Financier | Commitments |
---|---|
IDA Credit | 194.36 |
Borrower/Recipient | 81.81 |
P168290
Active
Dzung Nguyen , Steven Rubinyi
Socialist Republic of Vietnam
October 5, 2018
(as of board presentation)
June 11, 2019
May 21, 2020
US$ 276.17 million
Thanh Hoa Project Management Unit,Yen Bai Project Management Unit,Ky Anh Project Management Unit,Hai Duong City Project Management Unit
2019
US$ 194.36 million
B
February 8, 2024
June 30, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 194.36 |
Borrower/Recipient | 81.81 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 194.36 |
IBRD + IDA Commitment | 194.36 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 276.17 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 30, 2023 | IDA-64280 | Loan Disb | 2,698,000.00 |
Nov 27, 2023 | IDA-64290 | Loan Disb | 2,239,410.50 |
Nov 27, 2023 | IDA-64290 | Loan Disb | 147,812.90 |
Nov 27, 2023 | IDA-64290 | Loan Disb | 473,229.84 |
Oct 20, 2023 | IDA-64290 | Loan Disb | 408,407.94 |
Nov 3, 2023 | IDA-64290 | Loan Disb | 222,508.56 |
Jul 24, 2024 | IDA-64290 | Loan Disb | 540,527.40 |
Jul 24, 2024 | IDA-64290 | Loan Disb | 114,418.29 |
Jul 26, 2024 | IDA-64270 | Loan Disb | 813,444.44 |
Jul 24, 2024 | IDA-64290 | Loan Disb | 172,944.20 |
Jul 24, 2024 | IDA-64290 | Loan Disb | 890,749.25 |
Aug 13, 2024 | IDA-64280 | Loan Disb | 971,987.00 |
Mar 1, 2022 | IDA-64260 | Int Charges | 12,018.91 |
Mar 1, 2022 | IDA-64280 | Int Charges | 49,490.19 |
Mar 1, 2022 | IDA-64280 | Int Charges | 16,150.10 |
Mar 1, 2022 | IDA-64270 | Int Charges | 3,447.97 |
Mar 1, 2022 | IDA-64270 | Int Charges | 51,047.47 |
Mar 1, 2022 | IDA-64270 | Int Charges | 74,270.84 |
Feb 8, 2022 | IDA-64270 | Loan Disb | 1,062,117.00 |
Jan 22, 2024 | IDA-64290 | Loan Disb | 2,012,725.10 |
Jan 22, 2024 | IDA-64290 | Loan Disb | 614,368.10 |
Jan 22, 2024 | IDA-64290 | Loan Disb | 184,497.22 |
Jan 18, 2022 | IDA-64260 | Loan Disb | 2,311,000.00 |
Dec 30, 2021 | IDA-64270 | Loan Disb | 784,878.94 |
Dec 23, 2021 | IDA-64280 | Loan Disb | 3,552,173.00 |
Dec 5, 2023 | IDA-64290 | Loan Disb | 812,486.80 |
Dec 5, 2023 | IDA-64290 | Loan Disb | 495,309.30 |
Dec 5, 2023 | IDA-64290 | Loan Disb | 126,123.24 |
Dec 18, 2023 | IDA-64290 | Loan Disb | 465,000.00 |
Dec 18, 2023 | IDA-64270 | Loan Disb | 1,870,368.00 |
Dec 7, 2023 | IDA-64290 | Loan Disb | 127,222.82 |
Oct 11, 2023 | IDA-64270 | Loan Disb | 1,692,558.60 |
Jan 16, 2024 | IDA-64280 | Loan Disb | 1,922,862.00 |
Jan 17, 2024 | IDA-64270 | Loan Disb | 1,389,372.10 |
Sep 1, 2021 | IDA-64270 | Int Charges | 21,717.64 |
Sep 1, 2021 | IDA-64270 | Int Charges | 1,007.42 |
Sep 1, 2021 | IDA-64270 | Int Charges | 4,753.38 |
Aug 5, 2021 | IDA-64270 | Loan Disb | 4,364,150.00 |
Oct 1, 2021 | IDA-64260 | Loan Disb | 242,718.00 |
Sep 1, 2021 | IDA-64260 | Int Charges | 201.94 |
Sep 1, 2021 | IDA-64260 | Int Charges | 952.88 |
Sep 1, 2021 | IDA-64260 | Int Charges | 48,272.77 |
Sep 1, 2021 | IDA-64260 | Int Charges | 7,685.08 |
Sep 30, 2021 | IDA-64270 | Loan Disb | 4,668,460.00 |
