | 15.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Number of operational BRT buses | Value | 0.00 | 0.00 | 157.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
ITS and fare collection system is in use for SOTRA | Value | No | No | Yes |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Number of urban transport vehicles renewed | Value | 0.00 | 0.00 | 3000.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Number of informal operators benefitting from the social security coverage | Value | 0.00 | 0.00 | 5000.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Percentage of female staff in the BRT operator | Value | 0.00 | 0.00 | 30.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Roads rehabilitated non-rural | Value | 0.00 | 0.00 | 30.00 |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
A GRM (Grievance Redress Mechanism) is in use during construction | Value | No | No | Yes |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
Annual disclosure by MoT of the audited annual financial statements and the operational results of the BRT | Value | No | No | Yes |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
A GRM (Grievance Redress Mechanism) for the BRT operation is in use | Value | No | No | Yes |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |
A mirror system to monitor the fare collection system is in use at MoT | Value | No | No | Yes |
Date | April 1, 2019 | November 27, 2023 | June 30, 2025 | |
Comment |