Financier | Commitments |
---|---|
IBRD Guarantee | 50.00 |
International Bank for Reconstruction and Development | 70.70 |
Borrower/Recipient | 2.00 |
P169117
Active
Florian Kitt
Georgia
November 28, 2018
(as of board presentation)
May 23, 2019
November 28, 2019
US$ 172.70 million
Georgian State Electrosystem
2019
US$ 70.70 million
N/A
February 28, 2024
December 31, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IBRD Guarantee | 50.00 |
International Bank for Reconstruction and Development | 70.70 |
Borrower/Recipient | 2.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 70.70 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 70.70 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 172.70 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 11, 2023 | IBRD-89520 | Loan Disb | 1,231,881.00 |
Oct 25, 2022 | IBRD-89520 | Loan Disb | 492,579.60 |
Jan 25, 2023 | IBRD-89520 | Loan Disb | 231,587.94 |
Feb 14, 2023 | IBRD-89520 | Loan Disb | 1,012,762.56 |
Feb 14, 2024 | IBRD-89520 | Loan Disb | 349,196.62 |
Feb 12, 2024 | IBRD-89520 | Loan Disb | 323,085.00 |
Jan 2, 2024 | IBRD-89520 | Loan Disb | 1,539,014.50 |
May 23, 2019 | IBRD-89520 | Loan Commitment | 70,700,000.00 |
Oct 30, 2023 | IBRD-89520 | Loan Disb | 244,842.81 |
Dec 27, 2023 | IBRD-89520 | Loan Disb | 2,880,378.00 |
Nov 15, 2023 | IBRD-89520 | Int Charges | 147.61 |
Nov 15, 2023 | IBRD-89520 | Int Charges | 1,971.67 |
Nov 15, 2023 | IBRD-89520 | Int Charges | 50,265.42 |
Nov 15, 2023 | IBRD-89520 | Int Charges | 684,983.50 |
Dec 18, 2023 | IBRD-89520 | Loan Disb | 247,913.61 |
May 15, 2023 | IBRD-89520 | Int Charges | 3,163.27 |
May 15, 2023 | IBRD-89520 | Int Charges | 54,765.53 |
May 15, 2023 | IBRD-89520 | Int Charges | 412,176.80 |
May 15, 2023 | IBRD-89520 | Int Charges | 983.04 |
Aug 26, 2024 | IBRD-89520 | Loan Disb | 446,860.00 |
Feb 5, 2024 | IBRD-89520 | Loan Disb | 250,043.12 |
Jul 18, 2024 | IBRD-89520 | Loan Disb | 1,479,091.90 |
Jun 27, 2024 | IBRD-89520 | Loan Disb | 429,874.72 |
May 21, 2024 | IBRD-89520 | Loan Disb | 1,493,783.90 |
May 15, 2024 | IBRD-89520 | Int Charges | 27.45 |
May 15, 2024 | IBRD-89520 | Int Charges | 516.14 |
May 15, 2024 | IBRD-89520 | Int Charges | 43,506.17 |
May 15, 2024 | IBRD-89520 | Int Charges | 867,837.60 |
Dec 29, 2020 | IBRD-89520 | Loan Disb | 2,052,056.90 |
Aug 21, 2020 | IBRD-89520 | Loan Disb | 590,150.00 |
Nov 17, 2020 | IBRD-89520 | Loan Disb | 805,909.20 |
Nov 17, 2020 | IBRD-89520 | Loan Disb | 2,810,479.20 |
May 15, 2020 | IBRD-89520 | Int Charges | 715.75 |
May 15, 2020 | IBRD-89520 | Int Charges | 124,494.31 |
Nov 28, 2019 | IBRD-89520 | Loan Disb | 170,546.50 |
Nov 28, 2019 | IBRD-89520 | Fee Charges | 170,546.50 |
May 31, 2022 | IBRD-89520 | Loan Disb | 1,057,146.60 |
Nov 15, 2021 | IBRD-89520 | Int Charges | 79,553.43 |
Nov 15, 2021 | IBRD-89520 | Int Charges | 29,372.38 |
May 15, 2022 | IBRD-89520 | Int Charges | 69,831.00 |
May 15, 2022 | IBRD-89520 | Int Charges | 28,465.52 |
Apr 22, 2022 | IBRD-89520 | Loan Disb | 1,757,025.90 |
Jul 5, 2022 | IBRD-89520 | Loan Disb | 440,908.53 |
Nov 15, 2021 | IBRD-89520 | Loan Disb | 497,602.30 |
Nov 15, 2021 | IBRD-89520 | Int Charges | 17.19 |
Nov 15, 2021 | IBRD-89520 | Int Charges | 35.10 |
May 10, 2021 | IBRD-89520 | Loan Disb | 533,175.30 |
Nov 15, 2020 | IBRD-89520 | Int Charges | 91,512.66 |
Nov 15, 2020 | IBRD-89520 | Int Charges | 2,606.09 |
May 15, 2021 | IBRD-89520 | Int Charges | 84,479.99 |
May 15, 2021 | IBRD-89520 | Int Charges | 26,022.62 |
Jan 5, 2021 | IBRD-89520 | Loan Disb | 1,303,572.60 |
Oct 7, 2022 | IBRD-89520 | Loan Disb | 364,943.62 |
Oct 21, 2022 | IBRD-89520 | Loan Disb | 1,774,264.80 |
Oct 5, 2022 | IBRD-89520 | Loan Disb | 1,024,720.44 |
Oct 5, 2022 | IBRD-89520 | Loan Disb | 410,166.70 |
Dec 1, 2022 | IBRD-89520 | Loan Disb | 438,491.94 |
Nov 15, 2022 | IBRD-89520 | Int Charges | 266.46 |
Nov 15, 2022 | IBRD-89520 | Int Charges | 511.57 |
