Statistical Innovation and Capacity Building in the Pacific Islands

Abstract*

The 'Statistical Innovation and Capacity Building in Pacific Islands' project will support the regional organization, the Statistics for Development Division of the Pacific Community, to promote improved statistics management practices and trial innovations in the region.

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the quality of welfare data collection and accessibility to comparable welfare data in the Pacific Island Countries.

Key Details

Project Details

  • P168122

  • Active

  • William Seitz , Taufik Indrakesuma

  • Pacific Community

  • PNG & PI

  • January 11, 2019

  • (as of board presentation)

    February 11, 2020

  • June 9, 2020

  • US$ 4.40 million

  • Pacific Community - Statistics for Development Division (SPC-SDD)

  • East Asia and Pacific

  • 2020

  • US$ 4.40 million

  • N/A

  • August 11, 2023

  • December 31, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 4.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 4.40
IBRD + IDA Commitment 4.40
Lending Instrument
Grant Amount N/A
Total Project Cost** 4.40

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 22, 2023 IDA-D5440 Loan Disb 220,100.00
Jun 3, 2022 IDA-D5440 Loan Disb 214,820.00
Sep 22, 2022 IDA-D5440 Loan Disb 296,295.00
Apr 28, 2023 IDA-D5440 Loan Disb 109,830.00
Mar 8, 2023 IDA-D5440 Loan Disb 263,450.00
Apr 27, 2021 IDA-D5440 Loan Disb 241,670.00
Apr 16, 2024 IDA-D5440 Loan Disb 265,650.00
Sep 29, 2023 IDA-D5440 Loan Disb 159,135.00
Feb 11, 2020 IDA-D5440 Loan Commitment 4,400,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-12-12
Procurement Moderately Unsatisfactory 2024-12-12
Monitoring and Evaluation Satisfactory 2024-12-12
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-12
Project Management Satisfactory 2024-12-12
Financial Management Satisfactory 2024-12-12

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of PSMB-commissioned guidance notes approved and disseminatedValue0.004.0010.00
    DateAugust 30, 2019November 16, 2023December 31, 2025
    Comment
  • Number of regionally comparable indicators published on SPC platformsValue0.0014.0014.00
    DateAugust 30, 2019November 16, 2023December 31, 2025
    Comment
  • Number of experiment reports produced and submitted to PSMBValue0.000.004.00
    DateNovember 7, 2019November 16, 2023December 31, 2025
    Comment
  • Number of harmonized microdata sets published on SPC platformsValue0.008.005.00
    DateNovember 7, 2019November 16, 2023December 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of Pacific Statistics Methods Board meetings held during project lifetimeValue0.007.0010.00
    DateAugust 30, 2019November 16, 2023December 31, 2025
    Comment
  • Number of SPC staff trained in welfare analysisValue0.005.005.00
    DateAugust 30, 2019November 16, 2023December 31, 2025
    Comment
  • Number of consultations held around innovation experiments with beneficiary country NSOs and policymakersValue0.0015.0012.00
    DateNovember 7, 2019November 16, 2023December 31, 2025
    Comment
  • Number of PSMB commissioned works carried out using project financingValue0.002.005.00
    DateAugust 30, 2019November 16, 2023December 31, 2025
    Comment
  • Number of HIES reports produced within 12 months of the completion of data collectionValue0.001.006.00
    DateAugust 30, 2019November 16, 2023December 31, 2025
    Comment
  • Number of beneficiary country NSOs satisfied that their feedback has been reflected in the design of experimentsValue0.003.004.00
    DateNovember 1, 2019November 16, 2023December 31, 2025
    Comment
  • Number of regional workshops conductedValue0.002.003.00
    DateNovember 7, 2019November 16, 2023December 31, 2025
    Comment
  • Number of analytical papers and briefs produced by SPC-SDD over the project lifetimeValue0.0015.0010.00
    DateAugust 30, 2019November 16, 2023December 31, 2025
    Comment
  • Number of data collection innovation proposals approved by PSMBValue0.003.004.00
    DateAugust 30, 2019November 16, 2023December 31, 2025
    Comment
  • Number of gender indicators pubished on SPC platformsValue0.0016.0016.00
    DateAugust 30, 2019November 16, 2023December 31, 2025
    Comment