Sep 17, 2021 | IDA-64280 | Loan Disb | 1,355,000.00 |
Jun 15, 2022 | IDA-64270 | Loan Disb | 91,740.22 |
Jul 27, 2022 | IDA-64270 | Loan Disb | 674,299.56 |
Jul 11, 2022 | IDA-64270 | Loan Disb | 783,299.94 |
May 20, 2022 | IDA-64260 | Loan Disb | 2,516,000.00 |
Jun 29, 2022 | IDA-64270 | Loan Disb | 399,925.56 |
Jun 13, 2022 | IDA-64290 | Loan Disb | 1,921,000.00 |
May 18, 2022 | IDA-64270 | Loan Disb | 137,158.06 |
Mar 1, 2022 | IDA-64270 | Int Charges | 807.07 |
Mar 1, 2022 | IDA-64290 | Int Charges | 72,324.96 |
Mar 1, 2022 | IDA-64290 | Int Charges | 4,905.50 |
Mar 1, 2022 | IDA-64260 | Int Charges | 45,883.92 |
Jan 19, 2022 | IDA-64270 | Loan Disb | 762,323.56 |
Dec 20, 2021 | IDA-64290 | Loan Disb | 1,989,837.00 |
Nov 22, 2022 | IDA-64290 | Loan Disb | 270,906.20 |
Nov 22, 2022 | IDA-64290 | Loan Disb | 292,923.22 |
Nov 22, 2022 | IDA-64290 | Loan Disb | 744,526.30 |
Nov 23, 2022 | IDA-64290 | Loan Disb | 2,232,015.80 |
Dec 21, 2022 | IDA-64280 | Loan Disb | 3,081,000.00 |
Dec 20, 2022 | IDA-64260 | Loan Disb | 3,550,000.00 |
Dec 1, 2022 | IDA-64290 | Loan Disb | 1,179,111.00 |
Nov 28, 2022 | IDA-64290 | Loan Disb | 139,860.00 |
Nov 28, 2022 | IDA-64270 | Loan Disb | 724,526.80 |
Nov 9, 2022 | IDA-64280 | Loan Disb | 2,600,000.00 |
Nov 14, 2022 | IDA-64290 | Loan Disb | 206,602.50 |
Nov 15, 2022 | IDA-64290 | Loan Disb | 299,935.60 |
Sep 1, 2022 | IDA-64260 | Int Charges | 42,564.84 |
Sep 1, 2022 | IDA-64260 | Int Charges | 56,086.43 |
Sep 1, 2022 | IDA-64260 | Int Charges | 664.80 |
Sep 1, 2022 | IDA-64270 | Int Charges | 149,618.75 |
Sep 1, 2022 | IDA-64280 | Int Charges | 48,406.54 |
Sep 1, 2022 | IDA-64280 | Int Charges | 47,364.68 |
Sep 1, 2022 | IDA-64260 | Int Charges | 2,705.40 |
Sep 1, 2022 | IDA-64270 | Int Charges | 366.85 |
Sep 1, 2022 | IDA-64270 | Int Charges | 1,492.86 |
Sep 1, 2022 | IDA-64270 | Int Charges | 47,599.57 |
Sep 1, 2022 | IDA-64290 | Int Charges | 70,947.05 |
Sep 1, 2022 | IDA-64290 | Int Charges | 27,867.59 |
Sep 14, 2022 | IDA-64280 | Loan Disb | 2,788,781.00 |
Jan 9, 2023 | IDA-64290 | Loan Disb | 688,028.70 |
Jan 9, 2023 | IDA-64290 | Loan Disb | 292,215.62 |
Dec 13, 2022 | IDA-64290 | Loan Disb | 248,875.10 |
Dec 20, 2022 | IDA-64270 | Loan Disb | 821,735.40 |
Aug 12, 2021 | IDA-64290 | Fee Charges | 147,800.00 |
Apr 21, 2023 | IDA-64260 | Loan Disb | 4,920,000.00 |
Mar 1, 2023 | IDA-64260 | Int Charges | 38,788.34 |
Mar 1, 2023 | IDA-64260 | Int Charges | 193,112.90 |
Mar 1, 2023 | IDA-64270 | Int Charges | 445.26 |
Mar 1, 2023 | IDA-64270 | Int Charges | 3,039.81 |
Mar 1, 2023 | IDA-64270 | Int Charges | 43,718.11 |
Mar 1, 2023 | IDA-64270 | Int Charges | 418,059.97 |
Mar 1, 2023 | IDA-64280 | Int Charges | 243,301.19 |
Mar 1, 2023 | IDA-64290 | Int Charges | 63,137.13 |
Mar 1, 2023 | IDA-64290 | Int Charges | 163,007.10 |
Jan 15, 2021 | IDA-64270 | Loan Disb | 3,268,539.00 |
Jul 14, 2021 | IDA-64280 | Fee Charges | 106,225.00 |
Jun 18, 2021 | IDA-64260 | Loan Disb | 934,000.00 |
