Emergency Multi-Sector Rohingya Crisis Response Project

Abstract*

The Emergency Multi-Sector Rohingya Response Project of Bangladesh has the proposed development objective to strengthen the Government of Bangladesh systems to improve access to basic services and build faster and social resilience of the displaced Rohingya population. This project is comprised of four components: (1) Strengthening delivery of basic services, resilient infrastructure, emergency response and gender-based violence (GBV) prevention...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To strengthen the Government of Bangladesh systems to improve access to basic services and build the disaster and social resilience of the population of Cox’s Bazar district.

Key Details

Project Details

  • P167762

  • Active

  • Swarna Kazi , Debashish Shuvra, Mostafa Sabbih

  • People's Republic of Bangladesh

  • Bangladesh

  • October 3, 2018

  • (as of board presentation)

    March 7, 2019

  • June 9, 2019

  • US$ 165.00 million

  • Department of Public Health Engineering,Local Government Engineering Department,Ministry of Disaster Management and Relief

  • South Asia

  • 2019

  • US$ 165.00 million

  • A

  • June 25, 2024

  • June 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 165.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 165.00
IBRD + IDA Commitment 165.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 165.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 29, 2022 IDA-D4190 Loan Disb 4,587,571.00
Dec 28, 2022 IDA-D4190 Loan Disb 1,000,000.00
Feb 3, 2022 IDA-D4190 Loan Disb 1,475,517.00
Aug 24, 2022 IDA-D4190 Loan Disb 1,985,991.20
Dec 8, 2021 IDA-D4190 Loan Disb 3,265,047.80
Mar 16, 2022 IDA-D4190 Loan Disb 5,613,407.00
Apr 19, 2022 IDA-D4190 Loan Disb 4,690,277.50
Apr 20, 2022 IDA-D4190 Loan Disb 814,571.50
Jun 16, 2022 IDA-D4190 Loan Disb 2,293,362.80
Jun 4, 2024 IDA-D4190 Loan Cancel 3,593,270.20
Jun 17, 2024 IDA-D4190 Loan Disb 1,680,810.50
Jun 27, 2024 IDA-D4190 Loan Disb 3,114,828.20
Feb 26, 2024 IDA-D4190 Loan Disb 1,718,820.40
May 9, 2024 IDA-D4190 Loan Disb 3,134,153.20
Jun 13, 2024 IDA-D4190 Loan Disb 2,653,610.20
Mar 18, 2024 IDA-D4190 Loan Disb 167,370.81
Apr 29, 2024 IDA-D4190 Loan Disb 1,600,211.80
Apr 18, 2024 IDA-D4190 Loan Disb 3,183,604.80
Jan 17, 2024 IDA-D4190 Loan Disb 2,272,727.20
Feb 13, 2023 IDA-D5900 Loan Disb 2,969,415.80
Nov 3, 2022 IDA-D5900 Loan Disb 1,934,026.40
Nov 3, 2022 IDA-D5900 Loan Disb 463,339.20
Oct 12, 2023 IDA-D5900 Loan Disb 2,150,953.80
Aug 29, 2023 IDA-D5900 Loan Disb 1,623,768.60
Jul 26, 2023 IDA-D5900 Loan Disb 1,902,399.10
Jun 15, 2023 IDA-D5900 Loan Disb 2,988,237.20
Jun 15, 2023 IDA-D5900 Loan Disb 1,668,616.20
Mar 7, 2024 IDA-D5900 Loan Disb 2,741,623.50
Jan 25, 2024 IDA-D5900 Loan Disb 1,184,880.50
Mar 31, 2020 IDA-D5900 Loan Commitment 100,000,000.00
Mar 7, 2019 IDA-D4190 Loan Commitment 165,000,000.00
Dec 2, 2021 IDA-D5900 Loan Disb 2,913,753.00
Feb 10, 2022 IDA-D5900 Loan Disb 141,671.97
Aug 24, 2022 IDA-D5900 Loan Disb 1,580,079.60
Apr 21, 2022 IDA-D5900 Loan Disb 334,329.60
Jun 21, 2022 IDA-D5900 Loan Disb 2,759,407.00
Dec 7, 2021 IDA-D5900 Loan Disb 7,575,757.50
Jun 16, 2022 IDA-D5900 Loan Disb 719,800.80
Apr 27, 2023 IDA-D5900 Loan Disb 1,161,868.50
Feb 28, 2023 IDA-D5900 Loan Disb 652,488.56
Jan 12, 2023 IDA-D5900 Loan Disb 2,498,750.20
Feb 16, 2023 IDA-D5900 Loan Disb 1,976,349.90
Dec 21, 2023 IDA-D4190 Loan Disb 3,277,678.80
Jan 18, 2024 IDA-D4190 Loan Disb 415,044.66
Nov 30, 2023 IDA-D4190 Loan Disb 168,957.73
Nov 22, 2023 IDA-D4190 Loan Disb 59,405.08
Nov 19, 2019 IDA-D4190 Loan Disb 1,074,289.80
Jun 27, 2019 IDA-D4190 Loan Disb 2,958,580.00
Jul 12, 2021 IDA-D4190 Loan Disb 3,296,605.00
Oct 25, 2021 IDA-D4190 Loan Disb 872,844.60
Oct 25, 2021 IDA-D4190 Loan Disb 200,945.70
Jul 15, 2021 IDA-D4190 Loan Disb 2,948,110.50
Jun 28, 2021 IDA-D4190 Loan Disb 13,750,000.00
Apr 26, 2021 IDA-D4190 Loan Disb 4,191,603.50
Apr 19, 2021 IDA-D4190 Loan Disb 1,726,901.90
Jun 21, 2021 IDA-D4190 Loan Disb 1,274,704.90
Mar 23, 2021 IDA-D4190 Loan Disb 2,796,828.00
Dec 28, 2020 IDA-D4190 Loan Disb 691,453.10
Jan 25, 2021 IDA-D4190 Loan Disb 1,250,417.80
Dec 29, 2020 IDA-D4190 Loan Disb 4,785,593.50
Sep 16, 2020 IDA-D4190 Loan Disb 2,376,232.20
Sep 2, 2020 IDA-D4190 Loan Disb 4,327,716.50
Jul 7, 2020 IDA-D4190 Loan Disb 2,540,226.20
Jun 16, 2020 IDA-D4190 Loan Disb 12,000,000.00
Jun 16, 2020 IDA-D4190 Loan Disb 1,495,186.40
Apr 23, 2020 IDA-D4190 Loan Disb 7,000,000.00
Mar 3, 2020 IDA-D4190 Loan Disb 625,528.44
Jan 15, 2020 IDA-D4190 Loan Disb 69,263.38
Mar 31, 2020 IDA-D4190 Loan Disb 2,935,383.00
Mar 30, 2020 IDA-D4190 Loan Disb 2,354,326.00
Feb 12, 2020 IDA-D4190 Loan Disb 733,845.80
Oct 9, 2019 IDA-D4190 Loan Disb 5,906,674.50
Nov 26, 2019 IDA-D4190 Loan Disb 589,622.60
May 17, 2023 IDA-D4190 Loan Disb 285,334.78
Sep 19, 2023 IDA-D4190 Loan Disb 533,894.20
Jul 26, 2023 IDA-D4190 Loan Disb 901,625.44
Sep 7, 2023 IDA-D4190 Loan Disb 184,256.95
Jun 20, 2023 IDA-D4190 Loan Disb 1,848,414.50
Aug 31, 2023 IDA-D4190 Loan Disb 2,690,489.50
Feb 28, 2023 IDA-D4190 Loan Disb 305,618.97
Mar 6, 2023 IDA-D4190 Loan Disb 1,531,942.60
Feb 14, 2023 IDA-D4190 Loan Disb 2,453,732.20
Nov 3, 2022 IDA-D4190 Loan Disb 90,494.98

