Financier | Commitments |
---|---|
IDA Grant | 20.84 |
IDA Credit | 4.16 |
P167870
Closed
Syed Al-Zayed
People's Republic of Bangladesh
September 19, 2018
(as of board presentation)
September 19, 2018
N/A
US$ 25.00 million
Ministry of Primary and Mass Education (MoPME)
2019
US$ 25.00 million
B
September 6, 2022
June 30, 2021
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 20.84 |
IDA Credit | 4.16 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 25.00 |
IBRD + IDA Commitment | 25.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 25.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries: Number of out-of-school children enrolled in LCs | Value | 141000.00 | 687556.00 | 690000.00 |
Date | June 30, 2013 | March 29, 2018 | December 31, 2018 | |
Comment |
Percentage of female students enrolled in LC | Value | 50.00 | 49.00 | 50.00 |
Date | December 31, 2012 | March 29, 2018 | December 31, 2018 | |
Comment |
Percentage of disadvantaged students | Value | 70.00 | 87.00 | 85.00 |
Date | December 31, 2012 | March 29, 2018 | December 31, 2018 | |
Comment |
Average Grade retention rate | Value | 60.00 | 80.00 | 75.00 |
Date | December 31, 2012 | March 29, 2018 | December 31, 2018 | |
Comment |
Completion rate for LC students | Value | 73.00 | 91.85 | 78.00 |
Date | July 31, 2012 | December 31, 2017 | December 31, 2018 | |
Comment |
Completion of systematic student learning assessment | Value | No | Yes | Yes |
Date | December 31, 2012 | June 30, 2016 | December 31, 2017 | |
Comment |
Number of student-years supported | Value | 226991.00 | 1498898.00 | 1343068.00 |
Date | June 30, 2013 | November 5, 2013 | December 31, 2018 | |
Comment |
Number of DRP children enrolled in non-formal learning centers, disaggregated by gender (cumulative) | Value | 0.00 | 0.00 | 200000.00 |
Date | June 30, 2018 | December 31, 2020 | ||
Comment |
Number of DRP Children-year supported | Value | 0.00 | 0.00 | 350000.00 |
Date | June 30, 2018 | December 31, 2020 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of LCs supported | Value | 8400.00 | 20239.00 | 21700.00 |
Date | December 31, 2012 | August 31, 2017 | December 31, 2018 | |
Comment |
Student attendance rate | Value | 75.00 | 85.00 | 85.00 |
Date | December 31, 2012 | August 31, 2017 | December 31, 2018 | |
Comment |
Number of students in urban slum pilots | Value | 0.00 | 47975.00 | 50000.00 |
Date | December 31, 2012 | August 31, 2017 | December 31, 2018 | |
Comment |
Number of teachers trained under the project | Value | 0.00 | 19630.00 | 21700.00 |
Date | October 31, 2012 | August 31, 2017 | December 31, 2018 | |
Comment |
Number of skills training voucher utilized | Value | 0.00 | 12000.00 | 25000.00 |
Date | December 31, 2012 | March 30, 2018 | December 31, 2018 | |
Comment |
Number of Impact Evaluation Studies | Value | 0.00 | 2.00 | 4.00 |
Date | December 31, 2012 | June 30, 2016 | December 31, 2018 | |
Comment |
The number of LCs supported for the DRP in Cox’s bazar district | Value | 0.00 | 0.00 | 1500.00 |
Date | June 30, 2018 | December 31, 2020 | ||
Comment |
The number of teachers received special training in Cox’s Bazar district | Value | 0.00 | 0.00 | 2000.00 |
Date | June 30, 2018 | December 31, 2020 | ||
Comment |
Number of consultations held with DRP and host community during implementation | Value | 0.00 | 0.00 | 4.00 |
Date | June 30, 2018 | December 31, 2020 | ||
Comment |