Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 37.89 |
P167788
Active
Ernesto Sanchez-Triana , Jane Kibbassa, Arame Tall, Ayse Calicioglu Sengul
Republic of Senegal,Republic of Zambia,United Republic of Tanzania,Republic of Kenya,Republic of Ghana
Western and Central Africa
November 20, 2018
(as of board presentation)
July 27, 2020
August 14, 2020
US$ 37.89 million
Environmental Protection Agency (EPA),Direction de l’Environnement et des Etablissements Classés - DEEC,The National Environmental Management Council (NEMC),National Environmental Management Authority (Ministry of Environment and Forestry),Zambia Environmental Management Agency
2021
US$ 37.89 million
N/A
Substantial
July 31, 2025
BANK APPROVED
February 9, 2024
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 37.89 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 37.89 |
Total Project Cost** | 37.89 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2025-03-06 |
Financial Management | Moderately Satisfactory | 2025-03-06 |
Monitoring and Evaluation | Moderately Satisfactory | 2025-03-06 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-03-06 |
Procurement | Moderately Satisfactory | 2025-03-06 |
Project Management | Moderately Satisfactory | 2025-03-06 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Piloting of best environmental practices and cleaner technologies to help countries meet their Stockholm and Minamata Convention obligations completed and evaluated | Value | 0.00 | 0.00 | 8.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Knowledge products on mercury and uPOPs management designed and disseminated | Value | 0.00 | 0.00 | 10.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | 0.00 | 0.00 | 1.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | 0.00 | 0.00 | 1.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Senegal | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
Senegal | Value | 0.00 | 1.00 | 2.00 |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
Stakeholder outreach events completed | Value | 0.00 | 0.00 | 40.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Mercury use in ASGM reduced at pilot sites | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | 0.00 | 0.00 | 8.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | 0.00 | 0.00 | 8.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | 0.00 | 0.00 | 8.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Exposure to uPOPs pollution from open burning of hazardous waste including e-waste reduced at pilot sites | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | 0.00 | 0.00 | 8.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Senegal | Value | 0.00 | 2.00 | 8.00 |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
Zambia | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Policy interventions on mercury and e-waste management (including uPOPs emissions) designed and consulted | Value | 0.00 | 0.00 | 10.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Senegal | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
Tanzania | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Senegal | Value | 0.00 | 1.00 | 2.00 |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Private sector in selected pilot project sites engaged | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Senegal | Value | No | No | Yes |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
Guidelines and checklists for stakeholders and workers developed | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Training events for relevant stakeholders conducted | Value | 0.00 | 0.00 | 10.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Senegal | Value | No | No | Yes |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
Senegal | Value | No | No | Yes |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
Senegal | Value | 0.00 | 2.00 | 2.00 |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
Stakeholder communication strategy developed | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Trained inspection officers | Value | 0.00 | 0.00 | 110.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | 0.00 | 0.00 | 30.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Senegal | Value | No | Yes | Yes |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
Senegal | Value | 0.00 | 0.00 | 20.00 |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
Tanzania: % female participants | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Ghana: % female participants | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Zambia: % female participants | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Kenya: % female participants | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Senegal: % female participants | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Communities involved in planning, implementation and evaluation of demonstration pilots | Value | 0.00 | 0.00 | 10.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Tanzania | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Ghana | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Zambia | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Kenya | Value | 0.00 | 0.00 | 2.00 |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |
Senegal | Value | 0.00 | 2.00 | 2.00 |
Date | November 29, 2019 | December 1, 2022 | April 23, 2025 | |
Comment |
E-waste management and mercury use benchmarked in participating countries (volume/Mt) through the regional platform | Value | No | No | Yes |
Date | November 29, 2019 | October 26, 2020 | April 23, 2025 | |
Comment |