Sava and Drina Rivers Corridors Integrated Development Program

Abstract*

This project (Phase I of the SDIP MPA Program) will focus on four pillars of activities: 1) integrated management and development of the Sava River Corridor; 2) integrated management and development of the Drina River Corridor; 3) Project preparation and management; and 4) Enabling regional cooperation. Phase I activities have been identified and prepared through ongoing Bank support in the region as well as other initiatives financed by national...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Objective of the Project (Phase I of the Program) is to improve flood protection and enhance transboundary water cooperation in the Sava and Drina Rivers Corridors.

Key Details

Project Details

  • P168862

  • Active

  • Martin Albrecht , Andrew Losos, IGOR PALANDZIC

  • Republic of Serbia,Bosnia and Herzegovina

  • Western Balkans

  • March 22, 2019

  • (as of board presentation)

    August 6, 2020

  • January 26, 2021

  • US$ 151.50 million

  • Republic of Serbia Ministry of Construction, Transport and Infrastructure,Republika Srpska Ministry of Agriculture, Forestry and Water,International Sava River Basin Commission,Montenegro Ministry of Agriculture and Rural Development,FBiH Ministry of Agriculture, Water Management and Forestry,Br?ko District,Republic of Serbia Ministry of Agriculture, Forestry and Water Management

  • Europe and Central Asia

  • 2021

  • US$ 133.90 million

  • N/A

  • June 24, 2024

  • November 30, 2027

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 133.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 133.90
IDA Commitment N/A
IBRD + IDA Commitment 133.90
Lending Instrument
Grant Amount N/A
Total Project Cost** 151.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 6, 2020 IBRD-91290 Loan Commitment 32,600,000.00
Aug 6, 2020 IBRD-91300 Loan Commitment 16,300,000.00
Jun 15, 2022 IBRD-91280 Int Charges 1,324.87
Nov 15, 2021 IBRD-91290 Int Charges 64,501.48
Nov 15, 2021 IBRD-91290 Int Charges 318.78
Nov 15, 2022 IBRD-91290 Int Charges 34,018.70
Dec 15, 2021 IBRD-91280 Int Charges 92,525.48
Dec 15, 2021 IBRD-91280 Int Charges 77.97
Dec 23, 2022 IBRD-91290 Loan Disb 661,377.20
Feb 15, 2022 IBRD-91300 Int Charges 20,680.04
Feb 15, 2022 IBRD-91300 Int Charges 1,620.84
Aug 15, 2023 IBRD-91300 Int Charges 19,446.84
Aug 15, 2023 IBRD-91300 Int Charges 14,910.46
Feb 15, 2023 IBRD-91300 Int Charges 19,410.25
Feb 15, 2023 IBRD-91300 Int Charges 6,151.05
May 15, 2023 IBRD-91290 Int Charges 34,302.60
May 15, 2023 IBRD-91290 Int Charges 9,802.44
Dec 15, 2022 IBRD-91280 Int Charges 90,561.67
Dec 15, 2022 IBRD-91280 Int Charges 41,848.44
Oct 6, 2022 IBRD-91300 Loan Disb 114,739.66
Jan 12, 2024 IBRD-91290 Loan Disb -3,829,168.50
Nov 15, 2023 IBRD-91290 Int Charges 34,140.91
Nov 15, 2023 IBRD-91290 Int Charges 24,309.72
Dec 15, 2023 IBRD-91280 Int Charges 92,810.68
Dec 15, 2023 IBRD-91280 Int Charges 264,788.84
Dec 15, 2023 IBRD-91280 Loan Repay 652,293.30
Jun 15, 2023 IBRD-91280 Int Charges 91,910.59
Jun 15, 2023 IBRD-91280 Int Charges 174,916.64
Jun 15, 2023 IBRD-91280 Loan Disb 542,100.00
Jul 18, 2023 IBRD-91290 Loan Disb 441,560.66
Aug 6, 2024 IBRD-91290 Loan Disb -4,917,720.00
Jul 29, 2024 IBRD-91290 Loan Disb 1,796,697.40
Aug 15, 2024 IBRD-91300 Int Charges 19,076.70
Aug 15, 2024 IBRD-91300 Int Charges 29,174.00
Oct 13, 2023 IBRD-91290 Loan Disb 674,485.25
Dec 27, 2023 IBRD-91290 Loan Disb 2,035,194.20
Jun 15, 2024 IBRD-91280 Int Charges 90,293.38
Jun 15, 2024 IBRD-91280 Int Charges 252,677.22
Jun 7, 2024 IBRD-91300 Loan Disb 455,935.84
Jun 15, 2024 IBRD-91280 Loan Repay 636,177.75
May 15, 2024 IBRD-91290 Int Charges 3,012.00
May 15, 2024 IBRD-91290 Int Charges 156.90
Feb 15, 2024 IBRD-91300 Int Charges 19,398.21
Jun 18, 2024 IBRD-91290 Loan Disb 2,650,151.50
Feb 15, 2024 IBRD-91300 Int Charges 17,859.72
May 15, 2024 IBRD-91290 Int Charges 30,642.58
May 15, 2024 IBRD-91290 Int Charges 20,534.04
Mar 22, 2024 IBRD-91300 Loan Disb 112,488.97
Mar 28, 2024 IBRD-91290 Loan Disb 407,236.16
Aug 26, 2024 IBRD-91290 Loan Disb 1,961,075.50
Aug 26, 2024 IBRD-91290 Loan Disb 3,240,333.50
Jun 7, 2024 IBRD-91300 Loan Disb 480,669.56
Aug 15, 2024 IBRD-95670 Int Charges 49,486.99
Jun 11, 2024 IBRD-95670 Loan Disb 99,354.25
Jun 11, 2024 IBRD-95670 Fee Charges 99,354.25
Aug 15, 2024 IBRD-95670 Loan Disb -101,847.13
Jul 25, 2023 IBRD-95670 Loan Commitment 40,530,000.00
Aug 6, 2020 IBRD-91280 Loan Commitment 85,000,000.00
Jan 26, 2021 IBRD-91300 Loan Disb 45,517.50
Jan 26, 2021 IBRD-91300 Fee Charges 45,517.50
Nov 10, 2021 IBRD-91280 Loan Disb 11,549,500.00
Aug 15, 2021 IBRD-91300 Int Charges 6,027.77
Aug 15, 2021 IBRD-91300 Int Charges 13.96
Aug 15, 2021 IBRD-91300 Int Charges 1,302.25
Aug 15, 2021 IBRD-91300 Int Charges 21,242.46
Oct 21, 2021 IBRD-91290 Loan Disb -4,743,096.00
Sep 8, 2021 IBRD-91280 Loan Disb 231,041.90
Sep 8, 2021 IBRD-91280 Fee Charges 231,041.90
Oct 5, 2021 IBRD-91290 Loan Disb 4,637,800.00
Mar 31, 2021 IBRD-91300 Loan Disb 586,675.00
Jun 7, 2021 IBRD-91290 Loan Disb 91,173.75
Jun 7, 2021 IBRD-91290 Fee Charges 91,173.75
Aug 15, 2022 IBRD-91300 Int Charges 18,295.30
Aug 15, 2022 IBRD-91300 Int Charges 1,626.97
Jun 15, 2022 IBRD-91280 Int Charges 87,674.97
Jun 15, 2022 IBRD-91280 Int Charges 5,403.09
Jun 15, 2022 IBRD-91280 Int Charges 1,188.04
May 15, 2022 IBRD-91290 Int Charges 321.03
May 15, 2022 IBRD-91290 Int Charges 33,386.92
May 15, 2022 IBRD-91290 Int Charges 1,166.87
Nov 15, 2022 IBRD-91290 Int Charges 40,519.59
May 15, 2023 IBRD-91290 Int Charges 42,338.92
Oct 21, 2021 IBRD-91290 Loan Disb 4,743,096.00
May 15, 2022 IBRD-91290 Int Charges 5,390.16
May 15, 2022 IBRD-91290 Int Charges 40,426.19
Aug 15, 2024 IBRD-95670 Loan Disb 101,847.13
May 15, 2024 IBRD-91290 Int Charges 42,126.83
May 15, 2024 IBRD-91290 Int Charges 51,993.25
Nov 15, 2023 IBRD-91290 Int Charges 42,286.39
Jan 12, 2024 IBRD-91290 Loan Disb 3,829,168.50
Aug 6, 2024 IBRD-91290 Loan Disb 4,917,720.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2025-02-04
Financial Management Satisfactory 2025-02-04
Monitoring and Evaluation Moderately Satisfactory 2025-02-04
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-02-04
Procurement Moderately Satisfactory 2025-02-04
Project Management Moderately Satisfactory 2025-02-04

