Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
P168025
Closed
Gang Qin
People's Republic of China
February 4, 2019
(as of board presentation)
March 3, 2020
N/A
US$ 154.40 million
Jingyang Project Management Office
2020
US$ 100.00 million
N/A
Substantial
October 31, 2022
Yes
BANK APPROVED
April 22, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 154.40 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 31, 2022 | IBRD-90450 | Loan Cancel | 88,503,032.00 |
Mar 3, 2020 | IBRD-90450 | Loan Commitment | 100,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2022-06-01 |
Financial Management | Satisfactory | 2022-06-01 |
Monitoring and Evaluation | Satisfactory | 2022-06-01 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2022-06-01 |
Project Management | Satisfactory | 2022-06-01 |
Procurement | Satisfactory | 2022-06-01 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people benefiting from improved water supply services | Value | 0.00 | 0.00 | 220900.00 |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Reduction in Non-Revenue Water Rate [NRW] | Value | 32.00 | 0.00 | 17.00 |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Cost Recovery in water supply services | Value | 100.00 | 0.00 | 100.00 |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Female | Value | 0.00 | 0.00 | 110450.00 |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Number of people benefiting from safely managed sanitation services | Value | 0.00 | 0.00 | 199750.00 |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Female | Value | 0.00 | 0.00 | 99875.00 |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Percentage of customers satisfied with the services provided by the Project Company | Value | 0.00 | 0.00 | 85.00 |
Date | October 16, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Female | Value | 0.00 | 0.00 | 50.00 |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Project company is in compliance with the key performance indicators set out in PPP Agreement | Value | 0.00 | 0.00 | 100.00 |
Date | October 16, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Roadmap for tariff setting in Jingyang district to achieve operational cost recovery approved by JDG | Value | No | No | Yes |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Percentage of women in the communities participating in the community feedback meetings on WSS service quality | Value | 0.00 | 0.00 | 40.00 |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Number of new households connected to wastewater system | Value | 0.00 | 0.00 | 53374.00 |
Date | March 5, 2020 | May 6, 2022 | October 31, 2025 | |
Comment |
Number of workshops to share project experience and lessons in Sichuan Province and China | Value | 0.00 | 0.00 | 3.00 |
Date | October 16, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Quality of water at tap meets quality standards | Value | Yes | Yes | Yes |
Date | October 18, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Percentage of female members on the village service quality monitoring groups | Value | 0.00 | 0.00 | 60.00 |
Date | October 18, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Number of households with improved septic tank and collection and septage removal | Value | 0.00 | 0.00 | 6712.00 |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Quality of effluent from wastewater treatment plants meets effluent standards | Value | Yes | Yes | Yes |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Percentage of communities (village committees) having provided feedback on the WSS services provided by the Project Company | Value | 0.00 | 0.00 | 100.00 |
Date | October 17, 2019 | May 6, 2022 | December 31, 2025 | |
Comment |
Number of households connected to improved piped water system | Value | 0.00 | 0.00 | 86310.00 |
Date | March 5, 2020 | May 6, 2022 | October 31, 2025 | |
Comment |