Sep 1, 2021 | IDA-64280 | Int Charges | 53,549.04 |
Sep 1, 2021 | IDA-64290 | Int Charges | 74,507.42 |
Mar 1, 2024 | IDA-64290 | Int Charges | 56.11 |
Jul 31, 2024 | IDA-64290 | Loan Disb | 164,638.30 |
May 28, 2024 | IDA-64290 | Loan Disb | 40,000.00 |
Feb 5, 2024 | IDA-64260 | Loan Disb | 4,127,000.00 |
May 6, 2024 | IDA-64290 | Loan Disb | 125,076.45 |
Sep 1, 2023 | IDA-64270 | Int Charges | 721,112.75 |
Jun 29, 2023 | IDA-64270 | Loan Disb | 1,094,036.20 |
May 17, 2023 | IDA-64270 | Loan Disb | 1,150,185.90 |
Aug 14, 2024 | IDA-64290 | Loan Disb | 139,572.70 |
Aug 14, 2024 | IDA-64290 | Loan Disb | 150,716.89 |
Aug 9, 2024 | IDA-64290 | Loan Disb | 140,000.00 |
Jan 29, 2024 | IDA-64290 | Loan Disb | 565,000.00 |
Jan 22, 2024 | IDA-64290 | Loan Disb | 308,519.38 |
Jan 22, 2024 | IDA-64290 | Loan Disb | 139,594.05 |
Apr 20, 2023 | IDA-64270 | Loan Disb | 963,319.40 |
Apr 4, 2023 | IDA-64270 | Loan Disb | 696,339.10 |
Jul 28, 2023 | IDA-64290 | Loan Disb | 234,038.69 |
Aug 1, 2023 | IDA-64280 | Loan Disb | 2,265,000.00 |
Aug 25, 2023 | IDA-64270 | Loan Disb | 945,726.00 |
Sep 1, 2023 | IDA-64280 | Int Charges | 36,209.49 |
Sep 1, 2023 | IDA-64280 | Int Charges | 435,523.90 |
Sep 1, 2023 | IDA-64290 | Int Charges | 56,273.47 |
Sep 1, 2023 | IDA-64290 | Int Charges | 28,963.57 |
Sep 1, 2023 | IDA-64290 | Int Charges | 469,603.60 |
Sep 1, 2023 | IDA-64290 | Int Charges | 1,603.66 |
Sep 7, 2023 | IDA-64290 | Loan Disb | 122,092.71 |
Sep 7, 2023 | IDA-64290 | Loan Disb | 635,340.06 |
Sep 7, 2023 | IDA-64290 | Loan Disb | 454,570.88 |
Sep 1, 2023 | IDA-64260 | Int Charges | 452,095.12 |
Sep 1, 2023 | IDA-64260 | Int Charges | 32,230.33 |
Sep 1, 2023 | IDA-64270 | Int Charges | 414.28 |
Sep 1, 2023 | IDA-64270 | Int Charges | 7,482.57 |
Sep 1, 2023 | IDA-64270 | Int Charges | 39,201.22 |
Sep 1, 2021 | IDA-64270 | Int Charges | 62,233.69 |
Jan 22, 2024 | IDA-64290 | Loan Disb | 286,760.06 |
Feb 2, 2024 | IDA-64280 | Loan Disb | 1,292,894.00 |
Jan 24, 2024 | IDA-64290 | Loan Disb | 279,256.03 |
Jan 24, 2024 | IDA-64290 | Loan Disb | 414,229.53 |
Jan 24, 2024 | IDA-64290 | Loan Disb | 743,607.56 |
Aug 2, 2024 | IDA-64290 | Loan Disb | 254,719.27 |
Mar 1, 2024 | IDA-64260 | Int Charges | 29,448.12 |
Mar 1, 2024 | IDA-64260 | Int Charges | 531,100.00 |
Mar 1, 2024 | IDA-64280 | Int Charges | 480.93 |
Jul 31, 2024 | IDA-64290 | Loan Disb | 328,861.30 |
Mar 1, 2024 | IDA-64270 | Int Charges | 1,126.05 |
Mar 1, 2024 | IDA-64270 | Int Charges | 32,625.01 |
Mar 1, 2024 | IDA-64270 | Int Charges | 931,904.70 |
Mar 1, 2024 | IDA-64290 | Int Charges | 1,393.29 |
Mar 1, 2024 | IDA-64290 | Int Charges | 48,911.81 |
Mar 1, 2024 | IDA-64290 | Int Charges | 651,119.56 |
Mar 1, 2024 | IDA-64280 | Int Charges | 11,943.22 |
Mar 1, 2024 | IDA-64280 | Int Charges | 30,329.71 |
Mar 1, 2024 | IDA-64280 | Int Charges | 608,181.90 |
Mar 1, 2024 | IDA-64270 | Int Charges | 45.34 |
Jul 31, 2024 | IDA-64290 | Loan Disb | 273,313.72 |
Jun 11, 2019 | IDA-64260 | Loan Commitment | 39,460,000.00 |
