Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 500.00 |
P168582
Active
Jean Lobet , Laila Ahmed, Laurent Gonnet
Arab Republic of Egypt
April 1, 2019
(as of board presentation)
March 20, 2020
N/A
US$ 500.00 million
Social Housing and Mortgage Finance Fund
2020
US$ 500.00 million
N/A
October 5, 2020
December 31, 2025
TBD
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 500.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 500.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 500.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 500.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1.1 Number of targeted households accessing ownership and rental housing units with support from the Program | Value | 0.00 | 243450.00 | 1052400.00 |
Date | April 1, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
2. Percentage of Program beneficiaries in bottom 20% of the income distribution | Value | 0.00 | 34.20 | 50.00 |
Date | April 1, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
3. Percentage of income spent on housing costs by Program beneficiaries | Value | 0.00 | 35.00 | 30.00 |
Date | April 1, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
4. Establishment of a housing M&E system functioning and informing the Multi-Year Plan and Annual Targets | Value | No | Yes | Yes |
Date | April 1, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
1.2 female-headed households as a percentage of benefeciaries | Value | 0.00 | 19.80 | 24.00 |
Date | April 1, 2015 | April 29, 2018 | June 30, 2020 | |
Comment |
5. Development, adoption and implementation of an alternative system that progressively phases out the interest rate subsidy | Value | No | No | Yes |
Date | May 31, 2019 | May 31, 2019 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
3.1. Number of households receiving demand side home ownership subsidies for new units under the AMP | Value | 0.00 | 241500.00 | 950000.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
4.1. Percent of demand-side subsidies supporting the purchase or rental of housing units within a 60 minute travel time to an employment center | Value | 0.00 | 100.00 | 50.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
5.1. Number of demand-side subsidies supporting the purchase or rental of housing units developed by the private sector | Value | 0.00 | 1950.00 | 250000.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
1.1. Completed executive by-laws, organizational structure, financing model, fiduciary arrangements, operating systems for the SHMFF | Value | No | Yes | Yes |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
2.1. Mechanism to monitor occupancy of housing post-subsidy established and functioning as per DLI definition | Value | No | Yes | Yes |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
1.2. SHMFF fully staffed as per organizational plan | Value | No | Yes | Yes |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
2.2. Percentage of rental housing units occupied by targeted beneficiaries at least 1 year after lease | Value | 0.00 | 100.00 | 75.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
5.2. PPP guidelines publicly disseminated | Value | No | Yes | Yes |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
4.2. Percent of demand-side subsidies supporting the purchase or rental of housing units within a 45 minute travel time to an employment center | Value | 0.00 | 100.00 | 50.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
3.2. Number of households participating in rental subsidy programs | Value | 0.00 | 1950.00 | 102400.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
2.3. Percentage of ownership housing units occupied by low-income households after at least 1 year of receiving subsidies under theAMP | Value | 0.00 | 100.00 | 85.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
5.3. Percentage of demand side subsidy supporting the purchase or rental of housing units developed by private sector | Value | 0.00 | 0.76 | 43.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
4.3. Percent of demand-side subsidies supporting the purchase or rental of housing units within a 30 minute travel time to an employment center | Value | 0.00 | 100.00 | 15.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
1.3. Internal audit function providing assurance services for the ownership and rental programs affiliated with the SHMFF established and operating | Value | No | Yes | Yes |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
3.3. Number of previously vacant units occupied 1 year after inclusion into the Program | Value | 0.00 | 85057.00 | 30000.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
1.4. Adequate staffing of social officers as per organizational plan | Value | No | Yes | Yes |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
4.4. Percentage of land made available for SHMFF developments that complies with location and service criteria stated in Law | Value | 0.00 | 100.00 | 100.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
2.4. Establish a unified social programs and beneficiary databases | Value | No | Yes | Yes |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
1.5. Number of capacity building and training workshops conducted for the hired social workers at the Central and Governorate level. | Value | 0.00 | 27.00 | 27.00 |
Date | August 10, 2015 | September 28, 2018 | December 31, 2024 | |
Comment |
2.5. Establishment of a functioning accountability and transparency mechanism in SHMFF as per DLI definition | Value | No | Yes | Yes |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
2.6. Average time required to resolve complaints in AMP | Value | 60.00 | 30.00 | 20.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
2.7. Percentage of resolved complaints received by SHMFFF and Governorate housing offices | Value | 0.00 | 90.00 | 90.00 |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
2.8. Annual published reports on complaints and how issues were resolved, including resolution rates | Value | No | Yes | Yes |
Date | August 10, 2015 | May 31, 2019 | December 31, 2024 | |
Comment |
3.1.1. Female- headed households as percentage of beneficiaries | Value | 0.00 | 20.00 | 0.00 |
Date | ||||
Comment |
3.2.1. Female-headed households as percentage of beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |