Financier | Commitments |
---|---|
IDA Credit | 50.00 |
P168847
Active
Christophe Grosjean , Mohamed Hammady
Islamic Republic of Mauritania
March 3, 2019
(as of board presentation)
November 17, 2022
March 27, 2023
US$ 50.00 million
Ministère de l'Agriculture
2023
US$ 50.00 million
N/A
Substantial
June 30, 2028
Yes
BANK APPROVED
November 14, 2024
Financier | Commitments |
---|---|
IDA Credit | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2024 | IDA-72250 | Int Charges | 6,115.12 |
Mar 15, 2024 | IDA-72250 | Int Charges | 35,041.93 |
Jun 27, 2023 | IDA-72250 | Loan Disb | 541,567.70 |
Nov 17, 2022 | IDA-72250 | Loan Commitment | 50,000,000.00 |
Apr 30, 2024 | IDA-72250 | Loan Disb | 59,778.42 |
Mar 15, 2024 | IDA-72250 | Int Charges | 33,905.16 |
Mar 15, 2024 | IDA-72250 | Int Charges | 33,905.16 |
Aug 22, 2023 | IDA-72250 | Loan Disb | 133,223.12 |
Jun 30, 2023 | IDA-72250 | Loan Disb | 145,548.30 |
Nov 17, 2023 | IDA-72250 | Loan Disb | 104,505.07 |
Oct 30, 2023 | IDA-72250 | Loan Disb | 143,100.20 |
Dec 15, 2023 | IDA-72250 | Loan Disb | 91,229.58 |
Apr 3, 2024 | IDA-72250 | Loan Disb | 124,504.65 |
Sep 15, 2023 | IDA-72250 | Int Charges | 10,401.23 |
Jun 20, 2023 | IDA-72250 | Loan Disb | 274,042.97 |
Sep 15, 2023 | IDA-72250 | Int Charges | 15,798.23 |
Sep 15, 2023 | IDA-72250 | Int Charges | 15,798.23 |
Sep 21, 2023 | IDA-72250 | Loan Disb | 286,436.84 |
Jun 14, 2023 | IDA-72250 | Loan Disb | 400,000.00 |
Jul 26, 2023 | IDA-72250 | Loan Disb | 1,400,000.00 |
Aug 17, 2023 | IDA-72250 | Loan Disb | 257,732.62 |
Jul 21, 2023 | IDA-72250 | Loan Disb | 49,156.49 |
Mar 27, 2023 | IDA-72250 | Loan Disb | 1,407,582.60 |
Jun 28, 2024 | IDA-72250 | Loan Disb | 126,058.16 |
Mar 6, 2024 | IDA-72250 | Loan Disb | 158,375.42 |
Jun 20, 2024 | IDA-72250 | Loan Disb | 175,511.81 |
Jun 20, 2024 | IDA-72250 | Loan Disb | 1,000,000.00 |
Jul 30, 2024 | IDA-72250 | Loan Disb | 420,256.53 |
Aug 26, 2024 | IDA-72250 | Loan Disb | 157,897.61 |
Jan 31, 2024 | IDA-72250 | Loan Disb | 88,131.82 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2024-12-13 |
Financial Management | Satisfactory | 2024-12-13 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-13 |
Monitoring and Evaluation | Satisfactory | 2024-12-13 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-13 |
Procurement | Moderately Satisfactory | 2024-12-13 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Land area under sustainable landscape management practices | Value | 0.00 | 0.00 | 5000.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Farmers reached with agricultural assets or services | Value | 0.00 | 0.00 | 36000.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Farmers reached with agricultural assets or services - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Increase in productivity of key targeted crops in irrigated areas (rice) | Value | 4.50 | 4.50 | 6.50 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Increase in productivity of key targeted crops in rainfed areas (sorghum) | Value | 0.50 | 0.50 | 1.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 0.00 | 72000.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Male | Value | 0.00 | 0.00 | 43200.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Female | Value | 0.00 | 0.00 | 28800.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Physical infrastructures rehabilitated/upgraded | Value | 0.00 | 0.00 | 120.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Appropriate legal and institutional framework for implementation and management of the ZOCA program established | Value | No | No | Yes |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Grievances responded and/or resolved within the stipulated service standards for response times | Value | 0.00 | 0.00 | 90.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Increase in cultivated area in project area as a result of project investments | Value | 0.00 | 0.00 | 2500.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Land and water rights inventories prepared and validated with local communities in ZOCA areas | Value | 0.00 | 0.00 | 100.00 |
Date | March 30, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Share of target beneficiaries with rating “Satisfied” or above on process and impact of project interventions | Value | 0.00 | 0.00 | 80.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Farmers adopting improved agricultural technology | Value | 0.00 | 0.00 | 6000.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Land area under project having a documented land-based (ententes foncières) open for investment | Value | 0.00 | 0.00 | 2500.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
PPPs registered under the ZOCA program | Value | 0.00 | 0.00 | 6.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Farmers adopting improved agricultural technology - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Farmers adopting improved agricultural technology - male | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Functional income generating sub-projects one year after establishment | Value | 0.00 | 0.00 | 60.00 |
Date | March 31, 2023 | October 2, 2023 | March 29, 2024 | |
Comment |
Youth < 30 years | Value | 0.00 | 0.00 | 65.00 |
Date | March 31, 2023 | October 2, 2023 | March 29, 2024 | |
Comment |
Value of new private agribusiness investments registered in the ZOCA program | Value | 0.00 | 0.00 | 20000000.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Women | Value | 0.00 | 0.00 | 40.00 |
Date | March 31, 2023 | October 2, 2023 | March 29, 2024 | |
Comment |
Total volume marketed for the smallholders and SMAES through ZOCAs | Value | 0.00 | 0.00 | 4500000.00 |
Date | January 30, 2023 | October 2, 2023 | April 30, 2028 | |
Comment |
Disadvantaged groups | Value | 0.00 | 0.00 | 5.00 |
Date | March 31, 2023 | October 2, 2023 | March 29, 2024 | |
Comment |
Annual real income per beneficiary derived from IGAs financed by the project | Value | 0.00 | 0.00 | 1000.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Women reaching this income among beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
MoA staff trained in planning and implementation of landscape restoration activities | Value | 0.00 | 0.00 | 90.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |
Area provided with new/improved irrigation or climate-resilient features | Value | 0.00 | 0.00 | 1500.00 |
Date | March 31, 2023 | October 2, 2023 | June 30, 2028 | |
Comment |