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • River basin management plan reflecting integrated measures updated and endorsed by countriesValueNoYesYes
    DateJanuary 31, 2020June 14, 2024July 30, 2026
    Comment
  • People protected from 1 in 100-year flood event in the Sava and Drina River Basins under the project (of which female)Value0.000.00270000.00
    DateJanuary 31, 2020June 14, 2024July 30, 2026
    Comment
  • Of which femaleValue0.000.000.00
    Date
    Comment
  • Area protected by flood risk mitigation measures under the projectValue0.000.00165000.00
    DateJanuary 31, 2020June 14, 2024July 30, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of embankments or dykes constructed or rehabilitatedValue0.001.5030.00
    DateJanuary 31, 2020June 14, 2024July 30, 2026
    Comment
  • Enhanced monitoring/ data sharing protocols and schedules developedValueNoNoYes
    DateJanuary 31, 2020June 14, 2024July 30, 2026
    Comment
  • Freight throughput at the Sava river port of Sremska Mitrovica in SerbiaValue234465.00234465.00300000.00
    DateMarch 2, 2020June 14, 2024January 30, 2026
    Comment
  • Flood monitoring and forecasting system upgraded in a participatory manner, publicly disclosed and adjusted based on citizen engagementValueNoNoYes
    DateJanuary 31, 2020June 27, 2024July 30, 2026
    Comment
  • Priority regional investments preparedValue0.000.005.00
    DateJanuary 31, 2020June 14, 2024July 30, 2026
    Comment
  • Percentage of grievances responded and resolved within an agreed time frameValue0.00100.0085.00
    DateJanuary 31, 2020June 27, 2024July 30, 2026
    Comment
  • Stakeholders consulted (of which female) and engaged during planning and preparation of project interventionsValue0.00200.001200.00
    DateJanuary 31, 2020June 14, 2024July 30, 2026
    Comment
  • Area protected by improved solid waste managementValue0.000.0031.50
    DateJuly 6, 2023June 14, 2024July 30, 2026
    Comment
  • of which femaleValue0.0098.00510.00
    DateSeptember 30, 2019June 14, 2024July 30, 2026
    Comment
  • Waterway improved through deminingValue0.000.0040.00
    DateJanuary 31, 2020June 14, 2024July 30, 2026
    Comment
  • Regional tourism master plan for the Sava and Drina Corridor that includes the establishment of a forum for women-headed SMEs is developed and endorsed..ValueNoNoYes
    DateJanuary 31, 2020June 14, 2024July 30, 2026
    Comment
  • Number of annual multi-national stakeholder workshops heldValue0.000.0012.00
    DateJanuary 1, 2020June 14, 2024January 30, 2026
    Comment