Lome-Ouagadougou-Niamey Economic Corridor

Abstract*

The development objective of the Lome-Ouagadougou-Niamey (LON) Economic Corridor Project for Burkina Faso, Niger, and Togo is to improve regional connectivity and socio-economic community infrastructure along the corridor between the capital cities of Togo, Burkina Faso, and Niger. The project comprises of five components. The first component, improvement of infrastructure and introduction of intelligent transportation systems on the LON corridor...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The proposed PDO is to improve regional connectivity and socio-economic community infrastructure along the corridor between the capital cities of Togo, Burkina Faso, and Niger.

Key Details

Project Details

  • P168386

  • Active

  • Ibrahim Kabore , Malaika Becoulet, Rima Aloulou

  • Togo,Niger,Burkina Faso

  • Western and Central Africa

  • April 2, 2020

  • (as of board presentation)

    July 16, 2021

  • February 25, 2022

  • US$ 470.00 million

  • Ministry of Road, Air and Rail Transport, Togo,Ministry of Transport, Niger,Ministry of Transport Road Safety and Urban Mobility, Burkina Faso

  • Western and Central Africa

  • 2022

  • US$ 470.00 million

  • B

  • December 22, 2023

  • September 30, 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 235.00
IDA Grant 235.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 470.00
IBRD + IDA Commitment 470.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 470.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 20, 2024 IDA-D8910 Loan Disb 514,653.16
Jul 16, 2021 IDA-69660 Loan Commitment 130,000,000.00
Jul 16, 2021 IDA-69670 Loan Commitment 60,000,000.00
Jul 16, 2021 IDA-D8900 Loan Commitment 45,000,000.00
Jul 16, 2021 IDA-D8910 Loan Commitment 130,000,000.00
Jul 16, 2021 IDA-D8920 Loan Commitment 60,000,000.00
Jun 30, 2022 IDA-D8910 Loan Disb 12,950,852.00
Jan 20, 2023 IDA-D8920 Loan Disb 314,271.03
Oct 19, 2022 IDA-D8920 Loan Disb 119,375.58
Dec 19, 2022 IDA-D8920 Loan Disb 128,058.13
Aug 18, 2022 IDA-D8920 Loan Disb 61,627.22
May 9, 2022 IDA-D8920 Loan Disb 4,532,798.00
Jun 17, 2022 IDA-D8920 Loan Disb 21,168.56
May 22, 2023 IDA-D8920 Loan Disb 61,216.01
Jul 19, 2023 IDA-D8920 Loan Disb 124,406.03
Sep 14, 2023 IDA-D8920 Loan Disb 60,035.61
Sep 21, 2023 IDA-D8910 Loan Disb 7,719,078.00
Aug 29, 2023 IDA-D8910 Loan Disb 8,683,574.00
Sep 20, 2023 IDA-D8910 Loan Disb 437,458.12
Sep 20, 2023 IDA-D8910 Loan Disb 1,406,306.50
Mar 21, 2023 IDA-D8920 Loan Disb 132,305.62
May 24, 2024 IDA-D8910 Loan Disb 240,134.17
Jan 19, 2024 IDA-D8920 Loan Disb 62,438.27
Feb 1, 2024 IDA-D8910 Loan Disb 191,602.48
Apr 25, 2024 IDA-D8910 Loan Disb 576,077.80
Jul 23, 2024 IDA-D8910 Loan Disb 126,985.36
Apr 18, 2024 IDA-D8920 Loan Disb 50,452.62
Apr 19, 2024 IDA-D8910 Loan Disb 189,124.61
Jan 11, 2024 IDA-D8910 Loan Disb 245,490.55
Nov 30, 2023 IDA-D8910 Loan Disb 234,002.55
Nov 22, 2023 IDA-D8920 Loan Disb 117,904.78
Jul 18, 2024 IDA-D8920 Loan Disb 53,142.01
Apr 2, 2024 IDA-D8920 Loan Disb 87,552.99
Jun 20, 2024 IDA-D8920 Loan Disb 57,454.92
Jun 11, 2024 IDA-D8910 Loan Disb 565,493.50
Feb 23, 2024 IDA-69660 Loan Disb 1,123.78
May 17, 2024 IDA-69660 Int Charges 10,015.73
May 17, 2024 IDA-69660 Int Charges 10,015.73
May 29, 2024 IDA-69650 Int Charges 19,707.29
May 29, 2024 IDA-69650 Int Charges 19,707.29
Apr 30, 2024 IDA-69650 Int Charges 19,443.33
Apr 30, 2024 IDA-69650 Int Charges 19,443.33
Apr 30, 2024 IDA-69650 Int Charges 64.37
Apr 30, 2024 IDA-69650 Int Charges 64.37
Feb 1, 2024 IDA-69660 Loan Disb 211.12
Jul 18, 2024 IDA-69660 Loan Disb 1,166,707.60
Jun 3, 2024 IDA-69650 Loan Disb 624,175.56
Jun 25, 2024 IDA-69650 Loan Disb 80,424.56
Jun 2, 2022 IDA-69660 Loan Disb 929,635.70
May 31, 2022 IDA-69650 Loan Disb 4,076,677.20
Nov 15, 2022 IDA-69660 Int Charges 5,407.93
Nov 15, 2022 IDA-69660 Int Charges 5,407.93
Aug 17, 2022 IDA-69660 Loan Disb 1,244,567.60
Aug 17, 2022 IDA-69650 Loan Disb 91,562.74
Jun 28, 2022 IDA-69650 Loan Disb 211,051.30
Apr 18, 2023 IDA-69650 Loan Disb 54,903.60
May 15, 2023 IDA-69650 Int Charges 18,607.19
May 15, 2023 IDA-69650 Int Charges 18,607.19
Jan 13, 2023 IDA-69650 Loan Disb 285,057.90
Apr 3, 2023 IDA-69650 Loan Disb 39,593.21
Dec 6, 2022 IDA-69650 Loan Disb 64,298.84
Sep 21, 2022 IDA-69650 Loan Disb 163,494.69
Nov 9, 2022 IDA-69650 Loan Disb 53,786.53
Nov 15, 2022 IDA-69650 Int Charges 14,405.50
Nov 15, 2022 IDA-69650 Int Charges 14,405.50
Sep 8, 2023 IDA-69660 Loan Disb 300,260.38
May 26, 2023 IDA-69650 Loan Disb 70,000.98
May 22, 2023 IDA-69660 Int Charges 8,491.11
May 22, 2023 IDA-69660 Int Charges 8,491.11
Feb 23, 2023 IDA-69650 Loan Disb 21,150.08
Nov 30, 2023 IDA-69660 Loan Disb 13,207.60
Jan 11, 2024 IDA-69660 Loan Disb 126,960.03
Nov 17, 2023 IDA-69660 Int Charges 8,951.20
Nov 17, 2023 IDA-69660 Int Charges 8,951.20
May 15, 2023 IDA-69650 Int Charges 208.96
May 15, 2023 IDA-69650 Int Charges 208.96
Jul 3, 2023 IDA-69650 Loan Disb 32,217.47
Jul 16, 2021 IDA-69650 Loan Commitment 45,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2025-03-09
Monitoring and Evaluation Satisfactory 2025-03-09
Procurement Moderately Satisfactory 2025-03-09
Progress towards achievement of PDO Moderately Satisfactory 2025-03-09
Project Management Moderately Satisfactory 2025-03-09
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-03-09

