Financier | Commitments |
---|---|
Extractives Global Programmatic Support | 0.35 |
P168666
Closed
Silvana Tordo , Fabienne Mroczka
Republic of Chad
October 22, 2018
(as of board presentation)
November 6, 2019
November 25, 2019
US$ 0.35 million
Ministere des Finances
2020
US$ 0.35 million
N/A
Low
April 30, 2021
TBD
BANK APPROVED
October 16, 2023
Financier | Commitments |
---|---|
Extractives Global Programmatic Support | 0.35 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 0.35 |
Total Project Cost** | 0.35 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Moderately Satisfactory | 2022-03-20 |
Progress towards achievement of PDO | Moderately Satisfactory | 2022-03-20 |
Overall | Satisfactory | 2022-03-20 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
The NTPS is able to measure its communication effectiveness | Value | No | Yes | Yes |
Date | July 31, 2019 | April 30, 2021 | April 30, 2021 | |
Comment |
The NTPS' Activity Implementation Ratio substantially improves | Value | Administrative cost to total cost = 70%Budget exe | Administrative cost to total cost = 30%Budget exe | Administrative cost to total cost = 97.7%Budget e |
Date | July 31, 2019 | April 30, 2021 | April 30, 2021 | |
Comment |
Institutional solutions for the mainstreaming of EITI reporting are identified | Value | No | Yes | Yes |
Date | July 31, 2019 | April 30, 2021 | April 30, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Internal administrative procedures are adopted | Value | No | Yes | Yes |
Date | July 31, 2019 | April 30, 2021 | March 31, 2021 | |
Comment |
Stakeholders mapping is finalized | Value | No | Yes | Yes |
Date | July 31, 2019 | April 30, 2021 | March 31, 2021 | |
Comment |