Financier | Commitments |
---|---|
IDA Grant | 50.00 |
P168608
Active
Francis Nkoka
Sierra Leone
July 9, 2019
(as of board presentation)
June 25, 2021
September 14, 2021
US$ 56.73 million
Freetown City Council,Bo City Council,Fiscal Decentralization Division in Ministry of Finance,Western Area Rural District Council,National Disaster Management Agency
2021
US$ 50.00 million
N/A
High
July 31, 2026
Yes
BANK APPROVED
January 31, 2024
Financier | Commitments |
---|---|
IDA Grant | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 56.73 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 14, 2021 | IDA-D8420 | Loan Disb | 1,865,000.00 |
Dec 3, 2021 | IDA-D8420 | Loan Disb | 3,612,907.20 |
Aug 2, 2024 | IDA-D8420 | Loan Disb | 178,663.80 |
Mar 23, 2023 | IDA-D8420 | Loan Disb | 2,568,630.00 |
Nov 8, 2023 | IDA-D8420 | Loan Disb | 2,508,152.80 |
Jun 20, 2024 | IDA-D8420 | Loan Disb | 124,424.00 |
Jun 25, 2021 | IDA-D8420 | Loan Commitment | 50,000,000.00 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2025-02-17 |
Financial Management | Moderately Satisfactory | 2025-02-17 |
Monitoring and Evaluation | Moderately Satisfactory | 2025-02-17 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2025-02-17 |
Procurement | Moderately Satisfactory | 2025-02-17 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2025-02-17 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Districts with functional decentralized emergency response services | Value | 0.00 | 0.00 | 2.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Increased municipal own source revenue (aggregated for all city councils) | Value | 0.00 | 28.00 | 15.00 |
Date | March 1, 2021 | November 17, 2023 | July 31, 2026 | |
Comment |
People provided with increased access to resilient municipal infrastructure and services | Value | 0.00 | 0.00 | 1700000.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
People provided with access to enhanced hydromet early warning systems | Value | 0.00 | 0.00 | 600000.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Cities with new planning frameworks adopted | Value | 0.00 | 0.00 | 4.00 |
Date | March 1, 2021 | October 27, 2023 | August 31, 2026 | |
Comment |
People provided with increased access to resilient municipal infrastructure and services - Female | Value | 0.00 | 0.00 | 850000.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Registered grievances resolved within the agreed timeframe | Value | 0.00 | 33.00 | 80.00 |
Date | February 1, 2021 | November 17, 2023 | July 31, 2026 | |
Comment |
Unplanned settlements upgraded | Value | 0.00 | 0.00 | 32.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Districts with Disaster Contingency Plans adopted | Value | 0.00 | 0.00 | 2.00 |
Date | February 1, 2021 | November 17, 2023 | July 31, 2026 | |
Comment |
People with access to new sanitation and/or water facilities constructed | Value | 0.00 | 0.00 | 20000.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Emergency Operations Centers (national and regional) established and equipped | Value | 0.00 | 0.00 | 2.00 |
Date | February 1, 2021 | November 17, 2023 | July 31, 2026 | |
Comment |
Staff trained in urban planning methods | Value | 0.00 | 56.00 | 100.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Beneficiary feedback surveys conducted at mid-term and closing | Value | No | No | Yes |
Date | October 1, 2020 | November 17, 2023 | December 31, 2025 | |
Comment |
Proportion of safely disposed municipal solid waste in Western Area | Value | 0.00 | 0.00 | 45.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Flood forecasting and alert systems established | Value | No | No | Yes |
Date | October 1, 2020 | November 17, 2023 | December 31, 2025 | |
Comment |
City councils staff trained in urban planning methods - Female | Value | 0.00 | 14.00 | 50.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Area of forested land restored and/or under improved management | Value | 0.00 | 443.00 | 1000.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Staff trained in DRM | Value | 0.00 | 262.00 | 300.00 |
Date | February 1, 2021 | November 17, 2023 | July 31, 2026 | |
Comment |
City councils with ICT system for property tax upgraded/established and operational | Value | 0.00 | 0.00 | 5.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Traders using upgraded markets | Value | 0.00 | 0.00 | 7000.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
City councils using a citizen engagement platform | Value | 0.00 | 0.00 | 5.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Traders using upgraded markets - Female | Value | 0.00 | 0.00 | 6000.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Average citizen satisfaction rate with at least 1 subproject provided under Component 2 | Value | 0.00 | 0.00 | 80.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Average citizen satisfaction rate with at least 1 subproject provided under Component 2 - Female | Value | 0.00 | 0.00 | 80.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Green house gas (GHG) reduction | Value | 0.00 | 33867.00 | 1815665.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Formal jobs in SWM created by the project, of which female | Value | 0.00 | 0.00 | 40.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |
Women completing the SWM livelihood support program under the project | Value | 0.00 | 64.00 | 800.00 |
Date | March 1, 2021 | November 17, 2023 | August 31, 2026 | |
Comment |