Jun 11, 2019 | IDA-64270 | Loan Commitment | 53,290,000.00 |
Jun 11, 2019 | IDA-64280 | Loan Commitment | 42,490,000.00 |
Jun 11, 2019 | IDA-64290 | Loan Commitment | 59,120,000.00 |
Jan 13, 2023 | IDA-64270 | Loan Disb | 1,286,946.80 |
Mar 1, 2023 | IDA-64280 | Int Charges | 39,911.69 |
Jan 13, 2023 | IDA-64290 | Loan Disb | 3,917,862.00 |
Sep 1, 2020 | IDA-64260 | Int Charges | 58,489.21 |
Sep 1, 2020 | IDA-64270 | Int Charges | 78,988.57 |
Sep 1, 2020 | IDA-64280 | Int Charges | 62,980.40 |
Sep 1, 2020 | IDA-64290 | Int Charges | 87,630.05 |
Mar 1, 2021 | IDA-64270 | Int Charges | 64,935.90 |
Dec 23, 2020 | IDA-64260 | Fee Charges | 98,650.00 |
Dec 28, 2020 | IDA-64270 | Fee Charges | 133,225.00 |
Mar 1, 2021 | IDA-64260 | Int Charges | 48,627.56 |
Mar 1, 2021 | IDA-64290 | Int Charges | 73,157.62 |
Mar 1, 2021 | IDA-64280 | Int Charges | 52,578.96 |
Jan 22, 2021 | IDA-64260 | Loan Disb | 775,910.50 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Unsatisfactory | 2024-10-03 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2024-10-03 |
Financial Management | Moderately Unsatisfactory | 2024-10-03 |
Procurement | Satisfactory | 2024-10-03 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-10-03 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-10-03 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Area prone to floods in the area covered by the project interventions | Value | 1485.90 | 1406.50 | 407.90 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Cities with improved livability, sustainability, and/or management | Value | 0.00 | 0.00 | 4.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
People provided with improved urban living conditions | Value | 0.00 | 61387.00 | 239793.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Integrated urban development plan – including public transport plan and adequate provision of childcare services – approved for implementation | Value | 0.00 | 0.00 | 1.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
People provided with improved urban living conditions - Female (RMS requirement) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Urban asset management plans approved with approved annual budgets for O&M | Value | 0.00 | 0.00 | 2.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
People benefiting from improved drainage in the area covered by the project interventions | Value | 0.00 | 21407.00 | 206964.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Of which Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Of which Bottom 40% beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People provided with access to improved sanitation provided by the project | Value | 0.00 | 0.00 | 103400.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Of which Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Of which Bottom 40% beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People who have access to new or improved roads under the project | Value | 0.00 | 33800.00 | 83600.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Of which Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Of which Bottom 40% beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Users satisfied with the new or improved roads under the project | Value | 0.00 | 92.70 | 80.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Female users satisfaction | Value | 0.00 | 0.00 | 80.00 |
