Urban Resilience and Solid Waste Management Project

Abstract*

The proposed project components are: 1) Flood risk mitigation infrastructure and services: i) urban drainage and associated roadworks; ii) nature-based solutions for erosion and landslide control; 2) Improvement of solid waste management infrastructure and services: i) strengthening solid waste management capacities in the District of Abidjan and two selected inter-communal groups of secondary cities and ii) Strengthening sector governance, institutional...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objectives of the project are to reduce vulnerability to flooding in selected urban areas and improve solid waste management in targeted municipalities.

Key Details

Project Details

  • P168308

  • Active

  • Vivien Deparday , Laurence Ahiba

  • Republic of Cote d'Ivoire

  • Cote d'Ivoire

  • May 23, 2019

  • (as of board presentation)

    June 12, 2020

  • October 28, 2020

  • US$ 315.00 million

  • N/A

  • High

  • October 31, 2026

  • Yes

  • BANK APPROVED

  • March 18, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 315.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 315.00
IBRD + IDA Commitment 315.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 315.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 1, 2022 IDA-66860 Loan Disb 192,357.60
Sep 16, 2022 IDA-66860 Int Charges 214.18
Sep 16, 2022 IDA-66860 Int Charges 347,405.60
Sep 16, 2022 IDA-66860 Int Charges 18,823.82
Oct 6, 2022 IDA-66860 Loan Disb 307,964.94
Oct 6, 2022 IDA-66860 Loan Disb 543,535.50
Dec 29, 2021 IDA-66860 Loan Disb 433,536.62
May 25, 2022 IDA-66860 Loan Disb 389,906.40
Jan 21, 2022 IDA-66860 Loan Disb 264,098.20
Apr 11, 2024 IDA-66860 Loan Disb 974,056.40
Apr 11, 2024 IDA-66860 Loan Disb 703,327.56
Aug 29, 2024 IDA-66860 Loan Disb 644,267.94
Jun 10, 2024 IDA-66860 Loan Disb 750,889.94
Jul 26, 2024 IDA-66860 Loan Disb 199,342.70
Jun 10, 2024 IDA-66860 Loan Disb 695,044.90
Jun 16, 2023 IDA-66860 Loan Disb 262,164.30
Oct 27, 2023 IDA-66860 Loan Disb 343,868.94
Dec 22, 2023 IDA-66860 Loan Disb 667,157.90
Sep 29, 2023 IDA-66860 Loan Disb 264,956.56
Aug 19, 2024 IDA-66860 Loan Disb 656,972.25
Feb 28, 2024 IDA-66860 Loan Disb 220,596.81
Jun 12, 2020 IDA-66860 Loan Commitment 315,000,000.00
Aug 25, 2022 IDA-66860 Loan Disb 133,023.22
Mar 17, 2022 IDA-66860 Loan Disb 140,349.31
Mar 15, 2022 IDA-66860 Int Charges 4.02
Mar 15, 2022 IDA-66860 Int Charges 7.91
Mar 15, 2022 IDA-66860 Int Charges 381,652.70
Jun 28, 2022 IDA-66860 Loan Disb 312,765.30
May 18, 2022 IDA-66860 Loan Disb 2,437,516.80
May 18, 2022 IDA-66860 Loan Disb 1,625,011.10
Dec 13, 2021 IDA-66860 Loan Disb 487,102.38
Mar 15, 2022 IDA-66860 Int Charges 1,995.56
Apr 28, 2022 IDA-66860 Loan Disb 46,530.64
Jul 28, 2022 IDA-66860 Loan Disb 174,137.39
Feb 24, 2022 IDA-66860 Loan Disb 212,829.97
Sep 13, 2021 IDA-66860 Loan Disb 315,091.97
Sep 15, 2021 IDA-66860 Int Charges 418,591.20
Sep 15, 2021 IDA-66860 Int Charges 30,336.59
Nov 30, 2023 IDA-66860 Loan Disb 388,505.90
Jun 17, 2024 IDA-66860 Loan Disb 603,923.00