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-12-24
Procurement Satisfactory 2024-12-24
Project Management Satisfactory 2024-12-24
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-24
Overall Safeguards Rating Satisfactory 2024-12-24
Financial Management Moderately Satisfactory 2024-12-24
Monitoring and Evaluation Satisfactory 2024-12-24

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people with access to improved public infrastructure as a result of the projectValue0.00686095.00780800.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Number of people with access to climate resilient multi-purpose disaster shelters as a result of the projectValue0.0012500.0081000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Households participating in community workfare and servicesValue0.00175541.00100000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Development of the DRP Camp Management SystemValueNoYesYes
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Households supported through the participation of DRP women in community workfare and servicesValue0.000.000.00
    Date
    Comment
  • Of which are DRPValue0.00551447.00640000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are DRPValue0.0012500.0055500.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are DRP femalesValue0.00286752.00332800.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are DRP femalesValue0.006500.0028860.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are host communityValue0.00134648.00140800.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are host communityValue0.000.0025500.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are host community femalesValue0.0073686.0070400.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are host community femalesValue0.000.0012750.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people with access to improved water sources as a result of the projectValue0.00297395.00365800.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Workdays generated through community services (person-days)Value0.007718181.006000000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Beneficiaries satisfied with service deliveryValue0.0060.0070.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Workdays generated through community services (person days) to womenValue0.000.000.00
    Date
    Comment
  • Beneficiaries directly reached by communication activities as a result of the projectValue0.00901643.00540800.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are DRPValue0.00223200.00225000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Workdays generated through community workfare (person-days)Value0.001823409.003600000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are DRPValue0.00551447.00400000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are DRP femalesValue0.00116064.00117000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are DRP femalesValue0.00286752.00208000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are host communityValue0.0074194.00140800.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are host communityValue0.00350196.00140800.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are host community femalesValue0.0037098.0070400.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are host community femalesValue0.00175098.0070400.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Number of people with access to improved sanitation provided as a result of the projectValue0.00126419.00171800.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are DRPValue0.0076000.00117600.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are DRP femalesValue0.0039520.0061152.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are host communityValue0.0050419.0054200.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Of which are host community femalesValue0.0025209.0027100.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Climate resilient multi-purpose disaster shelters/primary schools constructedValue0.006.0040.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Climate resilient multi-purpose disaster shelters/community service centers constructedValue0.005.0030.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Climate resilient roads improved as a result of this projectValue0.00189.74250.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Climate resilient access and evacuation bridges constructed as a result of the projectValue0.0010.0010.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Lightning protection systems installedValue0.00621.00975.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Local markets improvedValue0.003.006.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Solar street lights installed as a result of the projectValue0.004000.004000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Warehouses for firefighting and search & rescue equipment constructedValue0.004.009.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Firefighting and search & rescue equipment provided to FSCDValueNoYesYes
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Women and girls using GBV services as a result of the projectValue0.0024000.0024000.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Construction of solar PV nano-grid systemsValue0.0035.00100.00
    DateDecember 22, 2019April 30, 2024June 30, 2024
    Comment
  • Climate-resilient rubber dams constructed / improved as a result of the projectValue0.001.003.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment
  • Emergency Operations Center (EOC) builtValue0.000.001.00
    DateMarch 5, 2019April 30, 2024June 30, 2024
    Comment