Date | ||||
Comment |
Bottom 40% users satisfaction | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People provided with access to new or improved public spaces | Value | 0.00 | 23785.00 | 110050.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Of which Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Of which Bottom 40% beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Users satisfied with the new or improved public spaces | Value | 0.00 | 94.30 | 80.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Female users satisfaction | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Bottom 40% users satisfaction | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Length of drains improved or constructed | Value | 0.00 | 22.66 | 50.13 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Beneficiaries involved in consultations for project planning/ implementation/ evaluation | Value | 0.00 | 3632.00 | 4100.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Length of waste water pipeline laid | Value | 0.00 | 86.40 | 277.30 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Of which Female beneficiaries | Value | 0.00 | 0.00 | 50.60 |
Date | ||||
Comment |
Additional waste-water treatment capacity provided | Value | 0.00 | 0.00 | 14600.00 |
Date | March 25, 2018 | January 1, 2024 | June 30, 2025 | |
Comment |
Of which Bottom 40% beneficiaries | Value | 0.00 | 0.00 | 50.00 |
Date | ||||
Comment |
Households connected to new or improved wastewater treatment systems | Value | 0.00 | 0.00 | 31900.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Stakeholder consultation sessions and training activities conducted in integrated urban development planning | Value | 0.00 | 3.00 | 12.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Length of roads and bridges constructed or improved, non-rural (Core) | Value | 0.00 | 19.68 | 30.29 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Area of new or improved walkable public space | Value | 0.00 | 130986.00 | 418861.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Average difference in the amount of time spent by local women as compared to local men on caring for children aged 3-72 months | Value | 51.00 | 51.00 | 30.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Strategic integrated plan developed | Value | 0.00 | 0.00 | 1.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Public transport plan developed | Value | 0.00 | 0.00 | 1.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |
Asset management plan developed | Value | 0.00 | 0.00 | 2.00 |
Date | March 25, 2019 | January 1, 2024 | June 30, 2025 | |
Comment |