Jul 8, 2024 IDA-66860 Loan Disb 244,508.60
Apr 24, 2024 IDA-66860 Loan Disb 1,319,006.90
Jan 19, 2024 IDA-66860 Loan Disb 1,271,095.40
Apr 11, 2024 IDA-66860 Loan Disb 1,133,840.60
May 31, 2024 IDA-66860 Loan Disb 736,179.00
Apr 9, 2024 IDA-66860 Loan Disb 1,001,851.30
Feb 9, 2024 IDA-66860 Loan Disb 617,236.44
Mar 18, 2024 IDA-66860 Int Charges 2,644.90
Mar 18, 2024 IDA-66860 Int Charges 346,876.78
Mar 18, 2024 IDA-66860 Int Charges 27,995.07
May 24, 2024 IDA-66860 Loan Disb 301,317.97
Apr 9, 2024 IDA-66860 Loan Disb 1,219,792.20
Sep 27, 2021 IDA-66860 Loan Disb 142,604.66
Sep 15, 2021 IDA-66860 Loan Disb -8,486,371.00
Oct 28, 2020 IDA-66860 Loan Disb 844,255.60
Oct 28, 2020 IDA-66860 Fee Charges 844,255.60
Mar 15, 2021 IDA-66860 Int Charges 484,506.53
Dec 8, 2020 IDA-66860 Loan Disb 6,090,559.50
Mar 29, 2021 IDA-66860 Loan Disb 57,506.18
Mar 15, 2021 IDA-66860 Int Charges 19,147.25
Jun 7, 2021 IDA-66860 Loan Disb 78,296.20
Sep 15, 2023 IDA-66860 Int Charges 128,796.07
Sep 15, 2023 IDA-66860 Loan Disb 18,262,282.00
Mar 18, 2024 IDA-66860 Int Charges 418,442.10
Mar 18, 2024 IDA-66860 Int Charges 66,477.47
Mar 18, 2024 IDA-66860 Int Charges 131,745.23
Oct 28, 2020 IDA-66860 Loan Disb 1,225,692.00
Sep 15, 2021 IDA-66860 Loan Disb 8,486,371.00
Mar 15, 2022 IDA-66860 Int Charges 67,069.05
Sep 15, 2022 IDA-66860 Loan Disb 6,348,709.00
Sep 16, 2022 IDA-66860 Int Charges 60,897.02
Mar 15, 2023 IDA-66860 Int Charges 64,809.43
Mar 15, 2023 IDA-66860 Int Charges 128,439.51
Sep 15, 2023 IDA-66860 Int Charges 64,989.35
Sep 15, 2022 IDA-66860 Int Charges 109.20
Sep 15, 2022 IDA-66860 Loan Disb -6,348,709.00
Jun 14, 2023 IDA-66860 Loan Disb 419,728.80
Jun 14, 2023 IDA-66860 Loan Disb 2,106,482.80
Jun 14, 2023 IDA-66860 Loan Disb 1,053,591.10
Aug 31, 2023 IDA-66860 Loan Disb 602,079.80
Sep 15, 2023 IDA-66860 Loan Disb -18,262,282.00
Jul 6, 2023 IDA-66860 Loan Disb 3,954,189.00
Sep 15, 2023 IDA-66860 Int Charges 847.93
Sep 15, 2023 IDA-66860 Int Charges 8,746.58
Sep 15, 2023 IDA-66860 Int Charges 352,543.34
Jul 6, 2023 IDA-66860 Loan Disb 892,167.56
Feb 24, 2023 IDA-66860 Loan Disb 587,477.44
Feb 24, 2023 IDA-66860 Loan Disb 965,179.40
May 15, 2023 IDA-66860 Loan Disb 600,683.30
Mar 15, 2023 IDA-66860 Int Charges 81.64
Mar 15, 2023 IDA-66860 Int Charges 196.53
Mar 15, 2023 IDA-66860 Int Charges 357,201.06
Mar 15, 2023 IDA-66860 Int Charges 35,471.00
Aug 1, 2023 IDA-66860 Loan Disb 283,647.50
Sep 15, 2023 IDA-66860 Int Charges 291,017.53
Jan 25, 2023 IDA-66860 Loan Disb 1,946,096.80
Mar 13, 2023 IDA-66860 Loan Disb 281,411.16
Mar 31, 2023 IDA-66860 Loan Disb 522,281.80
Mar 31, 2023 IDA-66860 Loan Disb 843,413.06
Oct 24, 2022 IDA-66860 Loan Disb 576,384.20
Oct 24, 2022 IDA-66860 Loan Disb 661,212.30
Oct 24, 2022 IDA-66860 Loan Disb 371,200.28
Dec 19, 2022 IDA-66860 Loan Disb 134,765.88
Sep 29, 2022 IDA-66860 Loan Disb 175,878.42
Mar 15, 2024 IDA-66860 Int Charges 148.66
Jun 24, 2024 IDA-66860 Loan Disb 1,266,990.20
Jun 24, 2024 IDA-66860 Loan Disb 1,179,451.50
Jun 27, 2024 IDA-66860 Loan Disb 563,094.75
Jun 17, 2024 IDA-66860 Loan Disb 171,480.77
May 16, 2024 IDA-66860 Loan Disb 644,216.06

