Cameroon-Chad Transport Corridor

Development Objective

The proposed project development objective is to improve the efficiency and safety of regional trade transport along the Douala-N’Djamena intermodal corridor.

Key Details

Project Details

  • P167798

  • Active

  • Papa Ndiaye , Ndeye Ba

  • Republic of Cameroon,Republic of Chad

  • Western and Central Africa

  • October 9, 2021

  • (as of board presentation)

    February 15, 2022

  • December 21, 2022

  • US$ 816.00 million

  • Ministère des Transports (Ministry of Transport),Ministère des Infrastructures et du Désenclavement (Ministry for Infrastructure and Opening-up),CAMRAIL

  • Western and Central Africa

  • 2022

  • US$ 713.00 million

  • B

  • April 4, 2024

  • June 30, 2032

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
EC: European Investment Bank 130.00
IDA Credit 313.00
EC: European Development Fund (EDF) 45.00
IDA Grant 225.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 538.00
IBRD + IDA Commitment 538.00
Lending Instrument
Grant Amount 175.00
Total Project Cost** 816.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 21, 2022 IDA-D9680 Loan Disb 730,134.70
Jan 8, 2024 IDA-D9680 Loan Disb 26,348.87
Jun 8, 2023 IDA-D9680 Loan Disb 721,749.00
May 31, 2023 IDA-D9680 Loan Disb 3,781,029.00
Jun 25, 2024 IDA-D9680 Loan Disb 182,117.98
Aug 16, 2024 IDA-D9680 Loan Disb 1,066,677.50
Mar 28, 2024 IDA-D9680 Loan Disb 3,764,315.20
Jun 8, 2023 IDA-D9680 Loan Disb -721,749.00
Jul 31, 2024 IDA-D9680 Loan Disb 1,221,011.80
Feb 9, 2024 IDA-D9680 Loan Disb 55,102.67
Feb 9, 2024 IDA-D9680 Loan Disb 32,058.14
Feb 9, 2024 IDA-D9680 Loan Disb 39,749.85
Feb 9, 2024 IDA-D9680 Loan Disb 53,085.16
Jan 29, 2024 IDA-D9680 Loan Disb 51,090.52
May 24, 2024 IDA-D9680 Loan Disb 41,239.03
Jul 15, 2024 IDA-D9680 Loan Disb 922,803.90
Apr 4, 2024 IDA-D9680 Loan Disb 13,350,729.00
Apr 4, 2024 IDA-D9680 Loan Disb 15,019,570.00
Mar 28, 2024 IDA-D9680 Loan Disb 3,346,058.00
Apr 26, 2024 IDA-D9680 Loan Disb 198,478.40
Feb 15, 2022 IDA-70360 Loan Commitment 313,000,000.00
Feb 15, 2022 IDA-D9680 Loan Commitment 225,000,000.00
Jun 13, 2024 IDA-70360 Loan Disb 725,377.90
Jul 23, 2024 IDA-70360 Loan Disb 1,658,320.60

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-10-16
Procurement Moderately Satisfactory 2024-10-16
Financial Management Moderately Satisfactory 2024-10-16
Project Management Moderately Satisfactory 2024-10-16
Monitoring and Evaluation Moderately Satisfactory 2024-10-16
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-16

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Freight transit time from departing the Port of Douala to arriving in N'Djamena along the project intermodal corridor (Days)Value20.0020.0012.20
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Reduction in the number of victims (casualties and/or hospitalizations) per vehicle-km reported on the project intermodal corridorValue0.000.0030.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Rail transit time from departing the Port of Douala to arriving at the Ngaoundéré platformValue7.107.105.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Reduction in the number of casualties and hospitalizations per train-km reported on the rail section of the project corridor (Douala-Yaoundé)Value0.000.0030.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Unloading and loading time at the Ngaoundéré platformValue1.701.701.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Reduction in the number of casualties per vehicle-km reported on the road section of the project corridorValue0.000.0030.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Road transport time from Ngaoundéré to N'DjamenaValue4.204.202.20
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Customs clearance time at destinationValue7.007.004.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Transport cost of one ton of freight along the project intermodal corridorValue155.38155.38141.16
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Rail transport costs for one ton of freight from departing the Port of Douala to arriving at the Ngaoundéré platformValue60.0060.0055.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Offloading cost for one ton of freight at the Ngaoundéré platformValue1.381.381.16
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Road transport operating costs for one ton of freight from Ngaoundéré to N'DjamenaValue94.0064.0085.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct and indirect beneficiariesValue0.000.008800000.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Direct and indirect beneficiariesValue0.000.003100000.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Platforms rehabilitatedValue0.000.00100.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Revision of major customs agreements between Chadian and Cameroonian administrationsValueNoNoYes
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Freight volume of the rail section the project corridorValue1.331.331.53
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Freight volume on the road component of the project corridorValue0.380.380.94
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Railway Master Plan updatedValueNoNoYes
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Formal registration procedure set in place for transportersValueNoNoYes
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Length of railway track rehabilitated to climate-resilient standardsValue0.000.00238.10
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Length of road rehabilitated to climate-resilient standardsValue0.000.00494.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Implementation of a diploma course for the railway sector in CameroonValueNoNoYes
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Chadian operators using the e-GUCE platformValue0.000.0050.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Rate of progress of railway signaling modernization worksValue0.000.00100.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Length of road maintained to climate-resilient standards on performance-based contractValue0.000.00577.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Operationalization of the center for collection and analysis of road safety dataValueNoNoYes
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Transparent freight allocation procedureValueNoNoYes
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Derailments reported per 1,000 trains operated on the project section of the railwayValue0.600.600.20
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Calibrated axle-load monitoring stations along the corridorValue0.000.006.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Registered grievances responded to and/or resolved within the stipulated service standards for response timeValue0.000.00100.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Share of women among workers employed during track rehabilitation and maintenanceValue5.705.7020.00
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment
  • Debt service coverage ratio of CAMRAILValue1.711.711.20
    DateFebruary 15, 2022March 12, 2024June 30, 2032
    Comment