Financier | Commitments |
---|---|
IDA Credit | 292.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 28.00 |
P167596
Active
Greg Browder , Olivier Durand, Francois Onimus
Islamic Republic of Pakistan
June 17, 2021
(as of board presentation)
December 19, 2022
January 10, 2023
US$ 320.00 million
Province of Sindh
2023
US$ 292.00 million
A
January 11, 2024
December 31, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 292.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 28.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 292.00 |
IBRD + IDA Commitment | 292.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 320.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 14, 2023 | IDA-72550 | Loan Disb | 332,000.00 |
Apr 13, 2023 | IDA-72550 | Loan Disb | 745,000.00 |
Jun 13, 2023 | IDA-72550 | Loan Disb | 29,488.00 |
May 15, 2023 | IDA-72550 | Loan Disb | -744,972.00 |
Nov 15, 2023 | IDA-72550 | Int Charges | 403.11 |
Nov 15, 2023 | IDA-72550 | Int Charges | 9,476.55 |
Nov 15, 2023 | IDA-72550 | Int Charges | 238,202.88 |
Dec 19, 2022 | IDA-72540 | Loan Commitment | 98,000,000.00 |
Dec 19, 2022 | IDA-72550 | Loan Commitment | 194,000,000.00 |
Dec 12, 2023 | IDA-72540 | Loan Disb | 40,000,000.00 |
Nov 15, 2023 | IDA-72540 | Int Charges | 7,227.60 |
Nov 15, 2023 | IDA-72540 | Int Charges | 7,227.60 |
Nov 15, 2023 | IDA-72540 | Int Charges | 12,046.00 |
Nov 15, 2023 | IDA-72540 | Int Charges | 126,559.18 |
Nov 15, 2023 | IDA-72540 | Int Charges | 126,559.18 |
Nov 15, 2023 | IDA-72540 | Int Charges | 208,879.66 |
May 15, 2024 | IDA-72540 | Int Charges | 2,047.65 |
May 28, 2024 | IDA-72540 | Loan Disb | 23,621,000.00 |
May 15, 2024 | IDA-72540 | Int Charges | 253,214.62 |
May 15, 2024 | IDA-72540 | Int Charges | 253,214.62 |
May 15, 2024 | IDA-72540 | Int Charges | 422,024.40 |
May 3, 2023 | IDA-72540 | Loan Disb | 4,800,000.00 |
Mar 1, 2024 | IDA-72550 | Loan Disb | 1,098,184.20 |
Nov 15, 2023 | IDA-72550 | Int Charges | 162,981.02 |
May 5, 2023 | IDA-72540 | Loan Disb | 29,579,884.00 |
May 15, 2024 | IDA-72550 | Int Charges | 976.71 |
May 15, 2024 | IDA-72550 | Int Charges | 233,540.25 |
May 15, 2024 | IDA-72550 | Int Charges | 215,344.34 |
Jun 27, 2024 | IDA-72550 | Loan Disb | 700,000.00 |
Jan 10, 2023 | IDA-72550 | Loan Disb | 485,000.00 |
Jan 10, 2023 | IDA-72550 | Fee Charges | 485,000.00 |
Mar 29, 2023 | IDA-72550 | Loan Disb | 745,000.00 |
May 15, 2023 | IDA-72550 | Int Charges | 91,052.61 |
May 15, 2023 | IDA-72550 | Int Charges | 9,283.14 |
May 16, 2023 | IDA-72550 | Loan Disb | 3,000,000.00 |
Sep 5, 2023 | IDA-72550 | Loan Disb | 1,230,328.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-20 |
Project Management | Moderately Satisfactory | 2024-12-20 |
Financial Management | Moderately Satisfactory | 2024-12-20 |
Monitoring and Evaluation | Satisfactory | 2024-12-20 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-20 |
Procurement | Moderately Satisfactory | 2024-12-20 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
FO subprojects in which agricultural surface water productivity increases by at least 20 percent | Value | 0.00 | 0.00 | 12.00 |
Date | October 1, 2022 | December 1, 2023 | December 29, 2028 | |
Comment |
FO subprojects where the AWB delivers the agreed upon water volumes in compliance with FO-AWB Water Service agreements | Value | 0.00 | 0.00 | 12.00 |
Date | October 1, 2022 | December 1, 2023 | December 29, 2028 | |
Comment |
Farmers who receive cash transfers and resume agricultural production in 2023 | Value | 0.00 | 234855.00 | 800000.00 |
Date | October 1, 2022 | December 1, 2023 | April 17, 2023 | |
Comment |
Acres of water thrifty crops supported through the smart subsidy scheme | Value | 0.00 | 0.00 | 80000.00 |
