Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 750.00 |
P167619
Active
Deborah Mikesell , Yannis Arvanitis
Kingdom of Morocco
September 23, 2018
(as of board presentation)
June 20, 2019
August 30, 2019
US$ 500.00 million
Ministry of National Education, Preschool, and Sports,Ministry of Economy and Finance
2019
US$ 750.00 million
N/A
May 20, 2024
July 31, 2026
No
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 750.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 750.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 750.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 500.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 1, 2020 | IBRD-89900 | Int Charges | 52,414.56 |
Aug 1, 2023 | IBRD-89900 | Int Charges | 173,623.56 |
Aug 1, 2023 | IBRD-89900 | Int Charges | 21,972.93 |
Aug 1, 2023 | IBRD-89900 | Int Charges | 130,409.43 |
Feb 1, 2023 | IBRD-89900 | Loan Disb | -99,875,736.00 |
Oct 24, 2022 | IBRD-89900 | Loan Disb | 13,143,174.00 |
Feb 1, 2023 | IBRD-89900 | Int Charges | 260,212.53 |
Feb 1, 2023 | IBRD-89900 | Int Charges | 131,260.95 |
Dec 1, 2022 | IBRD-89900 | Loan Disb | 11,172,300.00 |
Nov 9, 2022 | IBRD-89900 | Loan Disb | 14,349,782.00 |
Dec 23, 2022 | IBRD-89900 | Loan Disb | 18,934,484.00 |
Dec 21, 2022 | IBRD-89900 | Loan Disb | 9,460,552.00 |
Dec 19, 2022 | IBRD-89900 | Loan Disb | 28,179,606.00 |
Feb 1, 2022 | IBRD-89900 | Int Charges | 349,465.34 |
Aug 1, 2022 | IBRD-89900 | Loan Disb | -27,433,014.00 |
Aug 1, 2022 | IBRD-89900 | Int Charges | 299,826.25 |
Aug 1, 2022 | IBRD-89900 | Int Charges | 27,463.50 |
May 25, 2022 | IBRD-89900 | Loan Disb | 28,540,878.00 |
Feb 8, 2024 | IBRD-89900 | Loan Disb | 7,146,171.50 |
Feb 1, 2024 | IBRD-89900 | Int Charges | 172,605.61 |
Jan 19, 2024 | IBRD-89900 | Loan Disb | 11,653,445.00 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 142,715.19 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 201,056.89 |
Aug 1, 2024 | IBRD-89900 | Loan Repay | 227,120.56 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 1,025.11 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 19,860.38 |
Feb 1, 2024 | IBRD-89900 | Loan Disb | -11,569,954.00 |
Jun 10, 2024 | IBRD-89900 | Loan Disb | 10,644,359.00 |
Apr 5, 2024 | IBRD-89900 | Loan Disb | 1,932,964.00 |
Aug 1, 2024 | IBRD-89900 | Loan Disb | -19,549,646.00 |
Jun 9, 2023 | IBRD-94940 | Fee Charges | 618,852.75 |
Jun 9, 2023 | IBRD-94940 | Loan Disb | 618,852.75 |
Feb 12, 2024 | IBRD-94940 | Loan Disb | 1,266,361.80 |
Apr 15, 2024 | IBRD-94940 | Int Charges | 301,703.03 |
Apr 5, 2024 | IBRD-94940 | Loan Disb | 9,998,538.00 |
Apr 5, 2024 | IBRD-94940 | Loan Disb | 59,491,300.00 |
Apr 15, 2024 | IBRD-94940 | Int Charges | 26,321.21 |
Oct 20, 2023 | IBRD-94940 | Int Charges | 221,917.25 |
Oct 20, 2023 | IBRD-94940 | Int Charges | 9,398.82 |
Jun 7, 2024 | IBRD-94940 | Loan Disb | 7,527,961.00 |
Mar 17, 2023 | IBRD-94940 | Loan Commitment | 250,000,000.00 |
Jun 20, 2019 | IBRD-89900 | Loan Commitment | 500,000,000.00 |
Mar 15, 2021 | IBRD-89900 | Loan Disb | 15,963,009.00 |
Dec 8, 2020 | IBRD-89900 | Loan Disb | 24,837,696.00 |
Aug 1, 2020 | IBRD-89900 | Loan Disb | -52,853,232.00 |
Aug 30, 2019 | IBRD-89900 | Fee Charges | 1,231,071.50 |
Aug 1, 2021 | IBRD-89900 | Int Charges | 9,187.64 |
Aug 1, 2021 | IBRD-89900 | Int Charges | 15,060.93 |
Aug 1, 2021 | IBRD-89900 | Int Charges | 368,313.66 |
Aug 1, 2021 | IBRD-89900 | Int Charges | 58,043.21 |
Aug 1, 2021 | IBRD-89900 | Loan Disb | -26,541,460.00 |
Feb 1, 2021 | IBRD-89900 | Loan Disb | -24,787,432.00 |
Feb 1, 2021 | IBRD-89900 | Int Charges | 429,396.62 |
Feb 12, 2021 | IBRD-89900 | Loan Disb | 10,799,890.00 |
