The development objective of Gaza Emergency Cash for Work and Self-Employment Support Project for West Bank and Gaza is to provide target youth in Gaza with short‐term income support and increased access to internet‐enabled self-employment opportunities. This project has three components. 1) The first component, Cash for Work, aims to provide cash for work sub‐grants to selected NGOs to implement cash for work subprojects employing target youth. 2)...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To provide target youth in Gaza with short-term income support and increased access to internet-enabled self-employment opportunities

Key Details

Project Details

  • P167726

  • Closed

  • Samira Hillis , Cristobal Ridao-Cano, Friederike Rother

  • NGO Development Center

  • West Bank and Gaza

  • July 11, 2018

  • (as of board presentation)

    August 10, 2018

  • August 27, 2018

  • US$ 17.00 million

  • C

  • Not Applicable

  • June 30, 2022

  • Yes

  • BANK APPROVED

  • January 29, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Special Financing 17.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 17.00
Total Project Cost** 17.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2022-06-25
Procurement Satisfactory 2022-06-25
Financial Management Satisfactory 2022-06-25
Progress towards achievement of PDO Satisfactory 2022-06-25
Monitoring and Evaluation Satisfactory 2022-06-25
Overall Implementation Progress (IP) Satisfactory 2022-06-25

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 02-27-2023
OutcomesHighly Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-14-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of youth receiving cash for work from the Project, by genderValue0.004400.002200.00
    DateAugust 10, 2018June 30, 2022July 1, 2019
    Comment
  • Number of youth receiving e-work support that have done at least one paid freelancing job during the support or 6 months after that, by genderValue0.00375.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • of which, femaleValue0.002200.001100.00
    DateAugust 10, 2018June 30, 2022July 1, 2019
    Comment
  • Of which, femaleValue0.00188.000.00
    DateAugust 10, 2018June 30, 2022August 1, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of members from households where youth receive C4W from the ProjectValue0.0026400.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Number of youth receiving e-work support from the project, by genderValue0.00750.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • From CTP households or households on the waiting list for UNRWA's Job Creation ProgramValue0.0013200.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Of which, femaleValue0.00375.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Number of vulnerable people directly benefiting from services provided through C4W sub-projectsValue0.0080000.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Percentage of direct beneficiaries of e-work that are satisfied with the support provided by the Project, by type of support and genderValue0.0080.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Of which, disabled peopleValue0.006000.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • of which e-work female beneficiariesValue0.0080.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Of which, childrenValue0.0020000.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • of which e-work male beneficiariesValue0.0080.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Percentage of claims and grievances processed, and resolved within 30 days.Value0.0060.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Of which, womenValue0.0020000.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Percentage of direct beneficiaries of C4W that are satisfied with the support provided by the Project, by type of support and gender.Value0.0080.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Of which, C4W female beneficiariesValue0.0080.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Of which, C4W male beneficiariesValue0.0080.000.00
    DateAugust 10, 2018June 30, 2022
    Comment
  • Percentage of claims and grievances processed, and resolved within 30 days.Value0.0060.000.00
    DateAugust 10, 2018June 30, 2022
    Comment