Financier | Commitments |
---|---|
Local Communities | 20.00 |
IDA Credit | 300.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 30.00 |
P167794
Active
Wendwosen Feleke , Fook Eng, Amanuel Woldetsadik
The Federal Democratic Republic of Ethiopia
February 28, 2019
(as of board presentation)
June 13, 2019
December 16, 2019
US$ 350.00 million
Ministry of Education,Ministry of Water and Energy,Water Development Fund,Ministry of Health
2019
US$ 300.00 million
B
November 14, 2024
January 7, 2027
No
BANK APPROVED
Financier | Commitments |
---|---|
Local Communities | 20.00 |
IDA Credit | 300.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 30.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 300.00 |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 350.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 13, 2019 | IDA-64450 | Loan Commitment | 300,000,000.00 |
Oct 22, 2021 | IDA-64450 | Loan Disb | 4,714,851.00 |
Oct 15, 2021 | IDA-64450 | Int Charges | 648.42 |
Oct 15, 2021 | IDA-64450 | Int Charges | 648.42 |
Oct 15, 2021 | IDA-64450 | Int Charges | 111,423.79 |
Oct 15, 2021 | IDA-64450 | Int Charges | 111,423.79 |
Apr 16, 2021 | IDA-64450 | Int Charges | 86,391.25 |
Apr 16, 2021 | IDA-64450 | Int Charges | 86,391.25 |
Apr 16, 2021 | IDA-64450 | Int Charges | 270.08 |
Apr 16, 2021 | IDA-64450 | Int Charges | 270.08 |
Jan 20, 2021 | IDA-64450 | Loan Disb | 13,803,090.00 |
Oct 15, 2022 | IDA-64450 | Int Charges | 11,230.69 |
Oct 15, 2022 | IDA-64450 | Int Charges | 11,230.69 |
Oct 15, 2022 | IDA-64450 | Int Charges | 213,852.98 |
Oct 15, 2022 | IDA-64450 | Int Charges | 213,852.98 |
Mar 2, 2022 | IDA-64450 | Loan Disb | 158,038.58 |
Feb 15, 2022 | IDA-64450 | Loan Disb | 12,326,960.00 |
Apr 27, 2022 | IDA-64450 | Loan Disb | 16,273,675.00 |
Apr 15, 2022 | IDA-64450 | Int Charges | 672.32 |
Apr 15, 2022 | IDA-64450 | Int Charges | 672.32 |
Apr 15, 2022 | IDA-64450 | Int Charges | 127,346.44 |
Apr 15, 2022 | IDA-64450 | Int Charges | 127,346.44 |
Jun 22, 2023 | IDA-64450 | Loan Disb | 4,125,807.80 |
Apr 28, 2023 | IDA-64450 | Int Charges | 220,347.56 |
Apr 28, 2023 | IDA-64450 | Int Charges | 220,347.56 |
Apr 15, 2023 | IDA-64450 | Int Charges | 7,739.06 |
Apr 15, 2023 | IDA-64450 | Int Charges | 7,739.06 |
May 5, 2023 | IDA-64450 | Loan Disb | 6,189,600.00 |
Apr 15, 2024 | IDA-64450 | Int Charges | 19,887.53 |
Apr 15, 2024 | IDA-64450 | Int Charges | 19,887.53 |
Apr 15, 2024 | IDA-64450 | Int Charges | 593,424.25 |
Apr 15, 2024 | IDA-64450 | Int Charges | 593,424.25 |
Oct 30, 2023 | IDA-64450 | Int Charges | 1,641.49 |
Oct 30, 2023 | IDA-64450 | Int Charges | 1,641.49 |
Oct 30, 2023 | IDA-64450 | Int Charges | 257,247.60 |
Oct 30, 2023 | IDA-64450 | Int Charges | 257,247.60 |
Oct 2, 2023 | IDA-64450 | Loan Disb | 87,922,784.00 |
Oct 20, 2020 | IDA-64450 | Int Charges | 60,897.98 |
Oct 20, 2020 | IDA-64450 | Int Charges | 60,897.98 |
Apr 16, 2020 | IDA-64450 | Loan Disb | 15,810,852.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-11-03 |
Financial Management | Moderately Satisfactory | 2024-11-03 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-11-03 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-11-03 |
Procurement | Moderately Satisfactory | 2024-11-03 |
Project Management | Moderately Satisfactory | 2024-11-03 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people provided with access to safe sanitation services under the Project | Value | 0.00 | 1335513.00 | 1893000.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Proportion of water schemes that are functional and supply safe drinking water in areas under the Project | Value | 0.00 | 0.00 | 75.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Number of people provided with access to safe drinking water services under the Project | Value | 0.00 | 467302.00 | 3012000.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Proportion of rural and urban water supply scheme designs using data from the water resources management information system | Value | 0.00 | 0.00 | 75.00 |
Date | January 4, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Proportion of kebeles within the Project woredas declared and verified as open defecation free | Value | 0.00 | 36.00 | 80.00 |
