Financier | Commitments |
---|---|
Asian Infrastructure Investment Bank | 105.00 |
International Bank for Reconstruction and Development | 105.00 |
Borrower/Recipient | 90.00 |
P168633
Active
Zhiyu Chen , Poonam Ahluwalia Khanijo
India
November 6, 2018
(as of board presentation)
March 9, 2021
March 8, 2022
US$ 300.00 million
Local Self Government Department, Government of Kerala
2021
US$ 210.00 million
A
February 25, 2024
June 30, 2027
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Asian Infrastructure Investment Bank | 105.00 |
International Bank for Reconstruction and Development | 105.00 |
Borrower/Recipient | 90.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 105.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 105.00 |
Lending Instrument | |
---|---|
Grant Amount | 105.00 |
Total Project Cost** | 300.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 1, 2023 | IBRD-92080 | Int Charges | 36,867.60 |
Jan 1, 2023 | IBRD-92080 | Int Charges | 129,857.88 |
Jan 1, 2023 | IBRD-92080 | Int Charges | 374.99 |
Jan 1, 2023 | IBRD-92080 | Int Charges | 11.81 |
Jun 30, 2022 | IBRD-92080 | Loan Disb | 1,672,438.00 |
Jan 1, 2024 | IBRD-92080 | Int Charges | 126,329.12 |
Jan 1, 2024 | IBRD-92080 | Int Charges | 3,176.00 |
Jan 1, 2024 | IBRD-92080 | Int Charges | 95.89 |
Jul 1, 2023 | IBRD-92080 | Int Charges | 52,016.53 |
Jul 1, 2023 | IBRD-92080 | Int Charges | 127,644.74 |
Jul 1, 2023 | IBRD-92080 | Int Charges | 3,060.92 |
Jun 26, 2023 | IBRD-92080 | Loan Disb | 2,800,000.00 |
Jul 1, 2024 | IBRD-92080 | Int Charges | 153,803.77 |
Jul 1, 2024 | IBRD-92080 | Int Charges | 1,027.99 |
Jul 1, 2024 | IBRD-92080 | Int Charges | 124,396.63 |
Jun 20, 2024 | IBRD-92080 | Loan Disb | 2,900,000.00 |
Mar 9, 2021 | IBRD-92080 | Loan Commitment | 105,000,000.00 |
Jan 1, 2024 | IBRD-92080 | Int Charges | 152,254.80 |
Jul 1, 2022 | IBRD-92080 | Int Charges | 853.82 |
Jul 1, 2022 | IBRD-92080 | Int Charges | 78,899.99 |
Mar 8, 2022 | IBRD-92080 | Fee Charges | 262,500.00 |
Mar 8, 2022 | IBRD-92080 | Loan Disb | 262,500.00 |
Jun 29, 2022 | IBRD-92080 | Loan Disb | 25,667.03 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-11-06 |
Project Management | Moderately Unsatisfactory | 2024-11-06 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-11-06 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2024-11-06 |
Financial Management | Moderately Satisfactory | 2024-11-06 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-11-06 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of ULBs that accessed incentive grants for improving SWM services | Value | 0.00 | 0.00 | 60.00 |
Date | September 30, 2020 | November 10, 2023 | February 27, 2026 | |
Comment |
Number of people with access to improved solid waste management services | Value | 0.00 | 0.00 | 6000.00 |
Date | September 30, 2020 | November 10, 2023 | December 30, 2026 | |
Comment |
Solid waste disposed safely in engineered landfills, as per National SWM Rules 2016 | Value | 0.00 | 0.00 | 146000.00 |
Date | September 30, 2020 | November 10, 2023 | December 30, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of dumpsites closed | Value | 0.00 | 0.00 | 3.00 |
Date | September 30, 2020 | November 10, 2023 | February 27, 2026 | |
Comment |
Number of cities that have issued SWM bi-laws | Value | 0.00 | 0.00 | 60.00 |
Date | September 30, 2020 | November 10, 2023 | February 27, 2026 | |
Comment |
Household coverage of door to door segregated municipal waste collection services | Value | 0.00 | 0.00 | 70.00 |
Date | September 30, 2020 | November 10, 2023 | February 27, 2026 | |
Comment |
Number of landfills constructed and operational | Value | 0.00 | 0.00 | 3.00 |
Date | September 30, 2020 | November 10, 2023 | February 27, 2026 | |
Comment |
Number of participants in SWM training sessions | Value | 0.00 | 92.00 | 16800.00 |
Date | September 30, 2020 | November 10, 2023 | February 27, 2026 | |
Comment |
Share of plastic waste recycled at the local level | Value | 10.00 | 0.00 | 50.00 |
Date | September 30, 2020 | November 10, 2023 | December 30, 2026 | |
Comment |
Number of inter-municipal coordination arrangements in place for regional disposal systems | Value | 0.00 | 0.00 | 3.00 |
Date | September 30, 2020 | November 10, 2023 | February 27, 2026 | |
Comment |
Number of cities with city SWM plans | Value | 0.00 | 0.00 | 60.00 |
Date | September 30, 2020 | November 10, 2023 | February 27, 2026 | |
Comment |
Number of ULBs with improved human resource capacity for SWM | Value | 0.00 | 93.00 | 60.00 |
Date | September 30, 2020 | November 10, 2023 | February 27, 2026 | |
Comment |
Number of ULBs that adopted cost recovery system for SWM | Value | 0.00 | 0.00 | 60.00 |
Date | September 30, 2020 | November 10, 2023 | February 27, 2026 | |
Comment |
Number of women’s groups implementing SWM services financed by the project | Value | 0.00 | 0.00 | 120.00 |
Date | September 30, 2020 | November 10, 2023 | December 30, 2026 | |
Comment |
Share of the complaints registered resolved within 30 days | Value | 0.00 | 100.00 | 80.00 |
Date | September 30, 2020 | November 10, 2023 | December 30, 2026 | |
Comment |
Number of ULBs in which beneficiary satisfaction survey is conducted | Value | 0.00 | 0.00 | 60.00 |
Date | September 30, 2020 | November 10, 2023 | December 30, 2026 | |
Comment |