One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA)

Abstract*

The development objective of the Consolidated Water Supply, Sanitation (WSS), and Hygiene Account Project for Ethiopia is to increase access to safe WSS, and hygiene services and strengthen capacity for water resources management and service delivery. The project comprises of five components. The first component, rural WSS, and hygiene will help increase access to safe and reliable WSS services and promote hygienic practices in selected rural woredas...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase access to safe water supply, sanitation, and hygiene services and strengthen capacity for water resources management and service delivery.

Key Details

Project Details

  • P167794

  • Active

  • Wendwosen Feleke , Fook Eng, Amanuel Woldetsadik

  • The Federal Democratic Republic of Ethiopia

  • Ethiopia

  • February 28, 2019

  • (as of board presentation)

    June 13, 2019

  • December 16, 2019

  • US$ 350.00 million

  • Ministry of Education,Ministry of Water and Energy,Water Development Fund,Ministry of Health

  • Eastern and Southern Africa

  • 2019

  • US$ 300.00 million

  • B

  • November 14, 2024

  • January 7, 2027

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Communities 20.00
IDA Credit 300.00
Local Govts. (Prov., District, City) of Borrowing Country 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 300.00
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 350.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 13, 2019 IDA-64450 Loan Commitment 300,000,000.00
Oct 22, 2021 IDA-64450 Loan Disb 4,714,851.00
Oct 15, 2021 IDA-64450 Int Charges 648.42
Oct 15, 2021 IDA-64450 Int Charges 648.42
Oct 15, 2021 IDA-64450 Int Charges 111,423.79
Oct 15, 2021 IDA-64450 Int Charges 111,423.79
Apr 16, 2021 IDA-64450 Int Charges 86,391.25
Apr 16, 2021 IDA-64450 Int Charges 86,391.25
Apr 16, 2021 IDA-64450 Int Charges 270.08
Apr 16, 2021 IDA-64450 Int Charges 270.08
Jan 20, 2021 IDA-64450 Loan Disb 13,803,090.00
Oct 15, 2022 IDA-64450 Int Charges 11,230.69
Oct 15, 2022 IDA-64450 Int Charges 11,230.69
Oct 15, 2022 IDA-64450 Int Charges 213,852.98
Oct 15, 2022 IDA-64450 Int Charges 213,852.98
Mar 2, 2022 IDA-64450 Loan Disb 158,038.58
Feb 15, 2022 IDA-64450 Loan Disb 12,326,960.00
Apr 27, 2022 IDA-64450 Loan Disb 16,273,675.00
Apr 15, 2022 IDA-64450 Int Charges 672.32
Apr 15, 2022 IDA-64450 Int Charges 672.32
Apr 15, 2022 IDA-64450 Int Charges 127,346.44
Apr 15, 2022 IDA-64450 Int Charges 127,346.44
Jun 22, 2023 IDA-64450 Loan Disb 4,125,807.80
Apr 28, 2023 IDA-64450 Int Charges 220,347.56
Apr 28, 2023 IDA-64450 Int Charges 220,347.56
Apr 15, 2023 IDA-64450 Int Charges 7,739.06
Apr 15, 2023 IDA-64450 Int Charges 7,739.06
May 5, 2023 IDA-64450 Loan Disb 6,189,600.00
Apr 15, 2024 IDA-64450 Int Charges 19,887.53
Apr 15, 2024 IDA-64450 Int Charges 19,887.53
Apr 15, 2024 IDA-64450 Int Charges 593,424.25
Apr 15, 2024 IDA-64450 Int Charges 593,424.25
Oct 30, 2023 IDA-64450 Int Charges 1,641.49
Oct 30, 2023 IDA-64450 Int Charges 1,641.49
Oct 30, 2023 IDA-64450 Int Charges 257,247.60
Oct 30, 2023 IDA-64450 Int Charges 257,247.60
Oct 2, 2023 IDA-64450 Loan Disb 87,922,784.00
Oct 20, 2020 IDA-64450 Int Charges 60,897.98
Oct 20, 2020 IDA-64450 Int Charges 60,897.98
Apr 16, 2020 IDA-64450 Loan Disb 15,810,852.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-11-03
Financial Management Moderately Satisfactory 2024-11-03
Monitoring and Evaluation Moderately Satisfactory 2024-11-03
Overall Implementation Progress (IP) Moderately Satisfactory 2024-11-03
Procurement Moderately Satisfactory 2024-11-03
Project Management Moderately Satisfactory 2024-11-03

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people provided with access to safe sanitation services under the ProjectValue0.001335513.001893000.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Proportion of water schemes that are functional and supply safe drinking water in areas under the ProjectValue0.000.0075.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Number of people provided with access to safe drinking water services under the ProjectValue0.00467302.003012000.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Proportion of rural and urban water supply scheme designs using data from the water resources management information systemValue0.000.0075.00
    DateJanuary 4, 2019June 30, 2023June 30, 2024
    Comment
  • Proportion of kebeles within the Project woredas declared and verified as open defecation freeValue0.0036.0080.00
    DateJune 30, 2019June 30, 2023June 30, 2024
    Comment
  • RuralValue0.001293758.001451000.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • RuralValue0.000.0075.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • RuralValue0.00402783.002015000.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • UrbanValue0.0041755.00442000.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • UrbanValue0.000.00100.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • UrbanValue0.0064519.00997000.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Proportion of urban water service providers covering their operational costs under the ProjectValue0.000.00100.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • FemaleValue0.00667756.00946500.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • FemaleValue0.00251366.001506000.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of institutions (schools and health facilities) provided with advanced WASH facilities under the ProjectValue0.001983.002846.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Improved community water supply schemes constructed/rehabilitated under the ProjectValue0.001631.008260.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Additional volume of water available from improved water sources and NRW saving in towns under the ProjectValue0.003841.0047530.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Sector Management Information System (MIS) operationalizedValueNoNoYes
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Drought and flood early warning systems enhanced and operationalValueNoNoYes
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Percentage of water supply schemes with regular water quality and quantity monitoring in towns under the ProjectValue0.000.00100.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • SchoolsValue0.00830.001453.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • NewValue0.001467.006800.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Number of public/communal latrines constructed/rehabilitated in urban towns under the ProjectValue0.007.0055.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Percentage of grievances registered related to delivery of sub-project benefits that are timely and satisfactorily addressedValue0.00100.0080.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Health FacilitiesValue0.001153.001393.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • RehabilitationValue0.00164.001460.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Percentage of water supply schemes with regular water quality and quantity monitoring under the Project woredasValue0.000.0075.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Number of fecal sludge management systems constructed and providing service in the towns under the ProjectValue0.000.0020.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Percentage of schemes with completed environmental and social screening processes and against which required mitigation measures including compensations are settledValue0.0076.00100.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Number of safely managed latrines constructed under the ProjectValue0.00326896.00342000.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Sanitation marketing centers established and functional under the ProjectValue0.0062.0083.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Proportion of water supply schemes constructed that are managed by legally established and functional WASHCOMs under the ProjectValue0.0071.0060.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment
  • Proportion of WASHCOMs with at least 50 percent participation of women under the ProjectValue0.00100.0095.00
    DateJuly 1, 2019June 30, 2023June 30, 2024
    Comment