Feb 1, 2024 | IBRD-89900 | Int Charges | 833,820.00 |
Feb 1, 2024 | IBRD-89900 | Int Charges | 253,092.73 |
Feb 1, 2024 | IBRD-89900 | Int Charges | 125,292.93 |
Feb 1, 2024 | IBRD-89900 | Int Charges | 156,676.44 |
Feb 1, 2024 | IBRD-89900 | Int Charges | 413,625.84 |
Feb 1, 2024 | IBRD-89900 | Int Charges | 1,982,111.20 |
Aug 1, 2024 | IBRD-89900 | Loan Disb | 19,549,646.00 |
Feb 1, 2024 | IBRD-89900 | Loan Disb | 11,569,954.00 |
Aug 1, 2024 | IBRD-89900 | Loan Repay | 721,516.50 |
Aug 1, 2024 | IBRD-89900 | Loan Repay | 2,472,137.80 |
Aug 1, 2024 | IBRD-89900 | Loan Repay | 288,606.60 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 831,968.60 |
Feb 1, 2022 | IBRD-89900 | Int Charges | 130,677.20 |
Feb 1, 2022 | IBRD-89900 | Int Charges | 163,409.38 |
Feb 1, 2022 | IBRD-89900 | Int Charges | 869,652.10 |
Feb 1, 2022 | IBRD-89900 | Int Charges | 263,969.00 |
Aug 1, 2022 | IBRD-89900 | Int Charges | 148,595.47 |
Aug 1, 2022 | IBRD-89900 | Int Charges | 790,813.75 |
Aug 1, 2022 | IBRD-89900 | Int Charges | 240,038.88 |
Aug 1, 2022 | IBRD-89900 | Int Charges | 118,830.65 |
Aug 1, 2022 | IBRD-89900 | Loan Disb | 27,433,014.00 |
Feb 1, 2023 | IBRD-89900 | Loan Disb | 99,875,736.00 |
Feb 1, 2023 | IBRD-89900 | Int Charges | 840,299.90 |
Feb 1, 2023 | IBRD-89900 | Int Charges | 255,059.60 |
Feb 1, 2023 | IBRD-89900 | Int Charges | 126,266.62 |
Feb 1, 2023 | IBRD-89900 | Int Charges | 157,894.02 |
Feb 1, 2023 | IBRD-89900 | Int Charges | 416,840.25 |
Aug 1, 2023 | IBRD-89900 | Int Charges | 847,204.06 |
Aug 1, 2023 | IBRD-89900 | Int Charges | 257,155.23 |
Aug 1, 2023 | IBRD-89900 | Int Charges | 127,304.07 |
Aug 1, 2020 | IBRD-89900 | Int Charges | 94,473.36 |
Aug 1, 2020 | IBRD-89900 | Int Charges | 452,519.70 |
Aug 1, 2020 | IBRD-89900 | Int Charges | 111,534.99 |
Apr 16, 2020 | IBRD-89900 | Loan Disb | 48,520,340.00 |
Dec 5, 2019 | IBRD-89900 | Loan Disb | 123,664,648.00 |
Feb 1, 2020 | IBRD-89900 | Loan Disb | -124,293,176.00 |
Feb 1, 2020 | IBRD-89900 | Int Charges | 438,555.12 |
Feb 1, 2020 | IBRD-89900 | Int Charges | 3,656.01 |
Aug 30, 2019 | IBRD-89900 | Loan Disb | 1,231,071.50 |
Aug 1, 2023 | IBRD-89900 | Int Charges | 159,191.31 |
Aug 1, 2023 | IBRD-89900 | Int Charges | 420,265.12 |
Aug 1, 2023 | IBRD-89900 | Int Charges | 2,013,927.00 |
Feb 1, 2020 | IBRD-89900 | Loan Disb | 124,293,176.00 |
Aug 1, 2020 | IBRD-89900 | Loan Disb | 52,853,232.00 |
Feb 1, 2021 | IBRD-89900 | Int Charges | 932,020.90 |
Feb 1, 2021 | IBRD-89900 | Int Charges | 282,900.03 |
Feb 1, 2021 | IBRD-89900 | Loan Disb | 24,787,432.00 |
Aug 1, 2020 | IBRD-89900 | Int Charges | 914,162.70 |
Aug 1, 2021 | IBRD-89900 | Loan Disb | 26,541,460.00 |
Aug 1, 2021 | IBRD-89900 | Int Charges | 918,135.44 |
Aug 1, 2021 | IBRD-89900 | Int Charges | 278,685.34 |
Aug 1, 2021 | IBRD-89900 | Int Charges | 137,962.48 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 252,530.78 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 125,014.74 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 156,328.55 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 412,707.44 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 1,977,710.10 |
Aug 1, 2024 | IBRD-89900 | Int Charges | 223,381.52 |
Aug 1, 2024 | IBRD-89900 | Loan Repay | 3,036,382.00 |
Aug 1, 2024 | IBRD-89900 | Loan Repay | 1,202,527.50 |
Aug 1, 2024 | IBRD-89900 | Loan Repay | 553,162.60 |
Aug 1, 2024 | IBRD-89900 | Loan Repay | 601,263.75 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-02-07 |
Monitoring and Evaluation | Moderately Satisfactory | 2025-02-07 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-02-07 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PDO#1:Number of children enrolled in preschool units that received a quality label | Value | 0.00 | 0.00 | 100000.00 |
