Serbia Competitive Agriculture Project (SCAP)

Abstract*

The development objective of the Competitive Agriculture Project for Serbia is to improve agri-food market linkages of targeted beneficiaries. The project comprises of three components. The first component, improving the value-added of agriculture is to improve the productive and entrepreneurial capacity of small and medium agri-food producers, producer groups, and small and medium-sized enterprises (SMEs) to improve their linkages to markets. It...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Improve agri-food market linkages of targeted beneficiaries.

Key Details

Project Details

  • P167634

  • Active

  • Augusto Garcia , Olivera Jordanovic, Xueling Li

  • Republic of Serbia

  • Serbia

  • June 6, 2019

  • (as of board presentation)

    December 3, 2019

  • February 18, 2020

  • US$ 50.00 million

  • Ministry of Agriculture, Forestry and Water Management

  • Europe and Central Asia

  • 2020

  • US$ 50.00 million

  • N/A

  • Moderate

  • December 31, 2025

  • Yes

  • BANK APPROVED

  • May 21, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 50.00
IDA Commitment N/A
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 50.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 7, 2022 IBRD-90230 Loan Disb 13,732,200.00
Oct 4, 2022 IBRD-90230 Loan Disb 11,861,414.00
Nov 15, 2022 IBRD-90230 Int Charges 21,782.74
Nov 15, 2022 IBRD-90230 Int Charges 37,985.88
May 15, 2023 IBRD-90230 Int Charges 3,753.01
May 15, 2023 IBRD-90230 Loan Repay 1,579,153.80
May 15, 2023 IBRD-90230 Int Charges 398,409.72
Mar 22, 2024 IBRD-90230 Loan Disb 1,996,817.50
Nov 15, 2023 IBRD-90230 Int Charges 21,114.01
Nov 15, 2023 IBRD-90230 Int Charges 663,570.25
Nov 15, 2023 IBRD-90230 Loan Repay 2,085,792.20
Aug 8, 2023 IBRD-90230 Loan Disb 1,794,564.80
Aug 8, 2023 IBRD-90230 Loan Disb 6,910,307.00
May 15, 2024 IBRD-90230 Loan Repay 2,077,922.10
May 15, 2024 IBRD-90230 Int Charges 15,082.71
May 15, 2023 IBRD-90230 Int Charges 26,562.44
May 15, 2021 IBRD-90230 Int Charges 67,834.62
Nov 15, 2020 IBRD-90230 Int Charges 249.01
Nov 15, 2020 IBRD-90230 Int Charges 67,857.68
Apr 1, 2021 IBRD-90230 Loan Disb 2,347,400.00
Nov 15, 2021 IBRD-90230 Int Charges 62,354.08
Nov 15, 2021 IBRD-90230 Int Charges 690.20
May 15, 2022 IBRD-90230 Int Charges 47,977.46
Feb 18, 2020 IBRD-90230 Fee Charges 123,946.25
Feb 18, 2020 IBRD-90230 Loan Disb 123,946.25
May 15, 2020 IBRD-90230 Int Charges 44.87
May 15, 2020 IBRD-90230 Int Charges 33,066.71
May 15, 2024 IBRD-90230 Int Charges 770,706.80
May 15, 2023 IBRD-90230 Int Charges 660.95
Dec 3, 2019 IBRD-90230 Loan Commitment 50,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2024-12-20
Procurement Moderately Satisfactory 2024-12-20
Financial Management Satisfactory 2024-12-20
Progress towards achievement of PDO Satisfactory 2024-12-20
Monitoring and Evaluation Satisfactory 2024-12-20
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-20
Project Management Satisfactory 2024-12-20
Project Management Satisfactory 2024-12-20
Progress towards achievement of PDO Satisfactory 2024-12-20
Financial Management Satisfactory 2024-12-20
Monitoring and Evaluation Satisfactory 2024-12-20
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-20

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • New formal contracts signed between beneficiaries and buyers of their products/servicesValue0.001280.001230.00
    DateDecember 10, 2019May 7, 2024December 31, 2024
    Comment
  • New formal contracts signed between women beneficiaries and buyers of their products/servicesValue0.000.000.00
    Date
    Comment
  • Increase in the value of beneficiaries’ productionValue0.0020.0020.00
    DateDecember 10, 2019May 7, 2024December 31, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Beneficiaries successfully completing their business plansValue0.001280.001230.00
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment
  • Applications accessible from the integrated data platform of MAFWMValue0.000.006.00
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment
  • Farmers reached with agricultural assets or servicesValue0.004356.005500.00
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment
  • Users of the integrated information platform reporting satisfaction (satisfied or very satisfied) with the information received viathe platformValue0.000.0090.00
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment
  • Unique users of the integrated information systemValue0.000.0010000.00
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment
  • Farmers reached with agricultural assets or services - FemaleValue0.000.000.00
    Date
    Comment
  • Surveyed beneficiary women that report training/advisory services offered were responsive to their needsValue0.0095.4095.00
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment
  • Beneficiaries reached with financial servicesValue0.001352.001230.00
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment
  • Number of previously unbanked adults reached with transaction accountsValue0.001117.001100.00
    DateDecember 10, 2019May 7, 2024December 31, 2024
    Comment
  • Productivity increase of beneficiary productionValue0.0010.0010.00
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment
  • Private capital mobilized through the Project (million euros)Value0.0024.19 million euros30.00 million euros
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment
  • Commercial banks providing financial services to beneficiary farmers and business plans supported by the ProjectValue0.009.0010.00
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment
  • Percentage of beneficiaries that have environmentally sustainable practices and climate change mitigation measures.Value0.0035.0030.00
    DateDecember 3, 2019May 7, 2024December 31, 2024
    Comment