Nov 15, 2022 | IBRD-89520 | Int Charges | 65,720.41 |
Nov 15, 2022 | IBRD-89520 | Int Charges | 61,980.33 |
Nov 9, 2022 | IBRD-89520 | Loan Disb | 357,315.44 |
Dec 23, 2022 | IBRD-89520 | Loan Disb | 5,214,073.50 |
Dec 28, 2022 | IBRD-89520 | Loan Disb | 1,002,546.00 |
Dec 21, 2021 | IBRD-89520 | Loan Disb | 366,803.94 |
Aug 25, 2022 | IBRD-89520 | Loan Disb | 707,230.44 |
Jun 28, 2022 | IBRD-89520 | Loan Disb | 345,650.56 |
Jun 28, 2022 | IBRD-89520 | Loan Disb | 227,581.90 |
May 25, 2023 | IBRD-89520 | Loan Disb | 642,690.70 |
Aug 22, 2023 | IBRD-89520 | Loan Disb | 994,206.60 |
Dec 29, 2022 | IBRD-89520 | Loan Disb | -1,001,645.30 |
Mar 15, 2023 | IBRD-89520 | Loan Disb | 266,938.80 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2024-10-22 |
Project Management | Moderately Unsatisfactory | 2024-10-22 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-10-22 |
Financial Management | Satisfactory | 2024-10-22 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2024-10-22 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-10-22 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of end-user outages caused by failures of 500 kV OHLs in the western part of Georgia | Value | 4.00 | 2.00 | 0.00 |
Date | December 31, 2018 | December 31, 2022 | December 31, 2025 | |
Comment |
End of GSE rehabilitation regime | Value | No | Yes | Yes |
Date | December 31, 2018 | February 28, 2024 | September 30, 2020 | |
Comment |
Long-term commercial financing mobilized | Value | 0.00 | 0.00 | 100000000.00 |
Date | December 31, 2018 | December 31, 2023 | December 31, 2025 | |
Comment |
Average annual duration of end-user outages caused by failures of 500 kV OHLs in the western part of Georgia | Value | 161.00 | 24.00 | 0.00 |
Date | December 31, 2018 | December 31, 2022 | December 31, 2025 | |
Comment |
Reduction of cash deficit of GSE | Value | 3064460.00 | 0.00 | 0.00 |
Date | December 31, 2017 | December 31, 2023 | June 30, 2021 | |
Comment |
Improved decision-making on new investments in power transmission network as a result of institutional strengthening | Value | New investments in power transmission network are | New investments in power transmission network are | New investments in power transmission network are |
Date | December 31, 2018 | December 31, 2023 | December 31, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Jvari-Tskaltubo 500 kV OHL constructed | Value | 0.00 | 0.00 | 77.00 |
Date | December 31, 2018 | July 31, 2023 | December 31, 2025 | |
Comment |
Adequately staffed Environmental and Social Unit is established and maintained at GSE | Value | No | Yes | Yes |
Date | December 31, 2018 | July 31, 2023 | December 31, 2019 | |
Comment |
Closure of the transaction to raise commercial financing | Value | No | No | Yes |
Date | December 31, 2018 | July 31, 2023 | December 31, 2025 | |
Comment |
500/220 kV Tskaltubo substation constructed | Value | No | No | Yes |
Date | December 31, 2018 | July 31, 2023 | December 31, 2025 | |
Comment |
Mechanism is introduced to reduce or eliminate exposure of GSE to FX risks | Value | No | No | Yes |
Date | December 31, 2018 | July 31, 2023 | December 31, 2025 | |
Comment |
GSE is issued a credit rating by an international reputable rating agency | Value | No | No | Yes |
Date | December 31, 2018 | July 31, 2023 | December 31, 2025 | |
Comment |
Percentage of grievances recorded by the Project and resolved within a two-week period | Value | 0.00 | 100.00 | 100.00 |
Date | December 31, 2018 | July 31, 2023 | December 31, 2025 | |
Comment |
Percentage of citizens who believe that the project has established effective engagement processes | Value | 0.00 | 90.00 | 75.00 |
Date | December 31, 2018 | July 31, 2023 | December 31, 2025 | |
Comment |
Increase in demand for gender-based violence support services in project regions | Value | 0.00 | 0.00 | 10.00 |
Date | December 31, 2018 | July 31, 2023 | December 31, 2025 | |
Comment |