Financier | Commitments |
---|---|
IBRD Guarantee | 19.00 |
International Bank for Reconstruction and Development | 381.00 |
P169111
Active
Carmen Yee-Batista , Upneet Singh
India
September 28, 2018
(as of board presentation)
June 25, 2020
July 21, 2020
US$ 1118.95 million
National Mission for Clean Ganga, Ministry of Jal Shakti
2020
US$ 381.00 million
A
March 18, 2024
December 31, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IBRD Guarantee | 19.00 |
International Bank for Reconstruction and Development | 381.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 381.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 381.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 1118.95 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 25, 2020 | IBRD-91360 | Loan Commitment | 381,000,000.00 |
May 30, 2023 | IBRD-91360 | Loan Disb | 11,400,778.00 |
Jun 15, 2023 | IBRD-91360 | Int Charges | 395,107.22 |
Jun 15, 2023 | IBRD-91360 | Int Charges | 1,573,306.90 |
Jun 15, 2023 | IBRD-91360 | Int Charges | 373.03 |
Feb 17, 2023 | IBRD-91360 | Loan Disb | 8,515,009.00 |
Apr 25, 2023 | IBRD-91360 | Loan Disb | 18,606,966.00 |
Jun 15, 2024 | IBRD-91360 | Int Charges | 19,272.27 |
May 17, 2024 | IBRD-91360 | Loan Disb | 9,750,171.00 |
Jun 15, 2024 | IBRD-91360 | Int Charges | 4,262,925.00 |
Mar 29, 2024 | IBRD-91360 | Loan Disb | 12,666,619.00 |
Jul 26, 2024 | IBRD-91360 | Loan Disb | 14,056,255.00 |
Oct 2, 2023 | IBRD-91360 | Loan Disb | 22,170,026.00 |
Jan 16, 2024 | IBRD-91360 | Loan Disb | 13,060,339.00 |
Dec 15, 2023 | IBRD-91360 | Int Charges | 7,749.10 |
Dec 15, 2023 | IBRD-91360 | Int Charges | 3,108,394.50 |
Dec 15, 2023 | IBRD-91360 | Int Charges | 352,467.38 |
Jun 15, 2023 | IBRD-91360 | Int Charges | 39,301.01 |
Jun 15, 2024 | IBRD-91360 | Int Charges | 312,932.53 |
Jun 15, 2021 | IBRD-91360 | Int Charges | 50.00 |
Jun 15, 2021 | IBRD-91360 | Int Charges | 473,636.94 |
Jun 15, 2021 | IBRD-91360 | Int Charges | 4,574.66 |
Feb 22, 2021 | IBRD-91360 | Int Charges | 30.00 |
Dec 15, 2020 | IBRD-91360 | Int Charges | 262,191.25 |
Dec 15, 2020 | IBRD-91360 | Int Charges | 4,079.52 |
Jul 21, 2020 | IBRD-91360 | Loan Disb | 952,500.00 |
Jul 21, 2020 | IBRD-91360 | Fee Charges | 952,500.00 |
Dec 13, 2022 | IBRD-91360 | Loan Disb | 27,231,744.00 |
Dec 15, 2022 | IBRD-91360 | Int Charges | 448,062.80 |
Dec 15, 2022 | IBRD-91360 | Int Charges | 439,952.72 |
Dec 15, 2021 | IBRD-91360 | Int Charges | 476,360.90 |
Dec 15, 2021 | IBRD-91360 | Int Charges | 4,260.85 |
Jun 29, 2022 | IBRD-91360 | Loan Disb | 24,124,596.00 |
Jun 15, 2022 | IBRD-91360 | Int Charges | 473,757.84 |
Jun 15, 2022 | IBRD-91360 | Int Charges | 4,959.87 |
Dec 15, 2023 | IBRD-91360 | Int Charges | 206,156.89 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Moderately Unsatisfactory | 2024-09-28 |
Project Management | Satisfactory | 2024-09-28 |
Procurement | Moderately Satisfactory | 2024-09-28 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-09-28 |
Financial Management | Moderately Satisfactory | 2024-09-28 |
Monitoring and Evaluation | Satisfactory | 2024-09-28 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-09-28 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Adopted recommendations of the study on institutional framework for Ganga river basin management are implemented | Value | 0.00 | 80.00 | 80.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Amount of BOD pollution load reduced due to Project interventions | Value | 0.00 | 4318.00 | 30000.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
A public online system for continuous monitoring of water quality and flow in the Ganga and selected tributaries is functional | Value | No | No | Yes |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Number of STPs constructed or rehabilitated under the Project which meet the national discharge standards at least 95 percent of the time | Value | 0.00 | 4.00 | 12.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
A system for more detailed water balance tracking in key reaches is developed and implemented to guide operational flow regime optimization | Value | No | No | Yes |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Share of core staff positions filled in each implementing agency maintained above 80% at any point in time | Value | 80.00 | 85.00 | 90.00 |
Date | September 1, 2023 | February 29, 2024 | December 31, 2026 | |
Comment |
Wastewater treatment capacity created under the Project | Value | 0.00 | 247.00 | 865.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Detailed assessment of environmental flow options for all impacted river reaches completed, documented and disseminated | Value | No | No | Yes |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Volume of wastewater treated due to Project interventions | Value | 0.00 | 112.00 | 800.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Number of ULB with an integrated city-wide sanitation plan informed by a GIS and roadmap for financing long-term operation and maintenance approved by the ULB | Value | 0.00 | 0.00 | 2.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Number of facilities setup for fecal sludge treatment under the Project | Value | 0.00 | 0.00 | 5.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Percentage of female staff in NMCG and state-wise EAs | Value | 4.30 | 30.30 | 20.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Number of water quality monitoring stations generating real-time data | Value | 44.00 | 40.00 | 150.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Share of grievances redressed within 30 days of receipt | Value | 80.00 | 100.00 | 90.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
No of km of network laid under the Project | Value | 0.00 | 390.00 | 900.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
No of house connections delivered under the Project | Value | 0.00 | 92455.00 | 245000.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Number of States which have a roadmap for sustained O&M sanitation assets beyond the timeframe funded by Central Government | Value | 0.00 | 0.00 | 1.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |
Number of mass media campaigns implemented to promote behavior change | Value | 0.00 | 2.00 | 4.00 |
Date | July 21, 2020 | February 29, 2024 | December 31, 2026 | |
Comment |