Date | October 1, 2022 | December 1, 2023 | December 29, 2028 | |
Comment |
Sindh Strategic Water Plan approved by the Sindh Water Resources Commission | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | June 30, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Draft water bill submitted to Sindh Provincial Assembly by the Sindh Law and Parliamentary Affairs Department | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | June 30, 2027 | |
Comment |
Acres supported with improved on-farm water management measures | Value | 0.00 | 0.00 | 110000.00 |
Date | October 1, 2022 | December 1, 2023 | April 13, 2029 | |
Comment |
Water pricing reform study completed and Abiana rates increased by the Sindh Irrigation Department | Value | No | No | Yes |
Date | December 1, 2022 | December 1, 2023 | June 30, 2026 | |
Comment |
Sindh Food Department Wheat Strategic Reserve Monitoring System functional | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | December 29, 2028 | |
Comment |
Irrigation Department Transformed into Irrigation and Water Resources Department | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | June 30, 2028 | |
Comment |
Preparation studies for Right Bank investments completed | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | June 30, 2027 | |
Comment |
New policy on Sindh agriculture research and extension adopted by the Sindh Cabinet | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | June 30, 2026 | |
Comment |
Functional Hydro-Agro Informatics Program established | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | December 29, 2028 | |
Comment |
Farmers satisfied with development/implementation of Area Development Plan | Value | 0.00 | 0.00 | 70.00 |
Date | October 1, 2022 | December 1, 2023 | December 29, 2028 | |
Comment |
Akram Wah Canal physical works completed | Value | 0.00 | 0.00 | 100.00 |
Date | October 1, 2022 | December 1, 2023 | June 30, 2028 | |
Comment |
Sindh Crop and Market Monitoring System Improved | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | April 13, 2029 | |
Comment |
Representation of women in leadership increased in agriculture and water resources management organizations | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | December 29, 2028 | |
Comment |
Groundwater actively managed in conjunction with surface water supplies in at least 2 pilot FOs | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | December 29, 2028 | |
Comment |
Waterlogging and Salinity management capacity strengthened | Value | No | No | Yes |
Date | October 1, 2022 | December 1, 2023 | June 30, 2028 | |
Comment |
Target FOs with at least two women on the board | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Acres of applied research activities | Value | 0.00 | 0.00 | 8.00 |
Date | ||||
Comment |
Target WCAs with at least two women on the board | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Labs rehabilitated | Value | 0.00 | 10.00 | 8.00 |
Date | ||||
Comment |
Target AWBs with at least two women on the board | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Farmers and agricultural small and medium enterprises supported to enhance value chain for high value water thrifty crops | Value | 0.00 | 0.00 | 2100.00 |
Date | October 1, 2022 | December 1, 2023 | April 13, 2029 | |
Comment |
Farmers trained | Value | 0.00 | 0.00 | 80000.00 |
Date | October 1, 2022 | December 1, 2023 | April 13, 2029 | |
Comment |
of which female | Value | 0.00 | 0.00 | 10500.00 |
Date | October 1, 2022 | December 1, 2023 | April 13, 2029 | |
Comment |
Agriculture Extension offices rehabilited | Value | 0.00 | 0.00 | 15.00 |
Date | October 1, 2022 | December 1, 2023 | June 30, 2026 | |
Comment |