Date | April 3, 2023 | April 1, 2024 | July 31, 2026 | |
Comment |
PDO#2: Improved teacher practices in the classroom for all active teachers in primary and secondary education | Value | 2.8/5. | 2.8/5 | 3.1/5 |
Date | December 29, 2023 | December 29, 2023 | July 31, 2026 | |
Comment |
PDO#3: Implementation of performance contracts at AREF and DP level. | Value | No performance contracts. | 12 performance contracts have been signed. | 6 AREFs and 2 Provincial Directorates per AREFs ha |
Date | September 30, 2019 | April 1, 2024 | September 30, 2024 | |
Comment |
PDO#4: Number of public finance management tools required for ex-post control adopted by AREFs | Value | 0.00 | 0.00 | 63.00 |
Date | April 3, 2023 | April 1, 2024 | July 31, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
IRI 1.1 Criteria and process for approval of existing preschool educator's training programs established | Value | No | Yes | Yes |
Date | September 30, 2019 | April 1, 2024 | July 31, 2026 | |
Comment |
IRI 2.1: Increased average score of admitted CLE students, by gender | Value | Average BAC score for those admitted in CLE (x/20) | TBD | Average BAC score for those admitted in CLE (x/20) |
Date | September 30, 2019 | August 31, 2023 | July 31, 2026 | |
Comment |
IRI 3.1 Number of AREF preparing their annual budget based on the performance contract approach (Circular No. 4509 on financial management parastatals) | Value | 0.00 | 12.00 | 6.00 |
Date | September 30, 2019 | April 1, 2024 | September 30, 2024 | |
Comment |
IRI 1.2 Number of preschool educators who completed an initial in-service training program approved by MoE | Value | 0 | 5097 of which 85% is female | 10,000 (of which at least 50 percent are women). |
Date | September 30, 2019 | April 1, 2024 | July 31, 2026 | |
Comment |
IRI 2.2: In-service teachers receive and access personalized professional development opportunities through their AREF, by gender | Value | 0 | 0 | 30% of in-service teachers receive support; 30% re |
Date | September 30, 2019 | April 1, 2024 | July 31, 2026 | |
Comment |
IRI 3.2 Share of parents of primary school age kids using the MASSAR application | Value | 0.00 | 0.00 | 60.00 |
Date | September 30, 2019 | April 1, 2024 | July 31, 2026 | |
Comment |
IRI 1.3 Number of children aged 4 to 6 years enrolled in preprimary education | Value | 699,634.00 (313,672 are girls and 217,175 children | 931,393 enrolled (of which: 460,905 female/ 470,48 | 1,010,742 (of which 50 percent are girls) |
Date | February 28, 2019 | April 1, 2024 | July 31, 2026 | |
Comment |
IRI 3.3: Number of AREFs that have identified their integrated financial management information system (technical specifications ofthe solution identified are validated by the MoE) | Value | 0.00 | 0.00 | 4.00 |
Date | April 3, 2023 | April 1, 2024 | July 31, 2026 | |
Comment |
IRI 3.4 Number of schools that have volunteered to be part of the school labelling process (Number) | Value | 0.00 | 626.00 | 5000.00 |
Date | April 3, 2023 | April 1, 2024 | July 31, 2026 | |
Comment |
IRI 3.5 Percentage point improvement in subtraction and division among Level 4 students benefiting from TARL by AREF and gender. | Value | 0.00 | 0.00 | 15.00 |
Date | April 3, 2023 | April 1, 2024 | July 31, 2026 | |
Comment |
IRI 3.6 Reduction in reading proficiency gap between boys and girls among level 4 students benefiting from TaRL (disaggregated by gender) (new) | Value | 0 | 0 | Baseline + 10 percentage point increase. A gender- |
Date | April 3, 2023 | April 1, 2024 | July 30, 2026 | |
Comment |