Financier | Commitments |
---|---|
Free-standing Single Purpose Trust Fund | 72.00 |
Borrower/Recipient | 7.00 |
EC: European Investment Bank | 50.00 |
P167974
Closed
Rohan Shah , Joanna Moody
Sint Maarten Government
St Maarten
December 19, 2018
(as of board presentation)
September 18, 2019
April 7, 2020
US$ 129.00 million
National Recovery Program Bureau,Princess Juliana International Airport Operating Company N.V.
2020
US$ 122.00 million
N/A
Low
June 30, 2025
No
BANK APPROVED
April 9, 2024
Financier | Commitments |
---|---|
Free-standing Single Purpose Trust Fund | 72.00 |
Borrower/Recipient | 7.00 |
EC: European Investment Bank | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 122.00 |
Total Project Cost** | 129.00 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2025-06-25 |
Monitoring and Evaluation | Highly Satisfactory | 2025-06-25 |
Overall Implementation Progress (IP) | Highly Satisfactory | 2025-06-25 |
Progress towards achievement of PDO | Highly Satisfactory | 2025-06-25 |
Procurement | Highly Satisfactory | 2025-06-25 |
Project Management | Highly Satisfactory | 2025-06-25 |
Financial Management | Satisfactory | 2025-06-25 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Resistance of terminal building to Irma-level hurricanes | Value | No | No | Yes |
Date | March 1, 2019 | December 14, 2023 | June 30, 2025 | |
Comment |
Passenger handling capacity of the terminal | Value | 1000000.00 | 1000000.00 | 2500000.00 |
Date | March 1, 2019 | December 14, 2023 | June 30, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PJIAE and Government officials trained | Value | 0.00 | 0.00 | 50.00 |
Date | October 21, 2021 | December 14, 2023 | June 30, 2025 | |
Comment |
Replacement of Passenger Boarding Bridges with improved corrosion resistance | Value | Passenger Boarding Bridges not installed | Passenger Boarding Bridges with improved corrosion | Passenger Boarding Bridges with improved corrosion |
Date | June 3, 2019 | December 14, 2023 | June 30, 2025 | |
Comment |
Installation of structurally improved entrance doors | Value | Structurally improved entrance doors not installed | Structurally improved entrance doors not installed | Structurally improved entrance doors installed |
Date | June 3, 2019 | December 14, 2023 | June 30, 2025 | |
Comment |
Replacement of Baggage Handling System | Value | Baggage Handling System not replaced | Baggage Handling System not replaced | Baggage Handling System replaced |
Date | June 3, 2019 | December 14, 2023 | June 30, 2025 | |
Comment |
Replacement of exterior glazing panels | Value | No | No | Yes |
Date | June 1, 2019 | December 14, 2023 | June 30, 2025 | |
Comment |
Completion of package 2 terminal reconstruction works | Value | 0.00 | 59.65 | 100.00 |
Date | March 1, 2019 | December 14, 2023 | June 30, 2025 | |
Comment |
PJIAE submits quarterly reports describing claims received through GRM and how issues were resolved | Value | No | Yes | Yes |
Date | March 1, 2019 | December 14, 2023 | June 30, 2025 | |
Comment |