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Travel time for containerized freight on the corridor from ship arrival at the Port of Lomé to final clearance in Niamey (regional indicator)Value36.0036.0027.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Population of beneficiary communities able to access a local market by motorized transport within 30 minutes (regional indicator)Value22.0022.0026.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Border crossing time by truck at Kantchari-Torodi border (Burkina Faso - Niger)Value48.0048.0018.00
    DateJuly 1, 2021November 29, 2023September 30, 2027
    Comment
  • Population of beneficiary communities able to access a local market by motorized transport within 30 minutes (Burkina Faso)Value46.0046.0053.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Border crossing time by truck at the Cinkanse border (Togo - Burkina Faso)Value78.0078.0036.00
    DateJuly 1, 2021November 29, 2023September 30, 2027
    Comment
  • Population of beneficiary communities able to access a local market by motorized transport within 30 minutes (Niger)Value14.0014.0018.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Travel time for containerized freight on the corridor from ship arrival at the Port of Lomé to final clearance in Ouagadougou (regional indicator)Value18.0018.0014.00
    DateJuly 1, 2021November 29, 2023September 30, 2027
    Comment
  • Population of beneficiary communities able to access a local market by motorized transport within 30 minutes (Togo)Value15.0015.0019.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Reliability of travel time for containerized freight on the corridor from ship arrival at the Port of Lomé to final clearance in Niamey (regional indicator)Value36.0036.0022.00
    DateJuly 1, 2021November 29, 2023September 30, 2027
    Comment
  • Reliability of travel time for containerized freight on the corridor from ship arrival at the Port of Lomé to final clearance in Ouagadougou (regional indicator)Value15.0015.0010.00
    DateJuly 1, 2021November 29, 2023September 30, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of Aouda-Kara section rehabilitated (Togo)Value0.000.00110.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Implementation of qualifying training for transport operators (Niger)ValueNoNoYes
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Length of corridor access roads rehabilitated or improved (regional indicator)Value0.000.00531.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Registered grievances responded and/or resolved within the stipulated service standards for response timeValue0.000.0030.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Fenced parking lots built along the corridor (regional indicator)Value0.000.006.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Establishment of mechanisms to guarantee the quality of freight transport vehicles (Niger)ValueNoNoYes
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Length of rehabilitated/improved access roads linking areas of high agricultural production to RN1 (Togo)Value0.000.00120.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Share of the Lomé-Ouagadougou-Niamey road corridor equipped with a system to receive real-time traffic, incident and weather informationValue0.000.00100.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Optimization of cross-border facilities, processes and procedures at the Kantchari/Makalondi border (Burkina Faso, Niger)ValueNoNoYes
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Length of RN17, RR32 and RR06 paved and other roads improved (Burkina Faso)Value0.000.00231.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Decrease in annual fatalities from road accidents on the Lome-Ougadougou-Niamey corridorValue0.000.0015.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Percentage of the certified professionals in commercial trucking activities and the logistics industry that will be womenValue0.000.0015.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Length of access roads rehabilitated (Niger)Value0.000.00150.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Percentage of the certified professionals employed as a result of certification that will be womenValue7.007.0015.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment
  • Length of feeder road rehabilitated to climate resilient standards (regional indicator)Value0.000.00531.00
    DateApril 15, 2021November 29, 2023September 30, 2027
    Comment