Date | June 30, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Rural | Value | 0.00 | 1293758.00 | 1451000.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Rural | Value | 0.00 | 0.00 | 75.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Rural | Value | 0.00 | 402783.00 | 2015000.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Urban | Value | 0.00 | 41755.00 | 442000.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Urban | Value | 0.00 | 0.00 | 100.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Urban | Value | 0.00 | 64519.00 | 997000.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Proportion of urban water service providers covering their operational costs under the Project | Value | 0.00 | 0.00 | 100.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Female | Value | 0.00 | 667756.00 | 946500.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Female | Value | 0.00 | 251366.00 | 1506000.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of institutions (schools and health facilities) provided with advanced WASH facilities under the Project | Value | 0.00 | 1983.00 | 2846.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Improved community water supply schemes constructed/rehabilitated under the Project | Value | 0.00 | 1631.00 | 8260.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Additional volume of water available from improved water sources and NRW saving in towns under the Project | Value | 0.00 | 3841.00 | 47530.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Sector Management Information System (MIS) operationalized | Value | No | No | Yes |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Drought and flood early warning systems enhanced and operational | Value | No | No | Yes |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Percentage of water supply schemes with regular water quality and quantity monitoring in towns under the Project | Value | 0.00 | 0.00 | 100.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Schools | Value | 0.00 | 830.00 | 1453.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
New | Value | 0.00 | 1467.00 | 6800.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Number of public/communal latrines constructed/rehabilitated in urban towns under the Project | Value | 0.00 | 7.00 | 55.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Percentage of grievances registered related to delivery of sub-project benefits that are timely and satisfactorily addressed | Value | 0.00 | 100.00 | 80.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Health Facilities | Value | 0.00 | 1153.00 | 1393.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Rehabilitation | Value | 0.00 | 164.00 | 1460.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Percentage of water supply schemes with regular water quality and quantity monitoring under the Project woredas | Value | 0.00 | 0.00 | 75.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Number of fecal sludge management systems constructed and providing service in the towns under the Project | Value | 0.00 | 0.00 | 20.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Percentage of schemes with completed environmental and social screening processes and against which required mitigation measures including compensations are settled | Value | 0.00 | 76.00 | 100.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Number of safely managed latrines constructed under the Project | Value | 0.00 | 326896.00 | 342000.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Sanitation marketing centers established and functional under the Project | Value | 0.00 | 62.00 | 83.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Proportion of water supply schemes constructed that are managed by legally established and functional WASHCOMs under the Project | Value | 0.00 | 71.00 | 60.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |
Proportion of WASHCOMs with at least 50 percent participation of women under the Project | Value | 0.00 | 100.00 | 95.00 |
Date | July 1, 2019 | June 30, 2023 | June 30, 2024 | |
Comment |