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2025-04-15
Financial Management Moderately Satisfactory 2025-04-15
Monitoring and Evaluation Moderately Satisfactory 2025-04-15
Project Management Moderately Satisfactory 2025-04-15
Overall Implementation Progress (IP) Moderately Satisfactory 2025-04-15
Procurement Moderately Satisfactory 2025-04-15

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of residents protected against floodingValue0.00281422.00800000.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of people provided with access to improved solid waste services (number)Value001350000
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Of which women (percentage)Value0050%
    DateJanuary 24, 2020October 20, 2022June 30, 2026
    Comment
  • Of which women (percentageValue0050%
    DateJanuary 24, 2020October 20, 2022June 30, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Hectares of Green spaces and leisure areas created including NBS for erosion controlValue0.000.0015.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of signed delegation contract to the private sector in the waste management sector for the District of AbidjanValue0.000.001.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of additionnal secondary cities provided with Sanitation and Storm Water Master Plans through the projectValue0.000.005.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of people trained on solid waste management (number)Value00TBD
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Operational Drainage Operation and Maintenance strategyValueNoNoYes
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Of which women (percentage)Value0050%
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of studies supporting urban planning for municipalitiesValue1.000.005.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of women in small and medium enterprises completing the support program to enhance their chances to enter the SWM marketValue00TBD
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of people covered by an early warning system (number)Value00TBD
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • A system monitoring the number of women economically active in the SWM sector is in placeValueNoNoYes
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of digital information systems for solid waste management created by the projectValue0.000.001.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Of which women (percentage)Value0050%
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Percentage of designated Disaster Risk Reduction committees’ focal points who are womenValue0.000.0090.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of beneficiaries consulted during project implementationValue0.001066.00200.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of cities covered by a digital information system for urban planning created by the projectValue0.000.002.00
    DateJanuary 24, 2020July 11, 2023June 15, 2026
    Comment
  • Of which women (percentage)Value06350%
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Grievances registered related to project that are actually addressedValue0.0093.50100.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Percentage of workers recruited under the project who signed a Code of ConductValue0.00100.00100.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Primary/secondary drainage network and associated roadworks rehabilitated/builtValue0.007.2075.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment
  • Number of Solid waste management infrastructure built and functionalValue0.000.007.00
    DateJanuary 24, 2020July 11, 2023June 30, 2026
    Comment